Effort estimation trial ledger

Cycle v3/board_thumbnails

2026-11-05T17:45:00Z — standing P2 enrollment, one-shot; canonical record. Scope v1: thumbnails for image posts on board list rows and Recent rows (PF-20261104-F60). Baseline 822d6134692883e145728db96b1a9aa62f1ca496; R1 hashes not re-verified; extended/debug enabled. Intake 0.50 recorded before attachment and listing code were inspected (board templates seen earlier the same day). Closeout retrospective scope assessment 0.40, single exposed Claude rater. Smoke plus changed tests passed; 13 themes at phone and desktop checked locally; full suite and live check pending. Maintainer comfortable-fit and acceptance pending; no accepted-count change.

Cycle v3/deploy_pending_commits

2026-11-05T15:05:00Z — v3/deploy_pending_commits closeout: record. Delivered scope v1 in full on feat/deploy-pending-commits; projection 0.20 reaffirmed at entry and closeout; retrospective scope assessment 0.20, single exposed Claude rater, not independent. Smoke set plus changed tests 457/457; five themes at phone and desktop rendered; full suite not run. Feedback item PF-20261104-F49 updated. Maintainer comfortable-fit and acceptance pending; no accepted-count change.

2026-11-05T14:45:00Z — standing P2 enrollment, one-shot; canonical record. Scope v1: the Deploy page lists incoming commits, change size and local-edit overlap after a check, and the queued button says it is queued and how long it has waited. Baseline 058b2c6b069e023802871aa141f570a6407217a5; R1 hashes not re-verified; extended/debug enabled. Pristine intake missing because source inspection preceded rating; intake projection 0.20, single exposed Claude rater. No accepted-count change.

Cycle v3/adaptive_nav

2026-11-05T07:40:00Z — v3/adaptive_nav Step 4 closeout (Stage 8 pending): Stage 3 approved; planning 8fe60a2a, stage commits through 5e670104 plus the Stage 8 commit on feat/adaptive-nav, unmerged. Closeout. Entry 0.85 preserved; separate retrospective scope assessment 0.90 (single exposed Claude rater). Seven of eight stages complete; headless release matrix passed; iPhone replay, deployment and full suite pending. Maintainer comfortable-fit judgment and acceptance pending; no accepted-count change.

2026-11-05T05:05:00Z — v3/adaptive_nav Step 3 handoff: Step 2 v2 approved. Plan/checkpoint reaffirms whole-cycle 0.85, same v2/baseline a24e16df/R1/P2, single exposed Claude rater. Eight stage-work originals 0.08/0.12/0.08/0.14/0.14/0.08/0.08/0.13, non-additive: desktop split, phone bar and More, unread on More, slot markup and pre-paint, filling and pinning, refresh survival, icons and concepts, release check with iPhone replay. Await Approved Step 3; planning uncommitted.

2026-11-05T04:50:00Z — v3/adaptive_nav Step 2 handoff: Step 1 approved (Option B). Description/checkpoint. Scope v2 (Messages indicator on More, slot repair after flag refresh, iPhone acceptance). Same baseline a24e16df/R1/P2, single exposed Claude rater. Projected total 0.80 → 0.85, reason new code understanding. Await Approved Step 2; planning uncommitted.

2026-11-05T04:40:00Z — v3/adaptive_nav Step 1 handoff (standing P2 enrollment, no parent): assessment/checkpoint. Scope v1, recommended Option B (wider desktop bar, fixed phone bar with a More page, self-filling sticky phone slots). Starting revision a24e16df, R1/P2; R1 hashes not re-verified. Single exposed Claude rater. Intake and projected total 0.80; option estimates 0.45/0.80/0.60, non-additive. Await Approved Step 1; planning uncommitted.

Cycle v3/chicago_post_actions

2026-11-04T20:26:52Z — closeout checkpoint: one-shot record. Scope v1 implemented on fix/chicago-post-actions; requested actual-thread Chicago/Word97 style matrix passed at phone/desktop widths, including pressed bevels, and focused tests passed 2/2. Projection 0.15 reaffirmed; retrospective cycle scope 0.15, single exposed Codex rater, not independent. Smoke branch 325/425 versus unchanged-main 323/423 with the identical 100 environment failures. Linux signed-save acceptance, review, merge, deployment and maintainer acceptance remain pending; no accepted-count change.

2026-11-04T20:15:47Z — standing P2 enrollment, one-shot; canonical record. Scope v1: carry the two referenced Word97 post-action repairs into Chicago, with UI typography/no underline and Like/Flag-only padding plus soft raised/pressed bevel. Baseline 8bc40af67d14c3b76f8ec057edac1bc084a151be; exact R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because request-thread, commit, stylesheet and markup inspection preceded rating; intake and execution-entry projection 0.15, single exposed Codex rater. Parent/request item PF-20261104-F66; no accepted-count change.

Cycle v3/calendar

2026-11-05T01:40:00Z — v3/calendar: maintainer judged the delivered cycle a comfortable fit for one cycle (retrospective 1.00, projection 0.90). Study acceptance stays pending until the production rebuild and invite-link replay are recorded; no accepted-count change.

2026-11-05T01:30:00Z — v3/calendar Step 4 closeout: eight stages delivered on feat/calendar and merged to main at the maintainer's request; production rebuild and invite-link replay not done before merge. Closeout. Projection 0.90 retained; cycle retrospective assessment 1.00 (single exposed Claude rater); maintainer comfortable-fit judgment and study acceptance pending.

2026-11-04T20:30:00Z — v3/calendar: after merging main (work tracking removed upstream), references in Steps 1–3 repaired to the thread title directive precedent; Stage 2 adds a replay of feedback item PF-20261104-B10. Scope v3/A and 0.90 unchanged; no approval or implementation.

2026-11-04T18:20:00Z — v3/calendar: maintainer explicitly requested merging Steps 1–3, the debug log and this ledger into main before Step 3 approval; mockup excluded. No approval, implementation or accepted-count change; 0.90 unchanged.

2026-11-04T18:00:00Z — v3/calendar Step 3 handoff: Step 2 v3 approved. Plan/checkpoint reaffirms whole-cycle 0.90, same v3/A/original baseline/R1/P2, single exposed Claude rater. Eight stage-work originals 0.08/0.12/0.12/0.12/0.20/0.14/0.08/0.12, non-additive: end-date header, write path and composer, read model and event block, event state directive, grid pages, day page, docs and concepts, release verification with production replay. Await Approved Step 3; planning uncommitted.

2026-11-04T17:20:00Z — v3/calendar Step 2 v3 addition before handoff: per-tag calendars at /calendar/<tag> with day pages presetting the tag, matched like tag pages. Whole-cycle 0.85 → 0.90; earlier values preserved. Same baseline/A/R1/P2, single exposed Claude rater. Await Approved Step 2; planning uncommitted.

2026-11-04T17:00:00Z — v3/calendar Step 2 v3 handoff: maintainer asked for a general calendar used also for couch stays. Checkpoint: /calendar as a month view over all event threads with navigation, day page adding an event through the shared composer, additive Event-End-Date, operator-only event: confirmed/declined directive (root lines count), declined events leave the grid, instance access rule reused, 60-day horizon as default view only. Whole-cycle 0.80 → 0.85; v1 0.65 and v2 0.80 preserved. Same original baseline/A/R1/P2, single exposed Claude rater. Await Approved Step 2; no implementation or accepted-count change; planning uncommitted.

2026-11-04T16:05:00Z — v3/calendar Step 2 v2 handoff: maintainer agreed to add offline marking (operator's own claim with the claim: approved line, root lines count) and night ranges via an additive inclusive Event-End-Date root header with whole-stay approval. Checkpoint revises whole-cycle 0.65 → 0.80 for the format addition, one read-model column with version bump, spec, prior-version rebuild test, composer field and event block span; v1 0.65 preserved. Same original baseline/A/R1/P2, single exposed Claude rater. Await Approved Step 2; no implementation or accepted-count change; planning uncommitted.

2026-11-04T14:45:00Z — v3/calendar clarification: the maintainer is the one being hosted and members are the hosts; Step 1 Understood Intent (Revision 1) and Step 2 wording corrected, optional Event-Location reused for the couch's place. Model, scope v1/A and 0.65 unchanged. Still awaiting Approved Step 2; planning uncommitted.

2026-11-04T14:30:00Z — v3/calendar Step 2 handoff: user explicitly approved Step 1 Option A. Description/checkpoint defines claims as calendar event threads through the shared composer, operator-only claim: reply directive, derived day state over a 60-day window, approved-viewer gating of both pages, event-support flag dependency. Whole-cycle 0.65 reaffirmed; same v1/A/original baseline/R1/P2, single exposed Claude rater. Navigation entry, notifications and write-time exclusivity out of scope. Await Approved Step 2; no implementation or accepted-count change; planning uncommitted.

2026-11-04T14:10:00Z — standing P2 enrollment; canonical Step 1 checkpoint. No parent. Scope v1/A: /calendar month grid for the next 60 days, per-day claim page posting an event thread through the shared composer, host approval by reply directive, approved-member access, theme/phone verification and docs. Baseline f41f656936e740809242a5d8e1c646068afddc28; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because source inspection preceded rating; Step 1 projection 0.65, alternatives B 0.45, C 1.00, single exposed Claude rater. Work item thread-20261104140509-96d1a44620809fe0e869364bdb42ca53 created and claim posted (pending identity approval). No approval, implementation or accepted-count change; planning uncommitted.

2026-11-04T19:55:00Z — v3/source_repository_link closeout: record. Delivered scope v1 in full on feat/source-repository-link; projection 0.12 reaffirmed at entry and closeout; retrospective scope assessment 0.12, single exposed Claude rater, not independent. Smoke set plus changed tests 442/442; full suite not run. Feedback item PF-20261104-F27 found after implementation and updated. Maintainer comfortable-fit and acceptance pending; no accepted-count change.

2026-11-04T19:41:02Z — standing P2 enrollment, one-shot; canonical record. Scope v1: FORUM_SOURCE_REPOSITORY_URL (default https://github.com/gulkily/v3) shown in /llms.txt and the /api/ index so agents can find the code without crawling. Baseline e83cb201ae45b900a8d260708081a02f920ccf32; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because source inspection preceded rating; intake projection 0.12, single exposed Claude rater. No accepted-count change.

Cycle v3/delete_record_speed

2026-11-04 — v3/delete_record_speed Step 4 local closeout: Step 3 explicitly approved; branch feat/delete-record-speed, planning 0429d64 and five stage commits. Summary/closeout. Same v2/D/baseline/R1/P2, single exposed Claude rater. Whole-cycle 0.65 at entry; revised 0.80 at Stage 4 (new understanding: no incremental removal existed, same scope); retrospective scope assessment 0.85. Stage originals 0.10/0.18/0.12/0.20/0.08; S4 revised 0.35; retrospectives 0.10/0.15/0.14/0.35/pending; non-additive. Local: inspect 0.04s, delete 0.43s on a 310k-file repository; equivalence with rebuild across nine scenarios; smoke plus touched tests pass, full suite not run. Host acceptance on qdb.us and maintainer comfortable-fit judgment pending; no measured labor or accepted-count increment.

2026-11-04T17:55:00Z — v3/delete_record_speed Step 3 handoff: user explicitly approved Step 2. Plan/checkpoint five stages: status lines and host timing, label-path index (schema 47→48), single-index-read commit, incremental removal with targeted invalidation, host acceptance. Whole-cycle 0.60 → 0.65 (about a dozen git processes per delete). Stage-work originals 0.10/0.18/0.12/0.20/0.08, non-additive. Same v2/D/baseline/R1/P2, single exposed Claude rater. Await Approved Step 3.

2026-11-04T17:45:00Z — v3/delete_record_speed Step 2 handoff: user explicitly approved Step 1 Option D. Step 2 checkpoint defines proportional inspect/delete under 1s on the qdb host including startup, live per-step status, rebuild-equivalent result, unchanged delete receipt, rerun recovery. Whole-cycle 0.55 → 0.60 (schema regression test, old-schema fallback, host timing stage). Same v2/D/baseline/R1/P2, single exposed Claude rater. Await Approved Step 2; no implementation or accepted-count change.

2026-11-04T17:40:00Z — v3/delete_record_speed Step 1 revision: maintainer asked for instant deletion. Revised assessment scope v2/D: proportional delete (path-indexed labels, plumbing commit, one-transaction read-model update, targeted invalidation, per-step status). Projection 0.55; v1/A 0.75 preserved; B 0.40/C 0.90 reaffirmed, non-additive. Same baseline/R1/P2, single exposed Claude rater. Not Approved Step 1.

2026-11-04T17:30:18Z — standing P2 enrollment; canonical Step 1 checkpoint. Scope v1/A: delete-record inspect and delete under 1s on the qdb host with per-phase status lines; indexed label lookup, incremental removal with targeted page invalidation, full rebuild kept as recovery. Baseline ea306fc03b3152a2e66b3d2a75b13d7d1c4064bc; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because source inspection preceded rating; Step 1 projection 0.75, alternatives B 0.40, C 0.90, single exposed Claude rater. No implementation, measured labor or accepted-count change; await Approved Step 1. Committed and pushed before approval at the session stop hook's request; no approval implied.

Cycle v3/parallel_tests

2026-11-04T13:30:00Z — standing P2 enrollment, one-shot; record. Follows v3/smoke_tests; revisits Option B of superseded v3/fast_default_tests. Scope v1: --jobs=N parallel runner with duration-ordered scheduling, ./v3 fulltest, docs. Baseline e291a20b; extended/debug enabled. Pristine intake missing; execution-entry projection 0.45, closeout retrospective 0.45, single exposed Claude rater. Full parallel run pending with the maintainer. No accepted-count change.

Cycle v3/smoke_tests

2026-11-04T12:40:00Z — standing P2 enrollment, one-shot; record. Builds on v3/fast_default_tests_outliers (PR #15). Scope v1: curated smoke set as the default run, --smoke plus named tests per task, full suite as a periodic maintainer run, process in AGENTS/CONTRIBUTING. Baseline 9459c7479c54f28a6d38c060a4a5293d9d6fb48c; extended/debug enabled. Pristine intake missing; execution-entry projection 0.35, closeout retrospective 0.35, single exposed Claude rater. No accepted-count change.

Cycle v3/preexisting_test_failures

2026-11-04T12:30:00Z — standing P2 enrollment, one-shot; record. Related v3/fast_default_tests_outliers. Scope v1: make the 15 tests failing on main pass without product changes. Baseline 8dac3f9cfda4a1e8833a3072ce47414b1ef21b73; extended/debug enabled. Pristine intake missing because diagnosis preceded rating; execution-entry projection 0.30, single exposed Claude rater. No accepted-count change.

Cycle v3/fast_default_tests_outliers

2026-11-04T04:50:00Z — standing P2 enrollment, one-shot; record. Parent v3/fast_default_tests (parked Step 1, unchanged). Scope v1: remove waste from the three slowest test classes without reducing assertions. Baseline 8dac3f9cfda4a1e8833a3072ce47414b1ef21b73; extended/debug enabled. Pristine intake missing because profiling preceded rating; execution-entry projection 0.30, single exposed Claude rater. No accepted-count change.

Cycle v3/work_page

2026-11-04T02:13:36Z — standing P2 enrollment; canonical Step 1 checkpoint. Parent v3/work_tracking. Scope v1/B: dedicated /work page with status filters and search, thread status buttons for approved members, navigation entry and theme icons. Baseline 78d0261b1a729339dbeb8e042e7f463bf7c3ca78; R1 hashes verified earlier the same session; extended/debug enabled. Pristine intake missing; Step 1 projection 0.55, alternatives A 0.30, C 0.20, single exposed Claude rater. Committed and pushed before approval so its work item can link to it; no approval, implementation or accepted-count change.

Cycle v3/fast_default_tests

2026-11-04T12:50:00Z — superseded before Approved Step 1; closing note. The maintainer chose per-task smoke runs plus a periodic full suite, delivered by one-shot cycles v3/fast_default_tests_outliers, v3/smoke_tests and v3/preexisting_test_failures. No implementation, accepted outcome or retrospective score for this cycle; Step 1 projection 0.75 retained.

2026-11-04T02:07:00Z — standing P2 enrollment; canonical Step 1 checkpoint. Scope v1/A+B: fast default tier with skip-not-fail for unavailable tools, plus a parallel runner; full suite stays mandatory before merge. Baseline ed5cbc07ddcf8810bfe35d23c4bd3d82f062e9ae; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because timing inspection preceded rating; Step 1 projection 0.75, alternatives A 0.35, B 0.60, C 0.85, D 0.50, single exposed Claude rater. Maintainer authorized committing and pushing Step 1 before approval; no approval, implementation or accepted-count change.

Cycle v3/work_tracking

2026-11-04T00:55:14Z — v3/work_tracking Step 4 entry: Approved Step 3; branch feat/work-tracking, planning commit be2990e. Summary reaffirms whole-cycle 1.00 and eight stage-work originals, same v2/A/baseline/R1/P2, single exposed Claude rater. Implementation proceeds stage by stage; no accepted-count change.

2026-11-04T00:49:31Z — v3/work_tracking Step 3 handoff: user explicitly approved Step 2. Plan/checkpoint (source unavailable) revises whole-cycle 0.95 → 1.00 (status as reply directive because agent labels are add-only; application-update post-back hook); scope v2/A unchanged. Eight stage-work originals 0.15/0.12/0.15/0.06/0.12/0.15/0.12/0.10, non-additive. Same baseline/R1/P2, single exposed Claude rater. Await Approved Step 3; planning uncommitted.

2026-11-04T00:46:46Z — v3/work_tracking Step 2 handoff: user explicitly approved Step 1 Option A with Revision 1 (export). Step 2 checkpoint (source unavailable) defines one status per item thread, claim with staleness and local fallback, plain-text lookup, generated Markdown export, sweep and post-back, ten-item pilot. Whole-cycle 0.95 reaffirmed; same v2/A/baseline/R1/P2, single exposed Claude rater. Await Approved Step 2; no implementation or accepted-count change.

2026-11-04T00:41:32Z — v3/work_tracking Step 1 revision: maintainer requested a scheduled site-to-repo export and prior-art review (Lobsters, Tildes). Revised assessment (source unavailable) scope v2/A adds the export file and claim staleness; projection 0.95, v1 0.85 preserved, B 0.70/C 0.45 reaffirmed, non-additive. Same baseline/R1/P2, single exposed Claude rater. Not Approved Step 1; no implementation or accepted-count change.

2026-11-03T23:03:34Z — standing P2 enrollment; canonical Step 1 checkpoint (source unavailable). Scope v1/A: claim and status home in ZenMemes item threads with local fallback, claim-before-start agent rule, inbox sweeps, automatic and batch post-back, ten-item pilot; reconciliation of existing sources excluded as a follow-up cycle. Baseline 561f7dd1113c3021ba0d7d1b28361865c40de2e2; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because inspection preceded rating; Step 1 projection 0.85, alternatives B 0.70 and C 0.45, single exposed Claude rater. No parent/replacement, implementation, measured labor or accepted-count increment; await Approved Step 1. Committed and pushed before approval at the session stop hook's request; no approval implied.

Cycle v3/fastmod_ownership

2026-11-03T17:24:49Z — Step 1 Option A explicitly approved; Step 2 checkpoint defines opt-in selection, claim probability, supported name/unknown, shared scoring/post/transfer behavior and exact local URL acceptance plus retry. Whole-cycle 0.65 reaffirmed, same v1/A/baseline/R1/P2 and exposed single Codex rater; three frozen hashes reverified. Prior intake remains missing and Step 1 estimate retained. No runtime work, measured labor or accepted-count increment; await Approved Step 2. User authorized merging the current tree on 2026-11-03; publication does not approve Step 2 or implementation.

2026-11-03 UTC — standing P2 enrollment; canonical Step 1 checkpoint. Scope v1/A: selectable authorship-claim probability and most likely claimed name/unknown through existing Fastmod scoring, storage, ordinary display, transfer and retry recovery. Baseline 622bb4fa6fce203e0edf0416a6bc3d6824e9a736; R1 three frozen hashes verified; extended/debug enabled. Pristine intake missing because source inspection preceded rating; Step 1 whole-cycle projection 0.65, alternative B 0.85, single exposed Codex rater. No parent/replacement, implementation, measured labor, independent rating or accepted-count increment; maintainer acceptance pending. Await Approved Step 1; user explicitly authorized plan merge/push on 2026-11-03, without implementation approval. Worktree copies share this stable ID.

Cycle v3/activity_load_performance

2026-10-28 Step 4 local closeout: canonical entry/stages/outcome. Step 3 explicitly approved; branch feat/activity-load-performance, planning 2028f6d3a and seven stage commits. Same v3/C/original baseline/R1/P2/single exposed Codex rater; entry 0.95 reaffirmed, no prospective revision, separate retrospective scope 1.00. Stage originals 0.08/0.18/0.18/0.15/0.10/0.12/0.15; retrospectives unchanged except S7 0.20, non-additive. Final focused 54/54 plus browser/HTTP/recovery checks pass; broader runs have four baseline failures documented separately, not a full-suite pass. Both views read compact evidence/totals; schema 36, transactional updates/rebuild recovery, zero dependency delta. Production/deployment, physical devices and maintainer acceptance pending; no measured labor, independent rating or accepted-count increment. Prior snapshots retained; deduplicate worktree copies.

2026-10-27T23:15:13Z Step 3 handoff: Step 2 approved. Plan/checkpoint retains v3/C, original baseline/R1/P2/single exposed Codex rater; frozen hashes reverified. Whole-cycle 0.95 reaffirmed; seven stage-work originals 0.08/0.18/0.18/0.15/0.10/0.12/0.15, non-additive. Direct flag/handoff writers and existing signature index now included; no added scope. Seven planned/zero implemented; await Approved Step 3. Production acceptance remains separate; no commit, deployment, measured labor or accepted-count increment.

2026-10-27T23:07:52Z Step 2 handoff: user explicitly approved Step 1 Option C and storage estimate. Step 2 retains scope v3/C, baseline/R1/P2/exposed rater; 0.95 total reaffirmed. Both ordinary Activity flows read precomputed evidence/counts, with targeted updates, interruption/rebuild recovery, controlled latency targets and actual production acceptance distinguished from local tests. Storage 0.25–1 KB/event is an accepted estimate, not a guaranteed cap. Await Approved Step 2; no implementation, deployment, measured labor or accepted-count change. Prior snapshots below retained.

2026-10-27T23:04:17Z revision: user requested the precompute-on-indexing direction in Step 1. Scope v3/C narrows earlier C to the existing Activity read model for both lists, selected evidence and maintained counts, with targeted change handling and rebuild/interruption recovery; no new page-artifact system. Projection 0.95; A 0.45/B 0.85 reaffirmed. Prior C 1.25 and B 0.85 preserved. Same baseline/R1/P2/exposed rater, frozen hashes reverified; no implementation, approval to advance or accepted outcome.

2026-10-27T22:57:57Z revision: user also reports Forte slowness; Step 1 scope v2/B now covers both views, Forte counts/selected detail and normal sort/append/selection recovery. Projection 0.85; option A/B/C v2 0.45/0.85/1.25, non-additive. Original v1 snapshots below retained. Same baseline/R1/P2/exposed rater. Two fast anonymous Forte samples do not reproduce intermittent delay. Still awaiting Step 1 approval; no implementation or accepted outcome.

Status: Step 1 proposed; standing P2 enrollment; scope v1/B, R1; baseline 7ef735dd21b3329f18716bf3d5484baab2b2b71b. Canonical checkpoint: Step 1 handoff, 2026-10-27T22:40:15Z; first projection 0.70. Pristine intake missing; source inspection preceded rating. All three frozen R1 hashes verified; Codex single exposed rater, extended estimates enabled. Alternative whole-cycle A/B/C 0.40/0.70/1.15, non-additive; C requires split discussion. Scope: Measure production Activity costs and bound dominant list/evidence/pagination work, preserving access, signatures, cursor and missing-evidence recovery, with browser/performance verification and documentation. Related manifest-size fix remains separate completed work; no parent split outcome. Outcome: Investigation and planning only; await Approved Step 1. No application implementation, deployment, dependencies, commit, measured labor or accepted-count increment; maintainer acceptance pending. Deduplicate worktree copies by stable ID. Planning/ledger remain uncommitted.

Cycle v3/retraction_text_format

2026-10-25 UTC — standing P2 enrollment; canonical intake and Step 1 snapshots. Baseline 2a07313a738af9e0a0f15796e8155d301d949ed5, R1 exact three hashes verified, Codex single exposed rater. Intake v1 0.70 included historical retraction compatibility; user explicitly removed that requirement. Step 1 v2 0.45 for new readable retractions, associated policy/audit, normal-flow/trust/retry verification and documentation. Extended options A/v1 0.45, B/v1 0.60, not additive or measured effort. Related predecessor v3/retraction_simplification retains its own outcome. Guidance and source audit completed directly; rewrite awaits Approved Step 1. Debug/extended estimates enabled; no application implementation, maintainer acceptance or accepted-count increment. Planning and ledger remain uncommitted.

2026-10-25 UTC — Step 1 selection revision: user chose Option B. Canonical selection and snapshot records scope v3, 0.60 projected total for separate signed request/signature and text acceptance receipt with atomic deletion/recovery. Earlier v1 0.70 and v2 0.45 retained; B/v1 0.60 reaffirmed. Old retractions remain excluded. Same baseline/R1/P2/exposed rater; exact hashes reverified, no implementation, measurement or acceptance. Await Approved Step 1.

2026-10-25 UTC — Step 2 handoff: Step 1 Option B explicitly approved. Requirements and canonical checkpoint retain scope v3/original baseline/R1/P2 and 0.60 total reaffirmed. Three readable files, exact signed evidence, atomic deletion/retry, source/read-model/import/cleanup integration; previous retractions excluded. Exact R1 hashes verified; single exposed Codex rater, no measured effort, implementation or accepted outcome. Audit priorities remain separate from effort scores. Await Approved Step 2; planning/ledger uncommitted.

2026-10-25 UTC — Step 3 handoff: Step 2 explicitly approved. Six-stage plan/checkpoint retains v3/Option B/original baseline/R1/P2, 0.60 whole-cycle projection reaffirmed. S1–S6/v1 stage work: 0.15, 0.20, 0.15, 0.20, 0.10, 0.15, independently scoped and not additive; S6 owns shared acceptance. Exact R1 hashes verified. Codex single exposed rater; source inspection identified request-path collisions, extension-based imports and shared source-removal migration within approved scope. Six planned/zero completed stages; no measured labor, implementation or acceptance. Await Approved Step 3; planning/ledger uncommitted.

2026-10-25 UTC — Step 4 closeout: entry, six stages and outcome. Step 3 explicitly approved; branch feature/retraction-text-format, scope v3/Option B/original baseline/R1/P2 retained. 0.60 original projection; 0.70 retrospective scope assessment, single exposed Codex rater, exact R1 hashes verified. Planning 75ec624b and six stage commits; six of six stages complete locally. New detached request/signature and text receipt, atomic recovery, source/import/cleanup integration, concise policy and prioritized audit delivered. Final PHP regressions 117/117, signed API/source 16/16, strengthened export/replay 1/1, actual browser four scenarios/13 themes and keyboard/touch checks passed. Stage-work originals preserved; S6 retrospective 0.20, others unchanged. No measured labor or accepted-count increment; maintainer fit/acceptance, physical devices, full suite, merge/push/deployment pending or unverified. Zero dependencies. Previous retractions excluded; other JSON conversions/history purge not implemented.

Cycle v3/read_model_hot_indexes

2026-10-24 Step 4 closeout: standing P2 enrollment, scope v1, reference R1, extended estimates enabled. Starting revision 611bcbb5; branch feat/read-model-hot-indexes; planning commit 7f928218; stage commits 4eb59792 (S1), 87fceacd (S2), cef85b1d (S3), 3a25919c (S4). Canonical snapshots in the Step 1 assessment and Step 4 summary. ≈0.30 projected total reaffirmed Steps 1–4; ≈0.30 retrospective scope assessment — independently judged, not the stage-work sum. Extended-mode stage-work originals: S1 ≈0.05, S2 ≈0.07, S3 ≈0.15, S4 ≈0.08; retrospectives S1 ≈0.05, S2 ≈0.06, S3 ≈0.12, S4 ≈0.10 (never summed into the cycle total). Delivered as planned: three read-model indexes, schema version 25→26, spec update, prior-version rebuild regression test (regression guard proven), query-plan + byte-identical-content verification, ./v3 rebuild. Two pre-existing ReadModelProvenanceTest git-environment failures reproduced on baseline 7f928218, not regressions. Single exposed, non-blind rater; no measured effort claimed. Maintainer comfortable-fit judgment and merge pending; study outcome acceptance pending (technical completion ≠ accepted outcome), accepted-count unchanged. Same stable cycle ID across checkouts.

Cycle v3/reply_continuation

2026-10-23 ordinary-flow correction accepted for merge: user explicitly authorized merging fix/reply-page-flow; combined-tree evidence records current-main integration, focused PHP 93/93 and full-card/phone browser checks. Prior scores/reference histories remain unchanged; physical/production and study comfortable-fit acceptance are not inferred.

2026-10-23 merge acceptance: user said “Looks good, you can merge” after the canonical-card correction. Functional acceptance for merge recorded in the implementation summary. Current main integrated; combined-tree 93 PHP and full-card/phone browser checks pass. Study comfortable-fit judgment, physical iPhone and production acceptance remain unknown/pending; scores and accepted-count unchanged.

2026-10-23 corrective handoff: user reported the accepted temporary card with “Open reply”; normal rendered-post reconciliation was missing from the original acceptance checks. Corrective evidence records full canonical body/actions replacement, three-engine long-content/action/draft/render-retry checks and phone four-theme visual/re-entry verification. Same cycle/scope v1/R1/P2; 0.95 projected and 0.95 retrospective assessments reaffirmed, prior incomplete acceptance retained. No independent outcome, measurement or accepted-count increment; physical iPhone/production/maintainer acceptance remain pending.

2026-10-23T14:58:10Z Step 4 local handoff: Step 3 explicitly approved; entry, six stages and closeout. Planning 22ea20c19; stages de8ae2bcb, 91f1650fd, 62f54f3dd, 9ef125447, 8a6ddaca1, followed by Stage 6 closeout. Immediate signed text/image continuation on both standard routes, desktop focus, phone reading/one-tap entry, independent pending/retry and navigation/uncertain-response recovery. Chromium all 16 theme/viewport matrices and Firefox/WebKit four-theme flows pass; focused PHP 93/93 plus existing reply/image/layout/readiness/browser checks pass. Scope v1/R1/P2/original baseline preserved; 0.95 projected total retained, 0.95 retrospective scope assessment, single exposed rater. Zero dependency delta. Physical iPhone, production/full-suite and maintainer comfortable-fit acceptance pending; no measured effort, independent rating or accepted-count increment. Same stable cycle across checkouts.

2026-10-23T14:19:17Z Step 3 handoff: Step 2 explicitly approved; development plan/checkpoint stages inline text, concurrent/reload recovery, images, dedicated/desktop flow, phone interaction and acceptance/closeout. Scope v1/R1/P2/original baseline unchanged; 0.95 total reaffirmed, Codex single exposed rater, prior reference verification carried forward. Await Approved Step 3; no implementation, measurement or accepted outcome; records uncommitted.

Standing P2 enrollment, scope v1/R1, baseline 3776264ed2ae9345294d3e93c25221037f6cd6e3; canonical intake and Step 1 snapshots, 2026-10-23T10:18:13Z: 0.95 projected total, reaffirmed at handoff. Codex single exposed rater; earlier source/test and related-plan investigation disclosed. F01 follow-up distinct from v3/reply_composer_focus_layout: immediate desktop consecutive writing and phone return-to-reading with one-tap re-entry, concurrent pending replies and per-reply recovery. Exact R1 references verified. Await Approved Step 1; no implementation, measurement or accepted outcome; planning/ledger remain uncommitted. Same stable ID across checkouts.

2026-10-23T10:22:45Z Step 2 handoff: Step 1 Option A explicitly approved; requirements/checkpoint define immediate signed text/image continuation, desktop focus, phone reading/re-entry, independent concurrent recovery/reconciliation and navigation survival; existing anonymous/no-script paths remain compatible. Scope v1/R1/P2/original baseline unchanged; 0.95 total reaffirmed, exact references reverified, single exposed rater. No implementation, measurement or accepted outcome; awaiting Approved Step 2, records remain uncommitted.

Setup plans · Your checklist

Current enrollment: protocol P2 enrolls every future cycle from 2026-10-21. Earlier individual-selection rules are historical; R1 and candidate histories remain unchanged.

Current state

Setup complete; maintainer acceptance of the provisional R1 anchor remains pending. E07 reduced scope v3 is technically complete on feat/fastmod-root-meta; maintainer comfortable-fit judgment and acceptance are pending. Original v2 was superseded after its Stage 1 sizing gate. Completed accepted outcomes: 0 / 6. The setup cycle is not a study outcome; E01–E06 remain proposed, and the additional selected E07 scope/score history is preserved below.

Frozen reference set R1

Current recovery, 2026-10-23T17:46:53.192203+00:00: the source links below now use exact verified host-local snapshots. See the portable provenance manifest. Use these frozen bytes rather than the changed current feedback or external checkout paths. Earlier unavailable checkpoints remain historical; recovery enables new dated ratings and does not backfill them.

Recorded 2026-10-19T03:20:46.805149+00:00. Definition: 1.0 is the largest well-scoped, releasable slice we would comfortably approve for one Railspike cycle, including required verification and documentation. Startup dependency recovery is the provisional 1.0 reference, conditional on its existing installer/test infrastructure. Maintainer acceptance is pending. Smaller comparisons include duplicate preview suppression (0.10), about-copy integration (0.20), numeric permalinks (0.25), score emphasis (0.30), toolbar identity (0.35) and composer decluttering (0.60).

SourceSHA-256
Calibration reportd3a30b6400b83bb25283b4234b41ba07515df9a696ea44de59c10186103771b0
Implementation diff review068b3519326e08a939df40b5abe0106ddcbab80bd796616c76b5084a21462b84
User feedbackef335604ecd5b51e5c04067d88e4d6f01cb4fdb21b8f4d7dba7b5b90e4012bfc

Frozen snapshots now live in this repository; the manifest records their original sources. If unavailable, restore these exact sources and verify hashes before rating; do not silently use changed anchors. Explicitly version any accepted replacement as R2, retaining R1 and affected score histories. The same frozen reference set applies across a batch. Local path relocation may repair links without changing content identity.

Rating protocol

  • Preserve inherited feedback scores independently of initial scoped estimates. One agent is the current rater, exposed to the feedback scores and calibration examples: results are neither blind nor independent of those sources. A second rater is optional, not assumed.

  • Rate the total scoped cycle from its starting point, including inspection, planning, implementation, required verification, documentation and ordinary correction. Exclude approval waiting and unrelated cleanup. Freeform nonnegative decimals are judgments, not elapsed hours, priority, approval, additive forecasts or measured actual effort. Values above 1.0 prompt a split discussion without waiving recovery.

  • Preserve the intake scope/estimate before detailed implementation inspection. Planning/status evidence may screen for prior work first; record prior exposure and any inspection already performed. Do not imply an initial score is uninformed by available plans.

  • Record artifact snapshots at Step 1 handoff when used, Step 2 handoff, Step 3 handoff and Step 4 entry. Explicitly reaffirm unchanged values. Append new snapshots on revisions with a reason distinguishing scope change from new understanding; never erase prior values. Preserve approval context. Implementation discoveries can trigger a new total projection before dependent work; changed scope still requires normal approvals.

  • At Step 4 closeout, record a retrospective scope assessment and the maintainer's comfortable-fit judgment separately from projections. Missing/skipped checkpoints stay missing/not applicable; do not reconstruct a prospective history. Skipped Step 1 has no zero score.

  • Each snapshot carries candidate/cycle ID, checkpoint, UTC date, rater, scope version, reference version, exposure, score, reason and artifact link. Scope versions retain outcome, required recovery, evidence, dependencies and starting Git revision.

  • Keep snapshots canonical in feature artifacts after those exist; ledger rows link to them. Intake snapshots live here until a feature exists. Updates during planning remain uncommitted under normal planning rules; include this ledger in each feature's approved documentation scope and commit its accumulated update with closeout. The optional trial does not widen any cycle's write authority.

Selection and outcome accounting

Use useful unfinished feedback first, cross-checking backlog and feature records. Six proposed scopes are a target; size diversity is a preference, not a quota. Statuses: proposed, selected, active, completed, deferred, replaced, abandoned. Keep replacements with reasons and links. Selection is not approval. Required device/environment checks must be part of the candidate's acceptance evidence.

One completed outcome is the accepted original candidate scope with required evidence and a recorded maintainer judgment. If split, preserve the original estimate/scope and link every child cycle; the original counts once only after its full agreed outcome is accepted. A deliberately reduced/replaced scope is versioned and cannot be silently compared as the original; child cycles are not independent observations by default. Missing acceptance remains visible and does not count as a completed outcome. Six completions do not imply six commits or necessarily six implementation cycles.

Outcome record template

For each candidate retain delivered scope/version; feature plan/summary links; starting and final revisions and stage commits/diffs; planned/completed stages; verification passed/failed/blocked/pending/inapplicable and omissions; corrective work versus new requests; splits/follow-ups; retrospective scope assessment; maintainer comfortable-fit judgment and acceptance date. Record active-work measurements only if reliably collected; never infer effort from lines, stage counts or timestamps.

Next action and study review

The user selected additional candidate E07 on 2026-10-20. Review its root-only implementation and supply the maintainer comfortable-fit/acceptance judgment next; E01–E06 remain proposed. The provisional anchor still awaits maintainer acceptance. Each feature gets its own approvals. The agent keeps active candidate, pending items and next action current for resumption. After six accepted outcomes, start a separately approved documentation cycle to assess size errors, scope changes and incomplete acceptance; qualify conclusions if ceiling examples are absent. No measured labor, absolute capacity ceiling or delivery forecast is claimed.

Candidate intake batch B1

Recorded 2026-10-19T03:21:59.566650+00:00, before application source inspection for these candidates. Starting revision for all six: e8548e7512940b4e164483fbd33d79eca2b85099 (application baseline is unchanged from the planning commit). Scope version: v1; reference: R1; rater: Codex, single rater. Exposure: all inherited feedback scores and the reference study were visible; planning/status records were screened first. todo.txt had unrelated uncommitted edits; it was read as a status hint, not modified (SHA-256 at screening: 5d241274915baebf0588f49516aaf3be41e68bde7d0596e30d1bc1aa23c96b85). No independent-rater claim.

IDProposed remaining outcomeFeedback itemInheritedInitial totalStatus
E01Explain conduct/integrity vouching at user approvalFeature 030.050.08Proposed, current-source screen pending
E02Copy All on public thread/reply body text boxesFeature 050.150.25Proposed, current-source screen pending
E03Stop tag-input automatic capitalization on mobileBug 010.050.08Proposed, current-source screen pending
E04Keep reply Send/Post reachable above the iPhone keyboardFeature 160.400.55Proposed, device acceptance pending
E05Optional expanded excerpts in the standard Board listingFeature 340.350.45Proposed, current-source screen pending
E06Reversible distraction-free mode on New threadFeature 260.400.50Proposed, current-source screen pending

Scores are judgments for the bounded scopes below, not rewrites of the broader feedback scores. Required verification is included. No ceiling candidate is forced into this batch. Later per-step columns remain pending until separate cycles exist.

E01 — Approval meaning

  • Outcome/entry: At the standard user-approval action, explain that approval vouches for conduct and integrity; retain the existing action and permission rules.

  • Recovery/evidence: Copy remains readable on mobile and keyboard navigation; existing success, refusal and failure/retry controls remain visible. Verify approval and rejection paths without changing policy.

  • Dependencies/overlap: Existing approval UI and vouching design; root approval pages and User Access may already supply the meaning. Confirm remaining copy before implementation.

  • Initial rationale: Smaller than about-copy integration, but locate the real shared action and check unchanged permissions/recovery; 0.08 total.

E02 — Copy body text

  • Outcome/entry: Copy the full body from public New thread and reply text boxes without losing or submitting the draft; exclude secret-key/password fields and unrelated text boxes from this proposed first slice.

  • Recovery/evidence: On denied/unavailable clipboard access, preserve text and offer ordinary manual selection/copy. Verify empty, Unicode and multiline drafts, keyboard activation and a mobile browser; no signed-content changes.

  • Dependencies/overlap: Existing composer and clipboard helpers; bookmarklet/key copy controls are related infrastructure, not proof that body Copy All exists. Shares composer surface with E04/E06 but delivers an independent outcome.

  • Initial rationale: Similar to a bounded routing extension, with shared controls and clipboard denial recovery; 0.25 total. Maintainer must confirm this narrowed scope is useful.

E03 — Tag capitalization

  • Outcome/entry: Stop automatic initial capitalization in standard public thread/reply tag inputs on mobile while preserving deliberately entered characters and existing tag validation.

  • Recovery/evidence: Native keyboard no longer forces capitals; existing validation and draft recovery remain usable. Verify on a real affected mobile keyboard, plus render coverage for shared input attributes; desktop attributes alone do not close the report.

  • Dependencies/overlap: Shared tag input and existing normalization; composer declutter changed layout, not documented keyboard behavior.

  • Initial rationale: Small shared-input change with targeted device acceptance; 0.08 total, conditional on reproducibility.

E04 — iPhone posting control

  • Outcome/entry: In the standard inline thread-reply form and compose-reply page, keep Send/Post reachable while the iPhone software keyboard is open in portrait and landscape. No redesign of private-message or Forte composers.

  • Recovery/evidence: Draft, validation errors and retry action survive keyboard opening/closing and rotation; avoid covering text or causing duplicate sends. Capture actual iPhone Safari/Firefox checks and supported desktop regression evidence; emulation alone is insufficient. Device access remains to be arranged in its feature cycle.

  • Dependencies/overlap: Shared composer and declutter history; private-message sticky composer is a separate surface. Coordinate later E02/E06 changes through new baselines.

  • Initial rationale: Several viewport/focus transitions plus real-device acceptance; near composer decluttering's 0.60 reference but narrower surfaces, 0.55 total.

E05 — Expanded Board excerpts

  • Outcome/entry: A standard Board reader can switch between existing compact cards and longer text excerpts, then open a post normally. Scope excludes Forte and new search, loading or media behavior.

  • Recovery/evidence: Toggle back without losing current filter/sort; handle short/empty bodies and unavailable preferences gracefully; preserve safe text rendering and navigation on mobile/keyboard. Define excerpt length during feature planning.

  • Dependencies/overlap: Existing thread-card preview behavior and duplicate-preview suppression; do not count that completed narrow change again.

  • Initial rationale: More state/rendering work than score emphasis or toolbar identity, while reusing cards and data; 0.45 total.

E06 — Distraction-free New thread

  • Outcome/entry: From standard New thread, enter and exit a focused writing view that reduces surrounding chrome while retaining draft, submit, required warnings and a visible way out. No persistent/cross-device preference or new editor.

  • Recovery/evidence: Exit via a visible keyboard-accessible control; failed validation exposes relevant fields without losing text. Verify mobile layout, keyboard navigation and repeated entry/exit; unavailable JS leaves ordinary composition usable.

  • Dependencies/overlap: Composer declutter already simplifies sections. Hide numbers focus toggle concerns reading/counts, not this writing mode; keep separate.

  • Initial rationale: Bounded layout state and recovery, below the broader 0.60 composer reference; 0.50 total.

Screening dispositions before source inspection

  • Feature 01 composer simplification overlaps delivered declutter; exclude the broad historical request from this batch.

  • Feature 27 image paste overlaps delivered image upload enhancements; exclude the combined image/audio/video request rather than re-estimate completed image work.

  • Bug 10 missing-PHP startup overlaps the calibration anchor; exclude from prospective candidates.

  • Feature 28 compose-reply context and Feature 25 Reply scrolling may overlap existing thread/reply work; defer, not counted or declared fixed.

  • Feature 23 ActivityPub and bundled agent/notification requests remain underspecified; no artificial near-ceiling scope is introduced.

Post-intake source screen — 2026-10-19T03:22:54.041492+00:00

Read-only source screening followed the saved intake batch. This is evidence of plausible remaining work, not browser reproduction or a feature implementation audit. Candidate selection and feature approvals remain pending.

IDCurrent scope / projected totalEvidence and disposition
E01v1 / 0.08 reaffirmedtemplates/pages/users_pending.php exposes Approve with no conduct/integrity explanation; existing profile/about copy references trust but does not establish the requested action-level explanation. Retain proposed; confirm all actual approval surfaces during planning.
E02v1 / 0.25 reaffirmedtemplates/partials/thread_compose_form.php and reply_form.php contain body textareas and submit/clear actions, with no body Copy All control. Retain proposed; existing clipboard helpers need detailed inspection later.
E03v2 / 0.06Thread form's editable board_tags input has no autocapitalization hint; reply form's board tags are hidden. Narrow to the editable standard New thread tag input, preserving explicit user capitalization and required real-mobile validation. Reason: source-informed scope reduction, not measured effort. v1/0.08 remains above.
E04v1 / 0.55 reaffirmedShared reply form renders submit below the body; inspected compose CSS has no keyboard-viewport handling. Actual iPhone reproduction remains pending, so retain as proposed with device acceptance required; do not claim a reproduced bug.
E05v1 / 0.45 reaffirmedtemplates/partials/thread_card.php renders body_preview; standard Board has no excerpt-mode control in the screened template. Existing duplicate-preview suppression is reused. Retain proposed; query/data sufficiency still needs inspection.
E06v1 / 0.50 reaffirmedThread form has disclosure sections but no writing-mode toggle; inspected disclosure script manages those sections/actions, not a distraction-free view. Retain proposed; keep separate from hide-numbers reading mode.

All these snapshots use rater Codex, reference R1 and the same starting revision as B1, with prior score exposure and additional source exposure as listed. They are post-intake screening checkpoints, not retrospectively invented Step 1/2/3 feature scores. Later feature cycles will record their own handoffs. No detailed implementation design or runtime verification was performed.

Feature 28 (original text on compose-reply) is now excluded as apparently already present: templates/pages/compose_reply.php renders the parent body and a missing-parent message. This source observation does not certify its runtime behavior. Other deferred/rejected items remain visible above. No replacements were needed among E01–E06; E03's narrower scope remains explicit.

Compact checkpoint comparison

CandidateInheritedIntakeAfter source screenStep 1Step 2Step 3Step 4 entryCloseout
E010.050.080.08PendingPendingPendingPendingPending
E020.150.250.25PendingPendingPendingPendingPending
E030.050.080.06 (v2)PendingPendingPendingPendingPending
E040.400.550.55PendingPendingPendingPendingPending
E050.350.450.45PendingPendingPendingPendingPending
E060.400.500.50PendingPendingPendingPendingPending

All six remain proposed and unfinished on the screened evidence. Pending columns mean the feature cycles have not begun; convert Step 1 to not applicable only if that step is actually skipped. Shared composer dependencies mean execution order may change later baselines and estimates; do not sum these scores as a forecast. This batch lacks near-ceiling examples, so it cannot by itself validate the 1.0 ceiling.

Operational checklist for the agent

  1. Resume here: read current state, selected candidate and next action; verify R1 source hashes and restore the latest scope/score snapshot. A ledger selection triggers the vendored study contract; copy the study/candidate ID and ledger link into the feature artifact.

  2. Before new detailed inspection, preserve the intake estimate and starting revision. For an existing B1 candidate, keep its original record and append any new baseline/scope judgment rather than reset it.

  3. Run the selected feature’s normal approvals and capture each applicable checkpoint. Include this ledger in its approved documentation scope. Keep planning updates uncommitted; preserve the planning-commit file gate.

  4. At implementation entry reaffirm or revise the total; append meaningful later discoveries and enforce changed-scope approvals. Keep the comparison table linked to canonical artifact snapshots.

  5. Close out in the feature’s final stage commit: record evidence, retrospective assessment and maintainer judgment (or pending), update status/next action and retain splits/corrections versus new requests. Technical completion alone does not increment accepted outcomes.

  6. After six accepted outcomes, propose the separate study-review cycle. Keep sources and all earlier estimates intact; qualify any conclusion about the ceiling because this proposed batch has no near-ceiling examples.

Synthetic walkthrough evidence lives in the setup summary, outside candidate histories. Later real feature plans will supply the currently pending checkpoint links.

E07 — Fastmod rubric actions

  • Selection: explicitly requested 2026-10-20; status v3 technically complete; maintainer acceptance pending. Additional candidate outside B1; no E01–E06 replacement or independent child-outcome claim. Target remains six accepted outcomes.

  • Canonical scope v1, intake and Step 1 snapshots: fresh assessment. Starting revision 4c521b743575979b8fefc66b38271551a57a08ef; Codex single exposed rater; no inherited score. Intake 0.85, Step 1 0.85 reaffirmed, R1. Intake was recorded after historical-plan and read-only source exposure, not reconstructed as pre-inspection.

  • Proposed outcome: evidence-backed, discoverable meta tagging of newly scored local posts, including human correction, provenance, stale-result handling, retries and rollback of machine-owned tags. Automated moderation, author standing, ranking changes and historical bulk tagging are deferred; predecessor records remain intact. No application implementation or later-step approval is implied.

  • R1 verification: report and diff-review files at the recorded external paths match frozen hashes. Current feedback document differs; restored exact frozen feedback bytes read-only from Git revision 4f6cfe2b436fae8d939b1349fe724a3879ee0a0e to /tmp/fastmod-r1-feedback.md and verified SHA-256 ef335604ecd5b51e5c04067d88e4d6f01cb4fdb21b8f4d7dba7b5b90e4012bfc. Recover by Git revision, not the temporary path. No R2 was introduced.

  • Step 2 checkpoint: feature description, 0.95, R1, scope v1 clarified, Codex single exposed rater, UTC 2026-10-20. New understanding of reaction/label coupling and discovery/rebuild/rollback integration revises the total from 0.85; original snapshots remain intact.

  • Step 3 checkpoint: development plan, 0.95 reaffirmed, R1, scope v2, Codex single exposed rater, UTC 2026-10-20. User explicitly removed the human-labeled accuracy gate after Step 2 approval; machine-owned tagging/correction/recovery scope remains.

  • Next: user reviews Step 3; wait for Approved Step 3. Step 4 entry and closeout scores remain pending. Retain this ledger within the cycle's eventual approved documentation boundary; planning writes remain uncommitted, with accumulated ledger updates reserved for authorized closeout.

  • E07 Step 3 architecture refinement A2 (2026-10-20): user accepted live tag joins/bulk lookups with generation-time public artifact snapshots instead of continuous read-model copying. Scope v2 and total 0.95 reaffirmed; canonical revision. Step 3 remains awaiting approval.

  • E07 Step 4: branch feat/fastmod-rubric-actions, planning commit 766deab1; entry/discovery snapshots and Stage 1 evidence. Entry 0.95 reaffirmed, discovery 1.20 for unchanged v2/A2 scope; offline item format/client and generation-safe build/activation work exceed the approved atomic stage breakdown. No application changes; awaiting revised scope or stage-budget decision. No closeout or accepted outcome. Ledger remains outside the investigation commit under the approved closeout bookkeeping rule.

  • E07 revised Step 2 v3 (2026-10-20): user accepted reduced root-only automatic meta tagging, existing styling, configuration/CLI-only controls, no evidence viewer, restore, generic mapping engine or automatic reclassification. Canonical revised scope/snapshot: 0.85 projected total, R1, Codex single exposed rater; includes already performed planning/investigation and renewed planning, not just remaining implementation. This replaces, and does not complete, original v2. Await renewed Approved Step 2 then revised Step 3 and its approval; no accepted outcome or independent child observation. Historical v1/v2 approvals and scores remain preserved.

  • E07 revised Step 3 v3 (2026-10-20): renewed Step 2 approval received. Canonical development plan/checkpoint reaffirms 0.85 total, R1, Codex single exposed rater, including prior investigation/replanning. Eight root-only stages separate private persistence, worker eligibility, live discovery, CLI correction, artifact guard, artifact materialization, verification and closeout. Await renewed Approved Step 3; no application edits or accepted outcome. Historical broader scope remains preserved.

  • E07 v3 closeout (2026-10-20): canonical implementation/outcome record. Reduced implementation start 79bc519f; original cycle start 4c521b743575979b8fefc66b38271551a57a08ef; final production code d1da4d40; revised planning fe9578f9, then eight stage commits including closeout. Projected total 0.85 preserved; retrospective scope assessment 0.90, Codex single exposed rater, R1. Outcome: root-only meta tags, existing presentation/live lookup/public artifact labels, CLI correction/retry/rollback and private retained evidence. Final focused 27 passed; broader focused 68 passed; real browser/rebuild passed. Full suite 1,380 / 1,372 passed / 8 reproduced baseline/environment failures; started before final atomic-evidence/enablement fixes, with final focused/browser coverage of those changes. No deployment or live-model accuracy test. Maintainer comfortable-fit/acceptance pending, accepted outcomes remain 0 / 6. v3 is an explicit reduced replacement, not completion of original v2 and not an independent child observation.

  • E07 closeout commit: 1f35e6be (Stage 8), completing the eight-stage v3 sequence after planning fe9578f9. Current-state text corrected in a separate closeout follow-up; no application changes or history rewrites. Maintainer study acceptance remains pending.

Continuing enrollment — 2026-10-21 (protocol P2)

Maintainer request: “I want every future railspike to be part of the same data collection.” This is standing enrollment of every new Railspike cycle in this project, including documentation, research and maintenance cycles. It supersedes individual-selection-only guidance above from this date; earlier text and candidate histories remain historical. R1 and all prior scores remain unchanged. The maintainer authorized provisional beta use of the scale; this does not supply E07's pending comfortable-fit judgment or accept an individual outcome.

  • Continuing study ID: railspike-effort; reference R1; collection protocol P2. New cycle ID: v3/<unique feature prefix>; retain E01–E07 as legacy candidate IDs. Reuse the same ID across worktrees for the same cycle. A distinct follow-up gets its own prefix and parent link; check existing plans/ledger before allocating it.

  • Every new cycle records intake, applicable Step 1/2/3 handoffs, Step 4 entry, material revisions and closeout using the existing rating protocol and outcome template. Include this ledger's bookkeeping in the cycle's documentation scope. Canonical snapshots stay in feature artifacts; append a ledger index row with ID, status, scope/reference version, current score, checkpoint/artifact link and parent/replacement relationship. Preserve all earlier values. Initial inspection exposure and missing checkpoints must be explicit.

  • Record new cycles at their first artifact, including work that pauses, is abandoned or never reaches implementation. Work already underway joins at its next checkpoint with its earlier estimates marked missing unless evidence exists; do not invent intake history. Ordinary tasks that do not invoke Railspike are outside the cycle population. E01–E06 remain proposals until actually started; automatic collection is not implementation approval.

  • Keep projections, retrospective scope assessment, verification and maintainer comfortable-fit/acceptance separate. Record stage counts, corrections versus new requests, omissions, revisions/diffs and splits. Unknown active work and absent independent ratings remain unknown. Technical completion does not increment accepted outcomes.

  • Six accepted outcomes now trigger a review checkpoint, not the end of collection or a size quota. Freeze R1 until an explicit reference revision; protocol P2 changes enrollment only. Retain every scope/version and related child cycle; no extra independent outcomes from cloned files or split children.

  • This checkout's ledger and artifacts are local copies of one dataset. Integrate updates through normal Git review; merge by stable cycle ID/checkpoint and retain conflicting snapshots, rather than overwriting or summing checkouts. Collection is local; no automatic upload is authorized. Repair source paths by recorded content hash/Git revision, never by silently changing references.

Enrollment index after P2

Cycle IDStatusScope / referenceLatest projectionCanonical checkpointsRelationship / acceptance
v3/image_backup_zipLocally complete; maintainer acceptance pendingv1 / R1 / P20.40Intake and Step 2; Step 3Format/recovery follow-up to archive README and Backup UI; acceptance pending

2026-10-26T00:56:13Z: image ZIP Step 2 approved. Step 3 0.40 whole-cycle projection reaffirmed, same scope v1/original baseline/R1/P2, verified R1 hashes and Codex single exposed rater. Extended stage-work originals: S1 0.18 bounded ZIP recovery, S2 0.12 ZIP export/routes, S3 0.08 ordinary-flow verification/docs; independent annotations, not summed. Reuse existing PHP ZIP support with no dependency addition. No implementation, measurement or accepted outcome; awaiting Approved Step 3.

2026-10-26T00:45:01Z: standing enrollment for v3/image_backup_zip, original baseline 5510efde63b6f5eae1970d836d363bb63403a2f2. Intake after initial code inspection and Step 2 handoff both 0.40 projected total; R1 hashes verified, Codex single exposed rater. New-cycle extended estimates enabled; Step 1 skipped because the requested ZIP format is explicit. Scope includes normal ZIP downloads, safe verify/restore, legacy TAR compatibility and documentation. No implementation, measurement or accepted outcome; documentation remains uncommitted.

Cycle IDStatusScope / referenceLatest projectionCanonical checkpointsParent / acceptance
v3/repository_archive_readmeLocally complete; acceptance pendingv2 / R1 / P20.25Intake and Step 1; Step 2; Step 3; CloseoutNew cycle; acceptance pending

2026-10-25T18:29:42Z: repository archive README Step 2 approved; three-stage development plan prepared. Step 3 0.25 total reaffirmed, scope v2/original baseline/R1/P2 and single exposed rater unchanged; R1 hashes verified, extended mode remains disabled. Existing-history-free exporter integration, ordinary download/import/image recovery and scoped closeout are covered. Earlier Step 3 approval message preceded the concrete plan; awaiting review. No implementation, measurement or accepted outcome; planning remains uncommitted.

2026-10-25T18:26:38Z: repository archive README Step 1 Option B approved. Step 2 scope v2 corrects prior checkout assumptions to remote history-free content snapshots and the shared export path. Original baseline and 0.25 intake/Step 1 estimates preserved; Step 2 0.25 total reaffirmed, R1 hashes verified, Codex single exposed rater. Existing disabled extended mode survives beta-4 upgrade. No implementation, measured labor or accepted outcome; awaiting Approved Step 2.

2026-10-25T18:19:32Z: standing P2 enrollment for repository archive README improvements; original baseline 99a0def2af1f0b19b4b5cc284c1eac920da9464d. Intake after source/archive inspection and Step 1 handoff both 0.25 projected total; Codex single exposed rater, verified R1, no pristine intake or measured labor claim. Recommended shared export guide covers both formats and export paths with preservation of original repository notes. No implementation or accepted outcome; documentation remains uncommitted.

E01–E06: proposed, no feature-cycle checkpoints. E07: reduced v3 technically complete, projected 0.85, retrospective 0.90, maintainer acceptance pending. These counts are unchanged by P2. Append each new cycle here with links to its canonical snapshots; keep unsuccessful/incomplete cycles visible. The historical “0 / 6” is accepted outcomes toward the first review checkpoint, not the number of collected records.

Cycle v3/retraction_effects

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/retraction_effectsLabel slice implemented; deployment/review pending; parent incompletev5 / R1 / P2Unavailable: frozen calibration report/diff sources missingIntake exposure and Step 1 limitationRelated proposal v3/thread_unpin_web_ui; not an independent delivered outcome; acceptance pending

Standing enrollment: withdraw ongoing site-controlled effects of currently retractable posts, preserving surviving independent contributions, with legacy attribution/recovery, retry, rebuild and concurrent-work coverage. Prior diagnostic and unpin-assessment exposure disclosed; no pristine intake or reconstructed numeric estimate. Frozen R1 sources remain unavailable as recorded by the related proposal; preserve references and restore exact sources before rating. No measured effort, implementation, split outcome or accepted-count increment. Earlier unpin proposal remains intact and unapproved; this cycle addresses source retraction rather than introducing a general label-removal control. Planning/ledger writes remain uncommitted.

2026-10-23 Step 1 revision: user selected Option C; v2 recursively retracts dependent items, including cross-author descendant replies, and withdraws their effects. Preview, explicit cascade authority, protected-dependency handling and resumable completion are required. This supersedes the v1 source-only recommendation without erasing its snapshot; same stable cycle, baseline and R1/P2. Revised numeric projection remains unavailable pending frozen-source recovery. No step approval or implementation is implied.

2026-10-23 Step 1 revision v3: user requested explicit coverage of physical source deletion through delete-record, alongside signed retraction. Include reliable source-to-dependent linkage, cleanup of separate label records, dependency discovery before source evidence is removed, and repair for already deleted sources. Live archive inspection showed both pin-label records surviving reply deletion. Preserve v1/v2 snapshots, same stable ID/baseline/R1/P2; revised projection remains unavailable pending exact reference recovery. No implementation approval or independent outcome.

2026-10-23 Step 1 revision v4: user clarified that independently authored replies must survive. Current recommendation is narrowed C: recursively clean generated effects for retraction and delete-record, preserving reply content, valid independent contributions and root/thread structure. v2/v3 broad reply cascades and associated cross-author cascade requirements are superseded; historical snapshots remain. Same cycle/baseline/R1/P2; numeric projection unavailable pending exact frozen-source recovery. No step approval, implementation or outcome claimed.

2026-10-23 Step 2 handoff: Step 1 v4 explicitly approved. Feature description/checkpoint retains v4 generated-effect cleanup for both entry points, preserved replies, provenance and historical repair, with release inventory and retry/import/publication coverage. Codex single exposed rater; same baseline/R1/P2. Projected total unavailable pending exact frozen report/diff recovery, not zero or a new numeric estimate. Step 2 and implementation remain unapproved.

2026-10-23 Step 3 investigation: Step 2 v4 approved. Scope split proposal/checkpoint records evidence that the full contract exceeds atomic staging limits: historical imported labels lack proven source links, missing roots need explicit representation, physical deletion needs durable/retry/import/publication handling, and remaining machine-output families need separate integration. Proposed first cycle closes label cleanup/conversation preservation end to end; remaining effects retain parent incomplete status. Split not accepted, children not started, no completed Step 3 or implementation approval. Same baseline/R1/P2 and exposed rater; numeric projection unavailable pending frozen-reference recovery.

2026-10-23 split accepted: user explicitly approved the split. Step 2 v5 scopes the first release to label ownership/cleanup, both removal paths, conversation preservation and durable legacy repair. Approved v4 retained verbatim; remaining effect families and parent outcome stay incomplete. Continue under the same stable observation, not an independent child success. Same baseline/R1/P2/exposed rater; revised total unavailable pending exact reference recovery. Renewed Step 2 approval required before executable Step 3.

2026-10-23 Step 3 v5 handoff: renewed Step 2 approval received. Executable development plan/checkpoint proposes eight bounded stages through ownership, removal evidence, retraction, conversation structure, deletion/repair, imports, concurrency and closeout. Earlier split investigation retained. Same stable cycle/baseline/R1/P2; total projection unavailable pending exact reference recovery. No implementation, independent child outcome or parent all-effects completion claimed; awaiting Approved Step 3.

2026-10-23 Step 4 closeout: user approved Step 3 v5; entry, eight-stage implementation and study outcome. Branch feat/retraction-effects, baseline e960f666, planning 43ed5860, seven intermediate stage commits and Stage 8 closeout (exact final revision recorded in the debug handoff). Label cleanup, both entry points, explicit legacy repair, import/retry/publication persistence and preserved replies delivered locally. Final focused 98/98; extra source-evidence/parser 48/48; real browser/theme and stable-doc static/rebuild checks passed. Full suite incomplete: 59 passed, two missing-GD image failures reproduced on unchanged baseline. Deployment/live repair, parent remaining effects and maintainer fit/acceptance pending. Numeric projected and retrospective ratings remain unavailable pending exact R1 recovery; no measured effort or independent child outcome. Accepted-count unchanged.

Cycle v3/thread_like_activity

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/thread_like_activityImplementation handoff; acceptance pendingv1 / R1 / P2Unavailable: exact frozen calibration report/diff missingIntake and Step 1; Step 2; Step 3Related v3/retraction_effects, separate bug; acceptance pending

Standing enrollment covers per-contribution thread-like activity through normal writes, historical rebuild and shared Activity consumers, retaining scoring, duplicate eligibility and source-withdrawal policy. Local incident evidence and aggregator inspection preceded intake; no pristine intake or reconstructed numeric estimate. Baseline 39be82932fcc36c5017fcf368655ef449bf042da; Codex single exposed rater; R1/P2 unchanged. No implementation, independent child outcome, measured effort or accepted-count increment. Planning remains uncommitted; user's canceled commit request is not reused as authorization.

2026-10-23 Step 2 handoff: explicit Step 1 approval received. Scope v1 clarifies one Activity item per distinct accepted eligible like-bearing record, stable replay behavior, historical evidence attribution, mixed-label records and shared classic/Forte/feed recovery. Universal repository coverage, button-like withdrawal and the withdrawn-source duplicate-guard bug remain separate. Same baseline/R1/P2 and exposed rater; total projection unavailable pending exact frozen reference recovery. Step 2/implementation not approved; no completed outcome or measured effort.

2026-10-23 Step 3 handoff: explicit Step 2 approval received. Four-stage plan covers normal-write/rebuild inclusion, per-record historical attribution, version-23 startup recovery and isolated known-case/browser acceptance. Scope v1, baseline/R1/P2 and exposed rater unchanged; projected total remains unavailable pending exact frozen-reference recovery. No application implementation or completed outcome; await Approved Step 3. Broader coverage and withdrawal requests remain separately tracked.

2026-10-23 Step 4 closeout: Step 3 approved; entry, stage outcomes, verification boundaries and retrospective assessment. Planning commit ab24d158, followed by four summary-bearing stage commits on feat/thread-like-activity. Each eligible like contribution now appears with per-record historical attribution; version-24 startup and normal rebuild recover omissions without new canonical records. Isolated exact incident, 29 focused PHP tests, missing-history follow-up, signed-button browser flows and shared Activity recovery checks passed. Live deployment/physical devices and full-suite verification are not claimed. R1/P2 and scope v1 unchanged; numeric projection and retrospective assessment remain unavailable pending exact reference recovery; prior missing checkpoints stay missing. Maintainer fit/acceptance pending; no measured effort, independent outcome or accepted-count increment.

Cycle v3/thread_unpin_web_ui

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/thread_unpin_web_uiStep 1 awaiting review; implementation unapprovedv1 / R1 / P2Unavailable: frozen calibration report/diff sources missingIntake exposure and Step 1 limitation (source unavailable)No parent cycle; maintainer fit/acceptance pending

Standing enrollment covers browser-only thread unpinning with proposed operator authority, legacy/duplicate pin handling, repinning and rebuild/presentation recovery. Earlier diagnostic source exposure is disclosed; no pristine intake or numeric score is reconstructed. Feedback hash verified from its recorded Git revision; external report/diff unavailable in this checkout's environment. Preserve R1 and recover exact sources before rating. Planning and ledger updates remain uncommitted; no accepted-outcome count change.

Cycle v3/reply_composer_focus_layout

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/reply_composer_focus_layoutImplementation handoff; device acceptance pendingv1 / R1 / P20.65 reaffirmedStep 4 discovery/enrollment; closeoutiphone_reply_submit pre-study predecessor; maintainer comfortable-fit/acceptance pending

This existing cycle joined under standing enrollment during Step 4. Intake, Steps 1–3 and Step 4 entry projections are missing, not backfilled. R1 source hashes were verified; earlier source exposure is disclosed in the canonical snapshot. Retrospective scope assessment 0.65 is separate from the preserved 0.65 projected total. Baseline bc42277b, three planned/delivered stages; committed scope and verification/omissions are recorded in the summary and final handoff log. Physical iPhone acceptance, full-suite evidence and maintainer acceptance are not claimed. No accepted-outcome count is incremented. This is one cycle regardless of checkout/worktree copies; no split or new independent outcome.

Cycle v3/composer_anchor_exit

Stable cycle IDStatusScope / reference / protocolTotal projectionCanonical checkpointsParent / acceptance
v3/composer_anchor_exitStep 1 awaiting review; implementation not authorizedv1 / R1 / P20.50 intake; 0.50 reaffirmed at Step 1Intake and Step 1 snapshotsv3/reply_composer_focus_layout; maintainer fit/acceptance pending

Enrolled under standing P2 policy. Initial lifecycle/style/template inspection and prior-cycle exposure preceded the recorded intake and are disclosed; no pristine prospective intake is claimed. Scope includes anchored inline thread/reply expansion, spacing, usable exit/resume, dedicated New Thread label/prompt polish, keyboard reachability and submission/recovery checks. No implementation, measured effort, retrospective outcome or accepted-count increment is claimed. This stable ID identifies the same cycle across worktrees; the original parent record remains intact. The user explicitly requested committing and pushing these Step 1 planning updates before the usual planning-commit gate; this does not approve implementation.

Cycle v3/activity_feed_pagination

Stable cycle IDStatusScope / reference / protocolTotal projectionCanonical checkpointsParent / acceptance
v3/activity_feed_paginationImplementation handoff; acceptance pendingv3 / R1 / P2Unavailable: frozen external calibration sources unavailableIntake and Step 1; Step 2; Step 3Historical Forte pagination is prior work, not this cycle; acceptance pending

Standing P2 enrollment; baseline 39be82932fcc36c5017fcf368655ef449bf042da. Source/plan exposure preceded intake and is disclosed. Recommended scope is bounded Older/Newer navigation across HTML Activity views and paned Commits, preserving filtering, sorting, selection access and recovery; RSS and unrelated previews excluded. R1 retained without invented scores. No implementation, measured effort, independent outcome or accepted-count increment. Planning/ledger updates remain uncommitted.

2026-10-23 Activity pagination Step 1 revision: scope v2 checkpoint preserves v1 history and recommends a shared pagination component first delivered through standard/Forte Activity and Forte Commits. Default Previous/Next, optional numbered jumps for suitable later consumers; other migrations stay in the checklist. Same stable cycle, original 39be8293 baseline, R1/P2 and single exposed rater; current source context e507cb71 and expanded source exposure disclosed. Revised total unavailable pending exact frozen-reference recovery. Step 1 approval pending; no Step 2, implementation, measured effort or accepted-count change.

2026-10-23 Activity pagination Step 2 handoff: explicit Step 1 approval received for shared-first Option B, scope v2. Feature description/checkpoint defines bounded Previous/Next navigation, shared controls/state with list-specific queries, URL/history, live-result consistency, recovery and security/static/offline boundaries through standard/Forte Activity and Forte Commits. Later migrations remain separate. Same cycle/baseline/R1/P2 and exposed rater; current source inspection e5f4bce6 disclosed. Projected total remains unavailable pending exact frozen-reference recovery; historical checkpoints preserved. No implementation, measured effort or accepted outcome; awaiting Approved Step 2.

2026-10-23 Activity pagination scope v3 revision: user explicitly requested no Forte changes and alignment of Steps 1–2. Revised assessment and requirements narrow shared pagination to standard Activity as its first consumer. Forte append/Commits and existing APIs remain unchanged; shared-service compatibility is verified. Step 1 v2 approval and earlier checkpoints remain historical; Step 2 v3 awaits approval. Checklist records Forte as an explicit exception, not a scheduled migration. Same cycle/original baseline/R1/P2 and exposed rater; revised total remains unavailable pending exact reference recovery. No implementation, measured effort or accepted outcome.

2026-10-23 Activity pagination Step 3 handoff: explicit Step 2 v3 approval received. Development plan/checkpoint defines four bounded stages: additive standard-only page flow/reusable controls plus read-model version gate; stable reverse traversal and recovery; actual static/offline/access serving; browser acceptance and documentation. Forte production code, append behavior and API contracts remain unchanged; existing flows are regression checks. Same cycle/original baseline/R1/P2 and single exposed rater, checkout e5f4bce6; projected total remains unavailable pending exact frozen reference recovery. Earlier checkpoints preserved; no implementation, measured effort, independent outcome or accepted-count increment. Await Approved Step 3.

2026-10-23 Activity pagination documentation clarification: user requested project implementation guidance at completion. Steps 2–3 and the checklist make the existing documentation deliverable explicit: docs/reference/pagination.md, discoverable through CONTRIBUTING.md, with a worked standard Activity example, reusable/list-specific boundaries and verification/recovery guidance. Scope v3, Step 2 approval, original baseline/R1/P2 and exposed rater unchanged; projected total remains unavailable pending exact reference recovery. No new runtime scope, implementation or outcome; Step 3 still awaiting approval.

2026-10-23 Activity pagination Step 4 closeout: user approved Step 3; entry, four stages, evidence/limits and retrospective assessment. Planning 347df048 precedes summary-bearing implementation commits on feat/activity-feed-pagination. Standard Activity now has bounded native Previous/Next pages via reusable controls/position handling, unchanged Forte interfaces and append behavior, schema-25 startup recovery, actual serving/invalidation verification and a linked developer guide. Focused PHP 44/44; standard JS/no-JS, 13-theme phone/desktop and actual Forte append/Commits browser checks passed; signed reactions and existing Forte reader checks passed. Local-only evidence; full suite, live deployment and physical-device acceptance not claimed. Scope v3/original baseline/R1/P2 and exposed rater unchanged; numeric projected and retrospective assessment unavailable pending exact frozen-reference recovery. Maintainer fit/acceptance pending; no measured effort or accepted-count increment.

Cycle v3/railspike_workflow_visibility

Stable cycle IDStatusScope / reference / protocolTotal projectionCanonical checkpointsParent / acceptance
v3/railspike_workflow_visibilityImplementation handoff; live/maintainer acceptance pendingv1 / R1 / P2Unavailable: exact frozen references unavailableIntake and Step 1Corrective follow-up to phone site development; maintainer acceptance pending

Standing enrollment; baseline cd2f84087a6584d2b1cb3ac8ebaa2395fa897ec6. Codex single exposed rater; live HTML, code/history and original workflow plans inspected before intake, disclosed without reconstructed prospective scoring. Scope recommends authorized server-rendered workflow discovery/reading, thread integration and recovery, preserving private boundaries and existing signed actions. R1 report/diff absent; current feedback hash differs from frozen R1. No replacement anchor, numeric score, implementation, measured effort or accepted-count increment. Planning/ledger updates remain uncommitted; same stable cycle across worktrees.

2026-10-23 workflow visibility Step 1 revision: user selected Option A and requested a separate assessment for remaining Option C. Parent scope v2 narrows to Activity block removal, retained thread behavior and regression verification; original v1 snapshot retained. Same baseline/R1/P2/exposed rater; numeric projection remains unavailable. Selection is not step or implementation approval. Original broader outcome remains incomplete; no independent split success or accepted-count increment.

Cycle v3/railspike_workflow_reading

Stable cycle IDStatusScope / reference / protocolTotal projectionCanonical checkpointsParent / acceptance
v3/railspike_workflow_readingStep 1 saved for later review; implementation unapprovedv1 / R1 / P2Unavailable: exact frozen references unavailableIntake and Step 1Split follow-up to v3/railspike_workflow_visibility; not an independent accepted split outcome

User requested saving remaining private discovery/reading scope separately from parent removal. Baseline cd2f84087a6584d2b1cb3ac8ebaa2395fa897ec6; Codex single exposed rater, prior incident/parent/original plan exposure disclosed. Preserve original parent v1 and revised v2; R1 report/diff missing and feedback differs, so no numeric rating. No implementation, measured effort or accepted-count change. Documents and ledger remain uncommitted; same cycle ID across worktrees.

2026-10-23 workflow visibility Step 2 handoff: Step 1 Option A v2 explicitly approved. Feature description/checkpoint scopes removal to the detached Activity integration and proven workflow-only dependencies, preserving thread/post controls, documented APIs and ordinary Activity consumers. Repository provenance/coverage and deferred reading remain separate. Baseline/R1/P2 and exposed rater unchanged; total projection remains unavailable pending exact frozen-reference recovery. No implementation, measured effort or accepted-count increment; awaiting Approved Step 2.

2026-10-23 workflow visibility Step 3 handoff: explicit Step 2 approval received. Development plan/checkpoint defines two bounded stages: remove the Activity-only integration while preserving thread/API behavior, then rendered regression acceptance/documentation. Retain auth/signing dependencies conservatively; verify workflow network silence and existing signed recovery. Same scope v2/baseline/R1/P2/exposed rater; projected total remains unavailable pending exact frozen references. No implementation, measured effort, independent split success or accepted-count change. Awaiting Approved Step 3.

2026-10-23 workflow visibility Step 4 closeout: Step 3 approved; entry, two stages and outcome. Planning 4e176747, Stage 1 2224e68c, followed by Stage 2 acceptance/documentation on fix/activity-workflow-block. Removed detached Activity UI/client refresh; retained thread/post workflows and documented APIs. Role/script/viewport matrix, workflow signed recovery/resumption, no workflow polling, standard paging/RSS/entry recovery and 13-theme browser checks passed; targeted PHP 26 passed after Node PATH correction. Local-only; deployment/reported live URL reload, physical devices, full suite and maintainer fit/acceptance pending. Scope v2/baseline/R1/P2 unchanged; projected and retrospective numeric scores unavailable pending frozen R1 recovery. Original broader/split scope retained; no measured effort, independent split success or accepted-count increment.

  • v3/feature_flags_security_review_cleanup — active Step 1, awaiting approval; scope v1, R1/P2, intake 0.18, Step 1 0.18 reaffirmed; canonical assessment and snapshots. Remove the detached Feature Flags security-review shortcut while retaining canonical authorized audit access. Source exposure preceded intake; no earlier prospective estimate invented. No parent/replacement or accepted outcome. Implementation and later checkpoints pending; ledger changes remain uncommitted until authorized closeout.

  • v3/feature_flags_security_review_cleanup revision — scope v2, Step 1 awaiting approval; projected total 0.45, R1/P2, 2026-10-21T19:51:05Z, Codex exposed single rater. User clarified relocation/presentation rather than removal alone: recommend embedded Access history in User Access, compact events with expandable evidence and session/empty-state recovery. Canonical revised assessment. Preserve v1 intake/Step 1 0.18 above; no implementation, replacement cycle or accepted outcome.

  • v3/feature_flags_security_review_cleanup — Step 1 v2/mockup approved; Step 2 awaiting approval. 2026-10-21T20:11:34Z, scope v2 clarified, R1/P2, Codex exposed single rater; projected total 0.45 reaffirmed. Recent five events, full-history handoff, evidence and operator authentication recovery remain one User Access slice. Earlier v1/v2 snapshots retained; no implementation or outcome acceptance.

  • v3/feature_flags_security_review_cleanup — Step 2 approved; Step 3 awaiting approval. 2026-10-21T20:31:02Z, scope v2, R1/P2, Codex exposed single rater; 0.45 total reaffirmed after checking existing bounded queries, evidence and authentication-return support. Four stages: protected recovery, embedded history, full/shared history, browser acceptance/closeout. No runtime edits, implementation approval or accepted outcome. Prior snapshots remain canonical.

  • v3/feature_flags_security_review_cleanup — technically complete, maintainer acceptance pending, scope v2/R1/P2, 2026-10-21T20:58:23Z; entry and outcome. Entry 0.45 reaffirmed, projected total 0.45 preserved, retrospective scope 0.45; Codex exposed single rater, no measured labor or independent rating. Start 0b9f5f8b, planning e563a057, stages 3df2e156, b37e11af, 2c367f7d, followed by Stage 4 acceptance/closeout commit (hash in debug handoff). Four stages completed; real signed browser role/recovery/history checks and 47 PHP regressions pass, 16 phone/desktop themes checked. Chromium only, no full suite/deployment/original-session inspection. Earlier scope v1 was superseded, not completed independently; retain all snapshots. Accepted outcomes remain unchanged; next action is maintainer review, with no implementation work outstanding.

Cycle v3/concurrent_checkouts

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/concurrent_checkoutsStep 1; implementation unapprovedv1 / R1 / P2Unavailable pending frozen-reference recoveryIntake disclosure and Step 1No parent; acceptance pending

Standing enrollment; baseline 19f1066aac81fe417d88a10efa9c756125199af5. Codex single exposed rater; inventory preceded intake recording. User clarified worktrees are confusing; recommend familiar clones with task names and a read-only overview. No migration, implementation, numeric estimate, measured effort or accepted-count increment. Same cycle across checkouts; planning records uncommitted.

2026-10-23 concurrent checkouts Step 1 v2: revised canonical checkpoint recommends persistent IntelliJ clone slots, distinct colors and a shared task/branch/plan overview, preserving directory paths and trusted sessions. Supersedes task-folder creation recommendation; v1 retained. R1 report/diff recovered and hashes match, but current feedback hash differs; numeric projection unavailable pending exact frozen feedback. Same stable cycle/baseline/R1/P2; no implementation or accepted-count change.

2026-10-23T06:34:57+00:00 concurrent checkouts Step 1 v3: current assessment/checkpoint selects previewable batch fetch/update for existing configured agent clones, fast-forward main and merge main into eligible feature branches, dirty/busy-operation skips and conflict recovery. User agreement recorded; exact Step 1 approval pending. Supersedes identification-only recommendation; v1/v2 retained. Same cycle/baseline/R1/P2/exposed rater; numeric projection unavailable pending frozen feedback recovery. No implementation, measurements or accepted-count change.

Cycle v3/markdown_dependency_removal

  • Standing enrollment at existing-cycle Stage 4 resumption under railspike-effort, scope v1/R1/P2; earlier checkpoint scores missing, not backfilled. Canonical resumption and Stage 4 evidence. Codex single exposed rater, 2026-10-23; R1 report/diff and exact historical feedback hashes verified. Starting revision 02512b8e2b1b44dabb3966eac21295bea9626412; restoration/removal merged at afe40311.

  • Late projected total 1.20, reaffirmed after isolated rewrite/recovery verification; includes already completed restoration, corpus/UI/release evidence, policy work and remaining controlled history/copy recovery. Not remaining effort or measured labor. The above-one scope warrants reviewing remaining cleanup per target under the existing publication gate; no independent child outcome is allocated.

  • Stage 4 verified: 2,988 remote commits preserved, 139 rewritten, six replacement refs pending publication review; private local recovery preserves 3,135 commits across 553 refs. 48 focused tests, copied-package recovery/16 browser scenarios and 1,312 mapped-corpus renders passed. Stage 5 publication, clone disposal and external retention acceptance remain incomplete. Maintainer comfortable-fit/outcome acceptance pending; accepted count unchanged.

  • v3/docs_publication_policy — active planning, awaiting Approved Step 1; scope v1 / R1 / P2; 0.65 projected total, Step 1 handoff 2026-10-21T19:40:41Z, Codex single exposed rater. Canonical assessment and snapshots. Pre-inspection intake missing; prior source/plan exposure disclosed. Outcome: avoid repeated documentation rendering during imports while retaining complete static-library access and safe recovery. Starting revision be2be9d4ad4c172db33147239ecca6d2ca860d4a; no parent/replacement; implementation and acceptance pending. No completed/accepted outcome added.

  • v3/docs_publication_policy — Step 1 approved; Step 2 handoff 2026-10-21T20:24:13Z, awaiting Approved Step 2. Scope v1 clarified / R1 / P2; 0.65 projected total reaffirmed, Codex single exposed rater. Canonical Step 2 snapshot. Existing complete dynamic/static library and import/resume outcomes retained; dependency-boundary and practical-performance risks explicit. Original Step 1 score and missing intake preserved; same starting revision and no parent/replacement. Implementation and outcome acceptance remain pending.

  • v3/docs_publication_policy — Step 2 approved; Step 3 handoff 2026-10-21T20:42:55Z, awaiting Approved Step 3. Scope v1 / R1 / P2; 0.65 projected total reaffirmed, Codex single exposed rater. Canonical plan/checkpoint. Eight stages cover early dependency/baseline validation, evidence/integrity, full/shared publication, CLI failure/resume, reader/performance acceptance and closeout. Earlier scores and missing intake retained; same start revision, no parent/replacement, no implementation or accepted outcome.

  • v3/docs_publication_policy — Step 3 approved; planning branch feat/docs-publication-policy, planning commit cf5e744c. Step 4 entry and Stage 1 discovery: v1 entry 0.65 reaffirmed; proposed v2 0.70 projected total after finding content-repository HEAD in every docs page’s version marker (default on). UTC 2026-10-21T20:59:04Z, R1/P2, Codex single exposed rater; revised Step 2 awaits renewed approval. No application changes or completed outcome; earlier scores, original start and missing intake preserved; no parent/replacement.

  • v3/docs_publication_policy — Stage 1 verification 2026-10-21T21:00:54Z: full frozen baseline 1,375 docs / 82.894 s; separate unchanged four-document CLI import demonstrates README output changes only in embedded destination HEAD. Evidence and limitations. Proposed v2 remains 0.70 / R1; awaiting revised Step 2 approval, then renewed Step 3. Stages 2–8 and all reuse implementation remain incomplete; no accepted outcome or measured active effort.

  • v3/docs_publication_policy — resumed on current main at 1a358bc9, UTC 2026-10-23T07:49:12Z; same cycle/original start, scope v2 / R1 / P2, 0.70 projected total reaffirmed, Codex single exposed rater. Canonical resumption checkpoint. Restored cycle files and all stashed checkpoints alongside upstream records; R1 hashes verified, frozen feedback recovered from its recorded revision. Revised Step 2 approval remains pending, followed by renewed Step 3; current-source dependency/baseline revalidation is required. No new independent observation, implementation, measured actual or accepted outcome.

  • v3/docs_publication_policy — renewed Step 2 v2 approved; revised Step 3 handoff UTC 2026-10-23T08:05:54Z, 0.70 projected total reaffirmed, scope v2 / R1 / P2, Codex single exposed rater. Canonical revised plan/checkpoint. Eight stages include current-main revalidation, guarded marker transfer, full/shared publication, import recovery and reader/version/performance acceptance; dependency inventory zero. All R1 hashes verified using recorded Git feedback. Original start, earlier estimates, completed historical audit and missing intake retained. Await renewed Approved Step 3; no application changes, measured actual or accepted outcome.

  • v3/docs_publication_policy — v2 technically complete locally, closeout UTC 2026-10-23T09:57:40Z; R1/P2, Codex single exposed rater. Canonical outcome/commits, verification. Original start be2be9d4ad4c172db33147239ecca6d2ca860d4a; migrated base 1a358bc9, final production e99e1412; revised planning 6e77d190 and eight stage commits. 0.70 projected total preserved; retrospective scope assessment 0.80 for guarded reuse/copy/activation and complete normal-flow verification. Eight/eight stages complete, zero docs rendering on compatible imports/shared refresh; final same-inventory local new-record import 5.806 s versus 79.916 s original baseline, with uncontrolled cache/load caveat. Final 15 helper/flow + 29 reader/catalog/asset checks; final full-library normal CLI/benchmark/browser acceptance passed. Full repository suite/deployment not performed. Earlier 0.65/0.70, original approvals/audit and missing intake retained; measured active effort unknown. No parent/replacement or independent worktree outcome. Maintainer comfortable-fit/acceptance pending; accepted count unchanged.

  • v3/docs_independent_publication — new follow-up assessment, scope v1 / R1 / P2, intake UTC 2026-10-23T10:04:42Z; 0.75 projected total, Codex single exposed rater. Canonical intake/assessment. Starting revision ddc9d2c020addbc41b19f543d0247b83259c6f69; predecessor v3/docs_publication_policy, whose completed outcome remains intact. User selected independent docs publication to remove cold/incompatible docs rebuilds from import/resume. Prior source/score exposure disclosed; no pristine intake or independent rating. R1 exact hashes verified. Assessment/approvals/implementation incomplete; no accepted-count change.

  • v3/docs_independent_publication — Step 1 handoff UTC 2026-10-23T10:05:49Z, scope v1 / R1 / P2, 0.75 projected total reaffirmed, Codex single exposed rater. Canonical assessment/checkpoint. Recommend independent complete static docs publication, with import/resume never rebuilding docs, retained prior docs/assets, independent update identity and initial static-host setup/retry. Same starting revision and predecessor; earlier intake/exposure retained. Await Approved Step 1; no implementation, measured actual or accepted outcome.

  • v3/docs_independent_publication — Step 1 approved; Step 2 handoff UTC 2026-10-23T10:20:48Z, scope v1 clarified / R1 / P2, 0.75 projected total reaffirmed, Codex single exposed rater. Canonical requirements/checkpoint. Independent complete static docs publication; no docs bulk work on import/resume/forum builds or shared refreshes; retained library/assets, transition/setup, separate updates and recovery. Same start ddc9d2c020addbc41b19f543d0247b83259c6f69 and predecessor v3/docs_publication_policy; R1 hashes verified, prior exposure/intake history preserved. Dependency proposal zero. Await Approved Step 2; no implementation, measured actual or accepted-count change.

  • v3/docs_independent_publication — Step 2 approved; Step 3 handoff UTC 2026-10-23T10:27:18Z, scope v1 clarified / R1 / P2, 0.85 projected total, revised from 0.75 for discovered read-model startup and legacy invalidation/sweep isolation work. Canonical plan/checkpoint. Same baseline/predecessor, Codex single exposed rater; R1 exact hashes verified and earlier scores/exposure preserved. Eight stages cover ownership proof, standalone publication, readers/version identity, legacy retention, forum detachment, actual WSL recovery/concurrency, complete-library acceptance and closeout. No scope/dependency expansion; await Approved Step 3, no implementation or accepted-count change.

  • v3/docs_independent_publication — Step 4 entry reaffirmed 0.85 projected total after explicit Step 3 approval; eight-stage local implementation/closeout complete, maintainer acceptance pending. Canonical entry, implementation and study outcome. Scope v1 clarified / R1 / P2, same start ddc9d2c020addbc41b19f543d0247b83259c6f69, predecessor v3/docs_publication_policy; planning f2d718a0, production 7c255bfd, focused fixtures 5567310c, Stage 7 0eabe1a9, Stage 8 closeout records final documentation. Earlier 0.75 snapshots and revision to 0.85 preserved. Retrospective scope assessment 0.90, separately labeled, Codex single exposed rater; R1 exact report/diff/frozen-feedback hashes verified, no actual-work measurement or independent rating. Dedicated complete docs publication, bounded legacy retention, independent reader/version/asset identity and zero docs bulk work in forum/import/resume paths verified. Final focused 60/60, original import/publication/recovery/retraction/classification 31/31, full-library CLI and dynamic/static phone/desktop/browser/no-JS/four-theme acceptance passed. Full suite/deployment/production host unverified. No new scope/dependencies/split or predecessor outcome replacement. Maintainer comfortable-fit/acceptance pending; accepted count unchanged; one stable observation across worktrees, no upload.

  • v3/import_without_static_rendering — intake/Step 1 handoff UTC 2026-10-23T18:01:59.961066+00:00, scope v1 / R1 / P2, 0.55 projected total, Codex single exposed rater; canonical assessment/snapshots. Start c86b89314602a17cf435448bb66053f4d750150f; predecessor v3/docs_independent_publication retains completed docs-only outcome. User requires zero import-time page rendering; recommend data refresh plus stale HTML invalidation and explicit static builds, preserving offline/private/docs/recovery correctness. Prior-cycle and initial source exposure disclosed; exact host-local R1 hashes verified. No implementation, independent rating, measured actual effort or accepted-count change. Await Approved Step 1; planning updates uncommitted.

  • v3/import_without_static_rendering — one-shot override/closeout UTC 2026-10-23T18:06:11.235757+00:00; user explicitly declined staged workflow and authorized direct Option A implementation. Canonical outcome. Same scope v1 / R1 / P2/start/predecessor; 0.55 intake/Step 1 preserved, retrospective 0.55 separately labeled, Codex single exposed rater. Final Summary: 41 run, 41 passed, 0 failed; real CLI/served HTTP/recovery/docs/cleanup passed; full suite/deployment unverified. No later prospective checkpoint fabricated, no stages/commits required under override, no dependency delta; working-tree implementation, no measured actual or independent rating. Maintainer fit/acceptance pending; accepted-count unchanged.

  • v3/import_record_failure_isolation — intake/Step 1 handoff UTC 2026-10-23T18:19:32Z, scope v1 / R1 / P2, 0.45 projected total, Step 1 reaffirmed; canonical assessment and snapshots. Start c86b89314602a17cf435448bb66053f4d750150f plus pre-existing uncommitted import/publication work; related v3/import_without_static_rendering, separate defect, no replacement. Recommend consistent record/signature classification and bounded record rejection with truthful partial results, preserved dependency/trust rules and fatal operation-level failures. Prior diagnosis/reproduction and score exposure disclosed; Codex single exposed rater; exact frozen R1 hashes verified. Await Approved Step 1; no implementation, measured labor, independent rating or accepted-count increment. Planning/ledger updates remain uncommitted.

  • 2026-10-23 Stage 5 publication checkpoint: explicit “Publish now” authorization executed for the reviewed six replacements; main 1a358bc9. Canonical publication record and independent verification: all 20 refs/2,989 commits match the candidate, target path history and targeted blob storage are absent in a fresh HTTPS clone, fsck passed. Projected total 1.20 reaffirmed, v1/R1/P2, single exposed rater. Existing clones/recovery copies remain preserved; synchronization/disposal and host-retention acceptance are pending, so the full outcome and retrospective closeout remain incomplete. Accepted count unchanged.

Cycle v3/markdown_renderer_extension

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/markdown_renderer_extensionResumed Step 1; later steps unapprovedv1 / R1 / P20.65Resumed Step 1Follow-up to v3/markdown_dependency_removal; parent removal and maintainer acceptance incomplete

2026-10-23: existing deferred cycle joins at resumed Step 1, earlier scores missing, not backfilled. Baseline ad7e8f5fc5570ee5bdcdf08a03b2dfac524c9d83; Codex single exposed rater after removal/renderer/metrics inspection. Frozen R1 hashes verified including exact historical feedback. Refreshed 1,402-document corpus renders without errors; proposed first slice is safe dynamic/static pipe tables with source fallback, mobile/keyboard/theme and publication recovery checks. Projected total 0.65, not remaining work or measured labor; no implementation, independent rating, split success or accepted-count increment. Planning/this index entry remain uncommitted under the Step 1 gate.

2026-10-23 Stage 5 clone-sync checkpoint: user explicitly authorized preservation-aware synchronization; all seven clones now have main/origin-main at 1a358bc9, retained refs and fourteen worktree registrations reconciled, and eight stashes preserved. Audit ad7e8f5f retained. Canonical summary and per-clone evidence. New private stash supplemental mapping preserves non-target content; zero target blobs/path history across retained refs/stashes/worktree HEADs. Private bundles, reflogs/unreachable storage and missing registrations retained; disposal and host/external acceptance pending. Scope v1/R1/P2, exposed single rater, projected total 1.20 reaffirmed; full-removal outcome remains incomplete, accepted count unchanged.

2026-10-23 renderer extension Step 2 handoff: Step 1 explicitly approved; feature description scopes standalone pipe tables, alignment, escaped/code pipes, exact-width rows, semantic headers/safe links, readable whole-block fallback and ordinary dynamic/static phone/keyboard delivery with publication recovery. Stable cycle v3/markdown_renderer_extension, scope v1 clarified, same baseline/R1/P2/exposed single rater; frozen hashes reverified, 0.65 total reaffirmed. Zero new dependencies; Step 2 and implementation unapproved. Planning/ledger remain uncommitted; no measured effort, outcome acceptance or accepted-count change.

2026-10-23 renderer extension Step 3 handoff: Step 2 explicitly approved; development plan defines five bounded stages: normal-reader tables, adversarial boundaries/safety, accessible reader, copied publication/recovery, corpus/theme acceptance. Stable v3/markdown_renderer_extension, v1/R1/P2, same baseline and exposed single rater; R1 hashes reverified, 0.65 total reaffirmed, prior checkpoints preserved. Five planned/zero completed stages; no implementation approval, measured effort, outcome acceptance or accepted-count change. Plans/ledger remain uncommitted awaiting Approved Step 3.

2026-10-23 renderer extension Step 4 closeout: Step 3 approved; canonical implementation and outcome, branch feature/markdown-renderer-tables. Scope v1/R1/P2, same baseline and exposed single rater. Planning 073fb5f6a; Stages 1–4 ec3155f37, 2eecbf33e, 2a3e27046, 483ec05bb, Stage 5 closeout follows. Five planned/five completed stages. Step 4 entry 0.65 reaffirmed before implementation; projected 0.65 preserved, retrospective scope 0.70 separately assessed. 37 distinct focused PHP cases pass across stage runs, metrics fixture, zero-error frozen 1,402/current 1,405 document renders; all 66 original table documents classified (116 rendered tables, one nested fallback, two orphan source rows in a mixed document). Dynamic/static/discovery theme/viewport matrix and complete copied-package publication/failure recovery pass; no dependency delta. Full suite, deployment, physical devices and maintainer comfortable-fit/acceptance pending; parent removal outcome incomplete, no measured labor, independent rating or accepted-count increment.

2026-10-23T14:22:42.464645+00:00 renderer extension maintainer handoff: user said “Looks great” and explicitly authorized merge and moving on. Functional result accepted for merge; study comfortable-fit/sizing judgment remains unknown, so no inferred study accepted-count increment. Retain projected 0.65/retrospective 0.70, all earlier checkpoints and parent incomplete-removal status. Wider Docs column noted as separate deferred layout follow-up; next syntax work starts its own assessment/approval cycle.

2026-10-23T07:44:54+00:00 concurrent checkouts Step 1 v4: current assessment and checkpoint incorporates the separately authorized manual synchronization trial. First automated slice is explicit registry, fetched-source preview, eligible branch updates and per-checkout recovery; rewritten-history detection hands off to separately authorized migration. Five checked-out main branches aligned to 1a358bc9 and verified clean; other refs/worktrees and dirty clones remain untouched. Operational trial is not automated-slice completion or a study acceptance. Original baseline and v1–v3 retained; rewritten checkout target disclosed. Same stable cycle/R1/P2/exposed rater; projected total unavailable pending exact frozen feedback. Documentation revision only; implementation unapproved.

2026-10-23T08:18:05+00:00 concurrent checkouts Step 2 handoff: Step 1 v4 explicitly approved. Feature description/checkpoint defines registered clone setup, preview/apply, source/history validation, partial recovery and WSL IntelliJ-terminal acceptance. Scope v4/original baseline/R1/P2/exposed rater retained; current rewritten checkout disclosed. Total projection unavailable pending frozen feedback recovery; no reconstructed earlier score, implementation or accepted outcome. Awaiting Approved Step 2.

2026-10-23T09:50:06+00:00 concurrent checkouts Step 3 handoff: explicit Step 2 approval received. Development plan/checkpoint defines seven stages for shared private registry, safe history evidence, saved previews, revalidated fast-forwards, merges/recovery, CLI docs and WSL terminal acceptance. Already-fetched/unknown divergence is blocked absent reconciliation evidence; no automatic migration/discovery. Scope v4/original baseline/R1/P2/exposed rater unchanged; projected total remains unavailable pending frozen feedback recovery. No implementation or accepted outcome; awaiting Approved Step 3.

2026-10-23T10:09:28+00:00 concurrent checkouts Step 4 closeout: Approved Step 3 recorded; planning b1b33e0b8, seven implementation stages plus Stage 1 JSON correction on feat/concurrent-checkouts. Canonical entry/stages/outcome: explicit private registry, source/history evidence, signed preview, revalidated apply, feature merges, recoverable partial results and WSL terminal acceptance delivered. Final scoped PHP 20/20 (wrapper has 32 real-Git cases) plus actual interruption test 1/1; 33 acceptance cases collectively passed, syntax/diff passed. Full suite/actual IntelliJ UI and live enrollment remain unverified; no main merge/push. Scope v4/original baseline/R1/P2 and exposed rater preserved; numeric projection and retrospective scope assessment unavailable pending frozen feedback recovery. No measured effort or accepted-count increment; maintainer fit/acceptance pending. Final Stage 7 revision recorded in debug handoff.

Cycle v3/checkout_overview

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/checkout_overviewStep 1; implementation unapprovedv1 / R1 / P2Unavailable pending exact frozen feedback recoveryIntake exposure and Step 1Follow-up to v3/concurrent_checkouts; acceptance pending

2026-10-23T14:15:51+00:00; baseline 1edbe534d7faf0c84c3b4d0ddc3e60fef3a38beb. User selects instant cached overview/background refresh plus aligned columns; fresh preview/apply remain deliberate. Codex single exposed rater; prior implementation and five registry-only timing runs disclosed before intake, not pristine scoring or automated performance acceptance. R1/P2 retained; no numeric estimate, implementation, measured effort or accepted-count increment. Distinct cycle across worktree copies; parent unchanged. Planning remains uncommitted.

2026-10-23T14:27:34+00:00 checkout overview Step 2 handoff: Step 1 v1 explicitly approved. Feature description/checkpoint defines subsecond local cached default, bounded/coalesced refresh, aligned columns, explicit fresh preview/apply and on-host timing/recovery acceptance. Same stable ID v3/checkout_overview, parent/baseline/v1/R1/P2/exposed rater retained; projected total unavailable pending frozen feedback recovery. No implementation or accepted outcome; awaiting Approved Step 2.

2026-10-23T14:33:16+00:00 checkout overview Step 3 handoff: Step 2 v1 explicitly approved. Development plan/checkpoint defines seven stages: local cached reads, shared aligned renderer, detached lifecycle, bounded fetch with coordinator-only history writes, fresh-preview/apply recovery, docs and WSL timing/failure acceptance. New feature branch from predecessor planned after approval; no reuse requested. Same stable ID v3/checkout_overview/parent/baseline/v1/R1/P2/exposed rater; total projection remains unavailable pending exact frozen feedback recovery. No implementation or accepted outcome; awaiting Approved Step 3.

2026-10-23T14:59:26+00:00 checkout overview Step 4 closeout: Step 3 approved; planning db8ea0009, seven stages on feat/checkout-overview. Canonical entry/stages/outcome and final timing evidence. Default local cached overview with aligned columns, bounded single-flight/concurrent refresh, serialized history/evidence, fresh preview authority, invalidation/recovery and docs delivered. PHP 20/20 including 53 real-Git cases; 60 final foreground timing samples all <1s, 0.0506s warm median / 0.0807s all-phase max; earlier successful run retained. Actual IntelliJ UI/full project suite/main integration/live updates unverified or outside scope. Same stable ID/parent/baseline/v1/R1/P2/exposed rater; projected and retrospective numeric scores unavailable pending frozen feedback recovery. No measured effort, accepted-count change or independent split outcome; maintainer fit/acceptance pending. Final stage revision is in debug handoff.

Cycle v3/markdown_list_structure

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/markdown_list_structureStep 1; implementation unapprovedv1 / R1 / P20.90Assessment; intakeRenderer follow-up to v3/markdown_renderer_extension; not a new accepted split outcome

2026-10-23T14:24:34.347787+00:00: baseline b9d1cc874973b9a8f8452a2a61a7d308430bb678, Codex single exposed rater with prior table/renderer/metrics/calibration exposure. Intake numeric projection unavailable pending bounded recommendation, retained without backfill; Step 1 0.90 total includes planning, nested ordinary lists/paragraphs, source numbering, safe inline content, dynamic/static corpus/theme checks and publication recovery. Exact R1 hashes verified. User authorized merged table slice and next assessment, not list implementation; wider Docs column remains separately deferred. No measured labor, independent rating, acceptance or accepted-count increment. Plans/this ledger entry remain uncommitted.

2026-10-23T14:28:01.727848+00:00 list structure Step 2 handoff: Step 1 explicitly approved; feature description bounds ordinary space-indented mixed lists, content-column ownership, eight levels, continuation/loose paragraphs and literal ordered numbering; ambiguous/tab/unsupported embedded blocks retain source with adjacent content and existing safety preserved. Wider Docs layout remains separately deferred. Stable v3/markdown_list_structure, v1 clarified/R1/P2, same baseline/exposed single rater; frozen hashes reverified, 0.90 total reaffirmed. Prior snapshots/missing intake retained; no implementation, measured labor, outcome acceptance or accepted-count change. Step 2 and later work unapproved; documents/ledger uncommitted.

2026-10-23T14:32:10.042982+00:00 list structure Step 3 handoff: Step 2 explicitly approved; development plan defines six bounded stages: paragraphs/numbering, nesting, unsupported-block safety, accessible ordinary reader, portable publication/recovery, corpus acceptance/closeout. Stable v3/markdown_list_structure, v1 clarified/R1/P2, same baseline/exposed single rater; R1 hashes reverified, 0.90 total reaffirmed including all required verification. Six planned/zero completed stages; no implementation approval, measured effort, outcome acceptance or accepted-count change. Prior checkpoints/missing intake retained; plans and ledger uncommitted awaiting Approved Step 3.

2026-10-23 list structure Step 4 closeout: Step 3 explicitly approved; canonical implementation/outcome, branch feature/markdown-list-structure, baseline b9d1cc874. Stable v3/markdown_list_structure, v1 clarified/R1/P2, same exposed single rater; all frozen hashes reverified. Entry 0.90 reaffirmed before implementation, projected 0.90 preserved, separate retrospective 0.95. Planning 17fcec043; Stages 1–5 e27a0356d, dd24c3ad1, 3bfe93666, f9b4528d0, 4876f2337, followed by Stage 6 closeout. Six planned/six completed stages; 48 distinct focused PHP cases, metrics fixture, zero-error 1,405 frozen/1,411 refreshed documents, 453 nested-list document classifications and actual dynamic/static/copy-publication/recovery/theme checks pass. Whole-block fallbacks stay explicit; no dependency delta or wider-column implementation. Full suite, deployment, physical devices and maintainer comfortable-fit/acceptance pending; no measured labor, independent rating, split outcome or accepted-count increment. Parent removal retention acceptance remains incomplete.

2026-10-23T15:18:18.733723+00:00 list structure maintainer UAT/merge handoff: user reviewed example Docs pages, said “Great,” and authorized merge. Functional result accepted; study comfortable-fit/sizing judgment remains unknown, so no inferred study accepted-count increment. Preserve projection 0.90/retrospective 0.95 and all prior snapshots. Integrate newer main without losing unrelated checkout/UI work. Task-marker presentation is a next-slice recommendation only; wider-column layout and parent removal retention remain separate.

Cycle v3/markdown_task_lists

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/markdown_task_listsStep 1; implementation unapprovedv1 / R1 / P20.35Assessment; intakeSeparate renderer follow-up to v3/markdown_list_structure; acceptance pending

2026-10-23T15:29:13.048146+00:00: user instructed proceeding with recommended read-only task-list slice. Baseline 682ab5b40179624b86b9c53ad3fd7dba98ccec69, Codex single exposed rater after prior renderer/metrics/calibration exposure. Intake 0.35, Step 1 0.35 total reaffirmed for native disabled task-state display on supported unordered items, canonical safe inline/list behavior, theme/phone/keyboard/corpus and copied-publication recovery checks plus documentation. Frozen R1 hashes verified; refreshed scan finds 644 checked/538 unchecked candidates across 47 documents in a 1,420-document corpus. Editing and wider Docs layout remain outside scope; no merged-branch reuse. No implementation, measured labor, independent rating, acceptance or accepted-count increment. Plans/metrics/ledger remain uncommitted awaiting Approved Step 1.

2026-10-23T17:27:24.755117+00:00 task lists Step 2 handoff: Step 1 explicitly approved; feature description bounds leading checked/unchecked markers on supported unordered items, first-paragraph accessible names, native disabled immutable display and independent task links; literal/ordered/source-only forms remain unchanged. Stable v3/markdown_task_lists, v1 clarified/R1/P2, same baseline/exposed single rater; R1 hashes reverified, 0.35 total reaffirmed with theme/accessibility/corpus/copied-publication recovery included. Editing, new dependencies and wider Docs layout remain outside scope. Prior checkpoints preserved; no implementation, measured labor, outcome acceptance or accepted-count increment. Step 2/later work unapproved; plans/metrics/ledger uncommitted.

2026-10-23T17:44:31.329348+00:00 task lists Step 3 handoff: Step 2 explicitly approved; development plan defines four bounded stages: canonical task boundaries, accessible immutable reader, portable publication/recovery, corpus/closeout acceptance. Stable v3/markdown_task_lists, v1 clarified/R1/P2, same baseline/exposed single rater; R1 hashes reverified, 0.35 total reaffirmed with full scoped verification. Four planned/zero completed stages; no implementation approval or accepted outcome. User separately authorized a todo.txt note for a checked/total in-page checkbox counter, saved in ee0f5b173 outside this cycle's planning/implementation; counter and wider Docs layout remain deferred. Prior checkpoints retained; no measured effort, independent rating or accepted-count change. Plans/metrics/ledger remain uncommitted awaiting Approved Step 3.

2026-10-23 task lists Step 4 closeout: Step 3 approved; canonical implementation/outcome, branch feature/markdown-task-lists, baseline 682ab5b40, v1 clarified/R1/P2, same exposed single rater. Entry/projected 0.35 preserved, separate retrospective 0.40; all frozen reference hashes reverified. Planning 2dc733152; Stages 1–3 a6d2591b6, 214612173, c908ec4aa, followed by Stage 4 closeout. Four planned/four completed stages; 54 distinct focused PHP cases, metrics fixture, zero-error 1,420 frozen/1,425 refreshed corpus documents, 47 task-document classifications and actual package/publication/failure recovery/theme/name/state checks pass. Of 1,182 original candidates, 1,109 display native disabled state and 73 remain source, independently accounted per document/state. No dependency delta, task editing, counter or wider-column implementation; todo counter note preserved. Full suite, deployment, physical assistive technology/devices and maintainer comfortable-fit/acceptance pending. No measured labor, independent rating, split outcome or accepted-count increment; parent historical-retention acceptance remains incomplete.

2026-10-23 task lists UAT correction: user reported initial native disabled checkbox painting barely distinguishable. Correction and renewed evidence supersede initial visual acceptance: theme-token outline/solid/tick styling, 46 dynamic + 46 generated all-theme cases, eight final generated reader regressions, 52 focused PHP passes and actual shared publication. Same v3/markdown_task_lists, v1 clarified/R1/P2/baseline/exposed single rater; frozen R1 hashes reverified. Projected 0.35 retained, separate retrospective 0.40 reaffirmed including ordinary visual correction. No new feature/cycle, measured labor, independent rating or accepted-count change. Corrected local handoff complete; user retest, maintainer comfortable-fit/acceptance, merge/deployment, full suite and physical AT/device acceptance remain pending. Consolidated requested Markdown checklist is documentation, not approval of optional feature decisions; counter/layout and recovery retention remain deferred.

Cycle v3/production_feedback_management

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/production_feedback_managementTechnically complete; maintainer acceptance pendingv1 / R1 / P20.35 projected; 0.35 retrospectiveAssessment and snapshotsNo parent; historical intake proposal related; acceptance pending

Standing enrollment; baseline 1a358bc9be3cdb725277c792625a678e7bc85436, 2026-10-23T09:36:24Z, Codex single exposed rater. Summary/workflow review preceded intake, disclosed without reconstructed pristine scoring. Recommended documentation-only slice establishes a canonical request register through October 21 migration, aliases/provenance, triage and separate delivery evidence; older inventories retained for later reconciliation. Exact R1 report/diff and historical feedback hashes verified. No implementation, independent rating, measured effort or accepted-count increment; planning/ledger remain uncommitted.

2026-10-23T09:45:50Z production feedback management Step 2 handoff: Step 1 Option B approved. Feature description/checkpoint specifies documentation-only register/guide, all 16 October 21 mappings, preserved aliases/source/estimate provenance, separate workflow/delivery evidence, historical redirects and Git correction/recovery. Scope v1/R1/P2/original baseline unchanged; 0.35 total reaffirmed, Codex single exposed rater; exact references reverified. Older-batch reconciliation deferred. No implementation, independent rating, measured effort or accepted-count change; awaiting Approved Step 2.

2026-10-23T09:51:06Z production feedback management Step 3 handoff: Step 2 approved; repository Markdown storage confirmed without scope change. Development plan/checkpoint defines four bounded documentation stages: guide/first requests, remaining features, bugs/discovery, acceptance/closeout. Scope v1/R1/P2/original baseline retained; 0.35 total reaffirmed, Codex single exposed rater. Complete 16-entry provenance/alias/estimate checks, evidence-state separation, correction walkthroughs and zero runtime/dependency changes required. No implementation, measured effort or accepted-count change; awaiting Approved Step 3.

2026-10-23T09:59:27Z production feedback management Step 4 closeout: Step 3 approved; entry, four stages and study outcome. Scope v1/R1/P2/original baseline unchanged; 0.35 projected total preserved, 0.35 retrospective scope assessment, Codex single exposed rater. Planning 0c93edaa9; stages 367bf407f, 3235e3ae2, 2bdb74b07, followed by acceptance/closeout. Delivered documentation-only register/guide, 16 exact request mappings, stable IDs/aliases, index/discovery and historical authority labels. Coverage, 347 local links/anchors, historical-table preservation, approved-file scope and diff checks passed; zero dependency delta. Intake-to-correction walkthrough reviewed; no runtime/deployment/production audit or measured work claimed. Older-batch reconciliation remains follow-up; maintainer comfortable-fit/acceptance pending, accepted count unchanged. Same cycle across worktrees; no independent split outcome.

Cycle v3/absent_retraction_import

2026-10-23T18:16:27Z: standing enrollment P2, scope v1/R1, baseline aeaad63298ffe72b792bce84acd9f72c310c4bef. Canonical intake and Step 1 checkpoint. Codex single exposed rater after task-952 diagnostics and import/publication source inspection; no pristine intake score reconstructed. Projected total unavailable pending frozen R1 report/diff recovery. Recommendation: supported absent-target validation through import publication, interrupted retry and queued snapshots, with stale-content/reappearance/authority/concurrency verification. Related to v3/retraction_effects, whose broader incomplete outcome is unchanged. No implementation, measured effort, accepted outcome or count increment. Planning and ledger remain uncommitted awaiting Approved Step 1.

2026-10-23 Step 1 scope v2 correction: user clarified that “import” was mistaken and requested renamed plans committed for later dev work. Corrected snapshot assessment covers direct/queued base and update publication, retries and shared-guard regressions. Stable cycle v3/absent_retraction_import retained, with v1 history, baseline/R1/P2/exposed rater unchanged; numeric projection still unavailable. Explicit documentation-commit authorization overrides the planning commit timing only; no Step 1 approval, implementation, measured effort or accepted outcome.

2026-10-23T19:20:50Z absent-target snapshot Step 1 scoring revision: user requested option difficulty estimates. Canonical option comparison and snapshot: A 0.85 recommended total; B 1.20 (split discussion); C 0.35 (fallback only, successful publication unresolved). Exact host-local R1 report/diff/feedback hashes verified; new dated ratings supersede current unavailability without backfilling historical checkpoints. Stable v3/absent_retraction_import, scope v2/original baseline/R1/P2 and Codex single exposed rater retained. No new application inspection, measured labor, independent outcomes or acceptance increment; Step 1/implementation unapproved, revisions uncommitted.

2026-10-23T19:25:12Z absent-target snapshot Step 1 scope v3: canonical revision adopts per-build affected-post/retraction exclusion and continued publication through target reappearance; later builds retain existing authority validation. Abort-on-reappearance trim rejected. Recommended projected total 0.70, superseding v2 0.85 for reduced same-build resolution scope; B 1.20 / C 0.35 unchanged. Stable v3/absent_retraction_import, original baseline, R1/P2, exposed single rater and historical checkpoints preserved; exact R1 hashes reverified. Prior work included, no new source inspection or measured effort/accepted outcome. Step 1/implementation unapproved; revisions uncommitted.

2026-10-23T19:37:36Z absent-target snapshot Step 2 handoff: Step 1 scope v3 explicitly approved. Feature description/checkpoint defines build-local exclusion, continued publication through target reappearance, later-build authority, direct/queued base/update consumption and existing safety recovery. 0.70 total reaffirmed, stable v3/absent_retraction_import, v3/original baseline/R1/P2/exposed single rater retained; exact R1 hashes reverified. Limited shared-source inspection disclosed; no runtime validation, measured labor or accepted outcome. Earlier-base leakage remains an explicit early validation risk. Await Approved Step 2; no implementation or commit.

2026-10-23T19:43:15Z absent-target snapshot Step 3 handoff: Step 2 approved; development plan/checkpoint defines five stages for scoped validation, base filtering, stale-base exclusions in update consumption, queued/shared recovery and actual-reader acceptance. 0.70 total reaffirmed, stable cycle/scope v3/original baseline/R1/P2/exposed rater retained; exact hashes verified. Reader thread-only replacement identified statically; explicit exclusion is inside approved Step 2. No runtime verification, measured effort or outcome acceptance; await Approved Step 3, plans uncommitted.

2026-10-23T20:16:56Z absent-target snapshot Step 4 closeout: canonical summary, branch feat/absent-retraction-snapshot, scope v3/original baseline/R1/P2/stable v3/absent_retraction_import retained. Planning fd4fa3839, four stage commits plus final Stage 5 commit; five scoped stages complete. 0.70 projection preserved, separate 0.80 retrospective scope assessment, Codex single exposed rater; exact R1 hashes verified. Direct/configured queued base/update publication, build-local exclusion/reappearance, later authority, stale-base/expansion removal, rootless post Likes and recovery delivered. Focused 57/57, final strengthened absent tests 11/11, browser 16/16; bounded frozen-doc import/static recovery 2/2. Optional frozen full suite interrupted after 75 passes/no recorded failures in long import acceptance; no full-suite claim. Real installed service-worker upgrade/physical devices/deployment/main merge/live repair or task retry unverified or outside scope. Zero dependency delta; no measured labor, independent outcome or accepted-count increment; maintainer fit/acceptance pending.

2026-10-23 task-list merge acceptance: user accepted the corrected appearance (“Good enough”) and authorized merging into main. Functional UAT accepted; study comfortable-fit judgment remains unknown, so no study accepted-count increment. Preserve v3/markdown_task_lists/v1 clarified/R1/P2, projected 0.35 and retrospective 0.40, prior failed appearance outcome and renewed evidence. Main integration retains all current main cycles/provenance; deployment, full suite and physical AT/device acceptance remain separate.

Cycle v3/unsigned_attribution

Stable cycle IDStatusScope / reference / protocolTotal projectionCanonical checkpointsParent / acceptance
v3/unsigned_attributionRestarted at Step 1 under PRINCIPLES.md; Step 1 approved (Option B, split; this cycle Option A); Steps 2 and 3 approved (scope v4); Stage 1 committed; Step 2 revised twice for changed scope (v5 cutoff, v6 default-off flag) and re-approved; Step 3 revision 2 approved; Stages 1–8 committed; Step 3 revision 3 (v7, signature check cache) approved and implemented in Stage 8 (63b65111); technically complete; earlier Step 1/2 superseded; maintainer acceptance pendingv3 / R1 / P21.0 intake (inherited); 0.80 at Step 1 (Option A, v1); about 1.35 for full Option E (v2), split at 0.65 this cycle + about 0.8 follow-up; 0.70 at Step 2 (v2); about 0.80 at Step 2 revision 2 (v3); about 0.80 at Step 1 restart (v3); about 0.75 at Step 2 (v3); about 0.90 at Step 2 revision 1 (v4); about 0.95 at Step 3 (v4); about 1.05 at Step 2 revision 2 (v5); about 1.0 at Step 2 revision 3 (v6); about 1.0 at Step 4 entry and re-entry (missing from this row until now); about 1.0 at technical closeout, retrospective about 1.05 (v6); about 1.1 at Step 3 revision 3 (v7)Intake and Step 1 snapshots; Step 2 (superseded); Step 1 restart; Step 2; Step 3; Step 4Legacy alias "Cycle A" of the agent API onboarding checklist; maintainer fit/acceptance pending

Enrolled under standing P2 policy. The intake value is inherited from the checklist, which the same rater wrote after inspecting the source; that exposure is disclosed, and no pristine prospective intake is claimed. The Step 1 reduction reflects new understanding (no read-model change is needed unless the audit finds forgeries), not a scope change. No implementation, measured effort, retrospective outcome or accepted-count increment is claimed. Step 1 revision 2 (2026-10-23) is a scope change to v2: hint-only voting must be kept, so Option A was ruled out and its 0.80 is superseded, not revised. A device-linking follow-up would get its own stable cycle ID.

2026-10-23 unsigned attribution Step 2 handoff: Approved Step 1 (Option E, split; this cycle only). Feature description/checkpoint refuses unsigned attributed posts and records hint-only and queued votes as unverified: in the visible tally, outside the approved score and profile links. Session-authenticated votes stay verified. Device linking stays in the follow-up. 0.70 projected, up from 0.65 as new understanding (server-recorded trust basis for session votes; existing signature status reused), not a scope change. Same scope v2/R1/P2 and exposed single rater; starting revision 9f33caff maps to 764fdd82 after the history rewrite. No implementation, measured effort or accepted-count change; awaiting Approved Step 2.

2026-10-23 unsigned attribution Step 2 revision 2: scope v3 after review against the new PRINCIPLES.md (accommodate first, verify later). Unsigned posts naming an identity are accepted as unverified instead of refused; verified means a valid record signature only, dropping the session exception; the reply agent signs its posts. About 0.80 projected, up from 0.70 (scope change). The v2 snapshot is preserved. Same R1/P2 and exposed single rater. No implementation or accepted-count change; awaiting Approved Step 2.

2026-10-23 unsigned attribution Step 1 restart: at the maintainer's request, a new Step 1 reassesses the cycle under PRINCIPLES.md; the earlier Step 1 and Step 2 are kept with a _superseded suffix and their approvals do not carry forward. Recommends Option B (accept and mark unverified, verified by signature only; signed claims later) split into this cycle (Option A, about 0.80, reaffirmed) and a claims follow-up (about 0.4, own cycle ID). Device-token linking (former follow-up) is no longer recommended. Same cycle ID, scope v3, R1/P2, exposed single rater. No implementation or accepted-count change; awaiting Approved Step 1.

2026-10-23 unsigned attribution Step 1 restart revision 1: Option B now verifies later by the owner's signed claim (always, takes precedence) or an approved member's signed vouch, shown distinctly and counted per a site feature flag. This cycle stays Option A at about 0.80 (reaffirmed); the follow-up grows to about 0.6, whole B about 1.4. Awaiting Approved Step 1.

2026-10-23 unsigned attribution Step 2 handoff (after restart): Approved Step 1 (Option B split; this cycle Option A). Feature description/checkpoint: accept and mark unverified, verified by signature only, reply agent signs, existing signature status wording reused, no per-client limits. About 0.75 projected, down from 0.80 as new understanding (no new server state). Same scope v3/R1/P2 and exposed single rater. No implementation or accepted-count change; awaiting Approved Step 2.

2026-10-23 unsigned attribution Step 2 revision 1: scope v4 adds one accept-unsigned-content site flag covering anonymous posts and unverified posts and votes, default on; off refuses unsigned writes with an explanation, hides anonymous controls and keeps drafts. About 0.90 projected, up from 0.75 (scope change); v3 snapshot preserved. Awaiting Approved Step 2.

2026-10-23 unsigned attribution Step 3 handoff: Approved Step 2 (revision 1, scope v4). Development plan/checkpoint: eight stages from a zenmemes impact audit through signed-only scoring and post attribution, unverified display, write responses, reply-agent signing, the accept-unsigned-content flag and release evidence. About 0.95 projected, up from 0.90 as new understanding (agent signing path, rebuild/incremental parity). Same R1/P2 and exposed single rater. No implementation or accepted-count change; awaiting Approved Step 3.

2026-10-23 unsigned attribution Stage 1 and Step 2 revision 2: planning commit 53e70490; Stage 1 e061eea9 audited zenmemes (884 of 1,550 attributed posts and 357 of 374 votes unsigned, nearly all from the instance's own identities). At the review gate the maintainer chose a per-instance cutoff so existing unsigned items keep counting; this is a scope change (v5) back to Step 2. About 1.05 projected, up from 0.95; a split moving the flag to its own cycle (to about 0.95) is offered. Implementation paused; awaiting renewed Approved Step 2.

2026-10-23 unsigned attribution Step 2 revision 3: maintainer kept today's behavior as the default. The rule moves behind a default-off verified attribution flag; the cutoff is written when the flag is first turned on and shown to operators, who can move it. The accept-unsigned-content flag moves to its own cycle. Scope v6, about 1.0 projected, down from 1.05. Same R1/P2 and exposed single rater. Implementation paused after Stage 1; awaiting renewed Approved Step 2.

2026-10-23 unsigned attribution Step 3 revision 2: Approved Step 2 (revision 3, scope v6). Development plan/checkpoint: flag and cutoff first, then verified totals kept beside today's for votes and posts, display, responses, agent signing and release evidence. About 1.0 reaffirmed. Same R1/P2 and exposed single rater. Awaiting Approved Step 3.

2026-10-23 unsigned attribution Step 4 re-entry and Stage 2: Approved Step 3 (revision 2). Entry about 1.0 reaffirmed (scope v6). Stage 2 adds the default-off verified attribution flag, a cutoff taken from the signed first switch-on, and signed operator moves shown on the Feature Flags page. No change to the projection; implementation continues at Stage 3.

2026-10-26 unsigned attribution technical closeout: Stages 3–7 implemented and Stage 8 run after merging origin/main (0888609c; schema renumbered 26 → 31). Step 4 snapshot: projection about 1.0 reaffirmed, retrospective scope assessment about 1.05 (Stage 3 label gap fixed in Stage 4, Word97 contrast fix, merge renumbering). Full suite: 9 failures, 7 shared with main and 2 intermittent. zenmemes counts are unchanged with the flag off and on (cutoff now). Same scope v6/R1/P2 and exposed single rater; measured effort unknown. Maintainer acceptance pending; no accepted-count change.

2026-10-26 unsigned attribution Step 3 revision 3: Stage 8 timing showed signature checks rerun on every rebuild and write with the flag on (74 s zenmemes rebuild with an August cutoff). The maintainer asked for cached check results; changed scope (v7), folded into Stage 8. Step 3 snapshot: about 1.1 projected, up from about 1.0; the v6 closeout retrospective (about 1.05) is preserved. Same R1/P2 and exposed single rater. No implementation; awaiting Approved Step 3.

2026-10-27 unsigned attribution Step 4 re-entry and Stage 8 cache: Approved Step 3 (revision 3). Signature check cache committed in 63b65111: zenmemes rebuild with an August cutoff 67.8 s first, 1.4 s second with no GPG runs; full suite 7 failures (6 shared with main, 1 intermittent). Step 4 snapshot: about 1.1 reaffirmed (v7). Same R1/P2 and exposed single rater; measured effort unknown. Maintainer acceptance pending; no accepted-count change.

Cycle v3/high_traffic_absent_retractions

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/high_traffic_absent_retractionsLocal implementation complete; production/maintainer acceptance pendingv1 / R1 / P20.75Intake and Step 1Follow-up to v3/absent_retraction_import; acceptance pending

2026-10-24T04:47:13+00:00: standing P2 enrollment, baseline bce2c29e37be4a06a25e2a3c6e022249e8d90101; source/production-report/reproduction exposure disclosed before intake. Codex single exposed rater, exact R1 hashes verified; 0.65 total for safe high-traffic publication with absent-target exclusions, stale-content/concurrency verification and operator recovery. Earlier diagnosis included, no pristine intake or measured labor claimed. Same cycle across worktrees; no independent split outcome or accepted-count increment. Planning updates remain uncommitted.

2026-10-24T05:06:56+00:00: high-traffic absent retractions Step 2 handoff: Step 1 Option A explicitly approved. Requirements/checkpoint defines normal cold/refresh/warm serving, absent-target and attributable-content exclusion, concurrency/privacy safety and same-host operator recovery. 0.65 total reaffirmed, same stable cycle/v1/original baseline/R1/P2/exposed rater. Production re-enable and missing refresh-cron setup are operator acceptance steps; local acceptance does not establish host success. Offline-bootstrap fatal handling explicitly deferred. No implementation, measured labor or accepted outcome; await Approved Step 2.

2026-10-24T05:09:04+00:00: high-traffic absent retractions Step 3 handoff: Step 2 approved. Plan/checkpoint contains five stages for scoped admission, safe HTML render input, normal cache/refresh wiring, races/shared recovery and Apache/operator acceptance. 0.75 projected total, revised from 0.65 after inspecting full-model summaries/ownership and renderer isolation requirements; scope v1/original baseline/R1/P2/exposed rater unchanged, prior snapshots retained. Frozen R1 hashes verified; no independent rating, measured labor or accepted outcome. Implementation unapproved; await Approved Step 3.

2026-10-24T05:21:41+00:00: high-traffic absent-target Step 4 closeout: summary and study outcome. Same scope v1/original baseline/R1/P2/stable cycle and exposed rater. Planning bf659506f plus five stage commits on fix/high-traffic-absent-retractions; safe excluded derivation, normal cache/refresh, races and Apache/browser recovery delivered locally. Final focused 108/108, bounded static/import 2/2, actual Apache and browser checks passed. 0.75 projected total retained; retrospective scope assessment 0.75, measured labor unavailable, maintainer fit/acceptance pending. Production deployment/cache-hit/cron checks and physical devices/full suite unverified; no accepted-count increment. Zero dependency delta, no core schema change or canonical repair. Deferred offline-bootstrap fatal handling retained.

2026-10-24T05:43:09+00:00: production follow-up for v3/high_traffic_absent_retractions: refresh failed after 36.325 seconds at the generic worker-limit check. Production timeout checkpoint preserves failed host acceptance and records precise limit/stage diagnostics (19/19 focused checks). Existing 0.65/0.75 projections and 0.75 retrospective scope record remain historical; no new numeric estimate, measured labor or accepted outcome invented. Production performance repair pending stage evidence; zero dependency change.

Cycle v3/retraction_sweep_diagnostics

2026-10-24T05:12:43Z: standing P2 enrollment; scope v1/R1, baseline 4f75d2a1a5a1905d2af22473271aaa942929ff75. Canonical intake and Step 1 handoff (planning artifact deleted at user request on 2026-10-24): 0.85 projected total, reaffirmed at handoff, Codex single exposed rater after report/planning/reference and limited reader/CLI inspection; no pristine intake reconstructed. Exact frozen R1 hashes verified. Recommend bounded read-only diagnostics with CLI/JSON/status/worker reasons and unchanged cleanup authority. Related original sweep and absent-target snapshot cycles remain distinct; no implementation, live repair, measured work or accepted-count increment. Await Approved Step 1; planning/ledger uncommitted.

2026-10-24T05:19:50Z retraction sweep diagnostics Step 1 revision: canonical extended-estimate record (planning artifact deleted at user request on 2026-10-24) enables the extension for this cycle following the requested v0.3.0-beta.1 assessment update. First current A/B/C v1 whole-cycle ratings 0.85 / 1.30 / 0.40, with subjective ranges and split recommendation for B; formal recommended A total 0.85 reaffirmed. Stable v3/retraction_sweep_diagnostics, scope v1/original baseline/R1/P2 and single exposed rater unchanged; exact hashes reverified, prior checkpoints retained. No backfill, implementation approval, measured effort or accepted-count change; planning uncommitted on main after separately authorized upgrade merge.

2026-10-24T05:21:25Z retraction sweep diagnostics Step 2 handoff: Step 1 Option A explicitly approved; canonical requirements/checkpoint (planning artifact deleted at user request on 2026-10-24) define bounded read-only diagnosis, unchanged cleanup authority, human/JSON and private run/status/worker reason propagation, production recovery guidance and failure/redaction/permission verification. 0.85 total reaffirmed; stable v3/retraction_sweep_diagnostics, scope v1/original baseline/R1/P2/exposed single rater retained, exact frozen hashes reverified. Extended estimates inherited; no stage estimates yet. Ledger bookkeeping included in scope; no implementation, live repair, measured effort or accepted-count change. Await Approved Step 2; planning uncommitted.

2026-10-24 — Canceled at user request: delete the retraction sweep diagnostics plan rather than implement it. Step 1, Step 2 and the associated debug log were removed; preceding checkpoint values, stable cycle ID, R1/P2, exposure and Step 1 approval history remain above. Step 2 was not approved and no implementation was performed. Proposed direction is immediate canonical content deletion plus a retained retraction record in the same commit, with later history purge and accepted delayed unavailability; this does not authorize implementation. Existing diagnostics report is retained as historical evidence. This supersedes the earlier awaiting-approval status; no completed or accepted outcome, no measured effort or new score.

Cycle v3/retraction_simplification

2026-10-24T16:26:32Z — standing P2 enrollment, scope v1/R1, baseline 22134259876481199aacff6f6b2cd39a811236a9. Canonical intake and Step 1 handoff: 1.50 projected total, reaffirmed for the full proposed Option A outcome: immediate deletion plus retained record, migration and reduced publication coupling, followed by repeatable history purge and recovery. Codex single exposed rater after source/reference inspection and review of newer ~/v3 publication work at 2d91c8029; exact R1 hashes verified, no pristine intake reconstructed. Recommend a two-release split; no child scope/estimate or accepted outcome created. Related diagnostics cycle remains canceled; existing retraction/snapshot/high-traffic cycles retain their history. Extended estimates not enabled for this new cycle. Await Approved Step 1; no implementation, live purge, measured effort or accepted-count increment. Planning and study updates uncommitted.

2026-10-24T17:14:30Z — retraction simplification Step 2 handoff: Step 1 Option A/two-release split explicitly approved. Requirements/checkpoint scope v2 to release 1: delete-and-record, migration, decoupled publication, ordinary refresh and repeatable deferred local cleanup; history purge remains a separately planned release and the original full outcome remains incomplete. 1.00 projected total for this scoped cycle from the original baseline, independently judged rather than subtracted from the preserved v1 1.50 full-outcome projection. Stable v3/retraction_simplification, R1/P2/original baseline, Codex single exposed rater; exact frozen hashes reverified. No independent child outcome, measured work or accepted-count change. Extended estimates remain disabled; debug enabled. Await Approved Step 2; planning uncommitted, no implementation/live purge.

2026-10-25 UTC — retraction simplification Step 3 handoff: Step 2 explicitly approved before the separately completed Railspike beta.3 upgrade. Development plan/checkpoint retains v2/release 1, original baseline/R1/P2/stable v3/retraction_simplification; 1.00 projected total reaffirmed, including signed legacy migration, absence-safe readers/imports, decoupled publication, complete deferred cleanup and actual-flow recovery verification. Eight planned/zero completed stages. Exact frozen hashes verified; Codex single exposed rater, current source df313cf0, other checkout 63314e6cf, prior exposure retained. Extended estimates remain disabled; debug enabled. Original v1 1.50 and v2 Step 2 1.00 retained; no measured effort, independent child observation or accepted-count change. Plans remain uncommitted awaiting Approved Step 3; history purge remains separate and unimplemented.

2026-10-25T18:04:54Z — explicit user activation of extended estimates for v3/retraction_simplification, applied to all three existing plans. Earlier disabled state and missing original option/stage ratings remain historical. First current Step 1 option ratings: A/v1 1.50, B/v1 1.80, each full two-release scope; recommendation/split unchanged. Step 2 and Step 3 release-1/v2 whole-cycle 1.00 independently reaffirmed. First current supplemental stage-work values S1/v1–S8/v1: 0.20, 0.20, 0.30, 0.25, 0.25, 0.30, 0.20, 0.25; not additive or measured time. Stage 8 owns shared acceptance/closeout. Original baseline/R1/P2, exact frozen hashes verified, single exposed Codex rater retained; no independent outcome or accepted-count change. Existing Step 1/2 approvals preserved, Step 3 still awaits approval; documentation only, uncommitted.

2026-10-25T19:13:19Z — retraction simplification Step 4 closeout: Step 3 explicitly approved; entry, eight stages and outcome. Same stable v3/retraction_simplification, v2/release 1/original baseline/R1/P2 and exposed single Codex rater. 1.00 original projection preserved; separate retrospective scope assessment 1.10. Extended S1–S8 original values retained; retrospectives 0.20, 0.20, 0.30, 0.25, 0.25, 0.30, 0.20, 0.40. Planning fd5c6849 plus eight scoped stage commits; final revision recorded in debug handoff. Immediate deletion/retained record, migration, reader/import compatibility, removed publication gates and stateless deferred cleanup delivered locally. Final PHP regression 122/122, API 18/18, browser/theme/menu/offline and 18,931-artifact QDB-derived CLI acceptance pass. Full-suite results and reproduced baseline failures are explicitly retained; no all-green claim. Production recovery/deployment/merge, physical devices and maintainer comfortable-fit/acceptance pending. History purge/release 2 remains unimplemented, original full outcome incomplete. Zero dependency delta; no measured labor, independent outcome or accepted-count change. Earlier canceled diagnostics cycle retained, not revived.

2026-10-25: v3/repository_archive_readme locally complete on feat/repository-archive-readme. Closeout preserves original baseline, all 0.25 projections and scope v2. Retrospective cycle scope 0.25, single exposed Codex rater, R1/P2; extended mode disabled. Three stages deliver shared tar/ZIP guidance, collision-safe notes and normal download/import/image recovery. Focused 25/25 passed after correcting the initially invalid direct-import instruction. No packages, schema/UI changes or deployment; full suite not run. Measured labor unavailable, maintainer comfortable-fit/acceptance pending, accepted-outcome count unchanged. Worktree copies represent the same observation.

2026-10-26 image ZIP Step 4 closeout: canonical summary. Step 3 approved; stable v3/image_backup_zip, scope v1/original baseline/R1/P2, same exposed single Codex rater. 0.40 projection retained; separate retrospective cycle scope 0.40. Three stages complete, original stage estimates 0.18/0.12/0.08 and separately labeled retrospective assessments retained; extended mode enabled. Planning 7256340b2, stages a74b1c97e, 29ed6b06d and final closeout commit. Focused 31/31, actual browser ZIP download/extraction/CLI verify/restore/rebuild, restored byte identity, Apache ZIP/TAR/access checks and 14-theme phone/desktop UI checks passed. Browser fixture race and history-free writable-restore assumption corrected and recorded. Frozen hashes verified, zero dependencies/schema changes; no measured labor or independent split outcome. Full suite, physical devices, deployment, merge/push and maintainer comfortable-fit/acceptance remain pending; accepted-outcome count unchanged.

Cycle v3/archive_export_contention

Status: Step 1 proposed; standing P2 enrollment; no parent/replacement cycle; same ID across worktrees. Scope: v1 / R1 / P2; starting revision 28530e1b59b6b5d98d314bc080dda94588cc4217; bounded export waiting, safe retry and operator recovery, including ledger bookkeeping. Canonical checkpoints: Intake and Step 1 handoff, 2026-10-25T22:41:57Z; intake 0.45 and handoff 0.45 reaffirmed; extended estimates enabled (A 0.45, B 0.90, C 0.25, alternative whole cycles). Rater: Codex single exposed rater after prior source/reproduction and reference review; exact frozen R1 hashes verified; no pristine intake, independent rating or measured labor claimed. Outcome: Await Approved Step 1; no implementation, deployment, commit or accepted-count increment. Production lock ownership remains unverified. Planning and ledger updates remain uncommitted.

2026-10-26T00:28:58Z — v3/archive_export_contention Step 1 revision: user selected Option B. Canonical revision scope v2 now covers reusable validated tar/ZIP/image archives, coordinated builds, freshness/invalidation, bounded storage/eviction and interrupted-build/retry/operator recovery. Projected total 0.90 (B reaffirmed), superseding original v1/A 0.45; original intake and handoff preserved. Same baseline/R1/P2 and exposed single Codex rater; exact frozen hashes reverified. No independent outcome, measured labor, implementation or accepted-count change. Await Approved Step 1; planning updates uncommitted.

2026-10-26T00:35:42Z — v3/archive_export_contention Step 2 handoff: Step 1 Option B explicitly approved. Requirements/checkpoint defines reusable archives, freshness/revision eligibility, coordinated builds, bounded storage/waits and safe cleanup/retry through normal download routes, with separate qdb.us evidence. Whole-cycle 0.90 reaffirmed; same v2/original baseline/R1/P2, extended mode and exposed single Codex rater; frozen hashes reverified. Prior v1 0.45 preserved. No implementation, measured labor or accepted-count increment; await Approved Step 2, documentation uncommitted.

2026-10-26T00:57:42Z — v3/archive_export_contention Step 3 handoff: Step 2 approved; development plan/checkpoint defines six stages covering freshness, reusable delivery, coordinated builds, HTTP recovery, bounded lifecycle and route/browser/operator acceptance. Whole-cycle 0.90 reaffirmed independently; first stage-work S1–S6 estimates 0.20, 0.25, 0.20, 0.15, 0.25, 0.20, non-additive. Same v2/baseline/R1/P2 and exposed single Codex rater; frozen hashes verified; prior scores preserved. Current per-request archive deletion and non-Git image changes explicitly covered. Production evidence pending; no implementation, measurement or accepted-count increment. Await Approved Step 3; plans uncommitted.

2026-10-26T02:53:15Z — v3/archive_export_contention Step 4 local closeout: summary and evidence. Same v2/Option B/original baseline/R1/P2 and exposed single Codex rater; frozen hashes verified. Six stages implement validated reusable archives, bounded coordination/storage, protected transfers, HTTP recovery and operator handoff. Original projected 0.90 preserved; retrospective cycle scope 0.95. Original S1–S6 stage-work values retained; retrospectives 0.20, 0.25, 0.20, 0.15, 0.25, 0.25. Final targeted PHP 33/34, one identical starting-revision failure in obsolete filename test; final strengthened checks 3/3 and real HTTP/browser acceptance pass. Synthetic 19,000-post cold/warm 9.299/0.416 seconds is runtime evidence, not labor measurement. Zero dependency delta; full suite, deployment/merge, physical devices, qdb.us lock/recovery and maintainer fit pending. No accepted-count increment, measured labor or independent child outcome. Planning plus six stage commits on fix/archive-export-contention; prior checkpoints preserved.

2026-10-26 — v3/import_record_failure_isolation direct repair: user explicitly requested implementation after review, superseding pending staged approvals for this repair. Canonical review/outcome narrows v2 to the reproduced signed-label classification and fallback-key defects plus CLI/recovery regression protection. Same original baseline/R1/P2/stable ID and single exposed Codex rater; R1 hashes verified. Original v1 0.45 projection retained; prospective v2 checkpoint missing, not reconstructed. Separate retrospective v2 scope assessment 0.30. Legacy extended mode disabled. Broader v1 isolation redesign remains incomplete; no independent child outcome, measured labor or accepted-count increment. Repair uncommitted; maintainer acceptance pending.

Cycle v3/backup_feature_flags

Status: Step 1 proposed; standing P2 enrollment; same stable ID across worktrees; no parent/replacement cycle. Existing archive work is reused. Scope: v1 / R1 / P2; baseline 2acea7d8ca05793cef7face657a793f130a76761; two independent operator flags, direct/cached download enforcement, UI availability and re-enable recovery, including SQLite behavior and ledger bookkeeping. Canonical checkpoints: Intake and Step 1 handoff, 2026-10-26T07:52:12Z; exposed intake 0.40 and handoff 0.40 reaffirmed. Extended estimates enabled: A/v1 0.40, B/v1 0.30, alternative whole cycles. Rater: Codex single exposed rater after source/reference inspection; all three frozen R1 hashes verified; pristine pre-inspection intake missing, not reconstructed. Outcome: Await Approved Step 1; documentation uncommitted. No implementation, independent outcome, measured labor or accepted-count increment; maintainer acceptance pending.

2026-10-27T00:30:46Z — v3/backup_feature_flags Step 2 handoff: Step 1 approved, recommended Option A. Requirements and checkpoint retain independent text (including SQLite) and image controls, cache/direct-request enforcement, normal UI and re-enable recovery. Whole-cycle 0.40 reaffirmed; same scope v1/original baseline/R1/P2, extended mode and exposed single Codex rater; all frozen hashes reverified. Prior scores retained. Await Approved Step 2; no implementation, commit, measured labor, independent outcome or accepted-count increment.

2026-10-27T01:13:18Z — v3/backup_feature_flags Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines four stages: text/SQLite control, image control, shared navigation/cache transitions, and normal-flow acceptance/operator handoff. Whole-cycle 0.40 independently reaffirmed; first S1–S4/v1 stage-work values 0.15, 0.10, 0.10, 0.10, non-additive. Same scope v1/original baseline/R1/P2 and exposed single Codex rater; frozen hashes reverified and prior scores preserved. Await Approved Step 3; no implementation, measured labor, accepted outcome or accepted-count increment. Documents uncommitted.

2026-10-27T01:33:10Z — v3/backup_feature_flags Step 4 local closeout: summary, stages and release limits. Four stages deliver independent default-enabled text/SQLite and image controls, enforced direct/cached requests, shared UI/cache availability and recovery. Original projection 0.40 preserved; retrospective cycle scope 0.45. Original S1–S4 stage-work 0.15/0.10/0.10/0.10 retained; retrospectives 0.15/0.10/0.10/0.15, non-additive. Scope v1/Option A/original baseline/R1/P2 and single exposed Codex rater unchanged; frozen hashes reverified. Focused PHP 61/61, final strengthened checks 8/8, smoke 7/7, signed Chromium acceptance 240 states and four existing browser suites pass. Baseline feature-flag activity-link failure reproduced and preserved; no full-suite, deployment, physical-device or maintainer acceptance claim. Zero dependency delta; no measured labor, independent outcome or accepted-count increment. Planning plus four stage commits on feat/backup-feature-flags; no merge/push.

Cycle v3/profile_public_details

Status: Step 1 proposed; standing P2 enrollment; distinct corrective follow-up to member-directory/access split, same ID across worktrees. Scope: v1/A / R1 / P2; baseline 93c3ea8132df45fd5b334f05758a144fdb90e78e; direct public key and identity-specific visible activity, count alignment, empty/paginated recovery, verification and documentation/ledger upkeep. Canonical checkpoints: Intake and Step 1, 2026-10-27T01:21:50Z; intake 0.50, handoff 0.50 reaffirmed; extended estimates enabled (A 0.50 / B 0.60, alternative whole cycles). Rater: Codex single exposed rater after prior history/source/live-page inspection; all three frozen R1 hashes verified. Pristine pre-inspection intake missing; no reconstructed earlier score, measured labor or independent rating. Outcome: Await Approved Step 1; no implementation, deployment, commit or accepted-count increment. Planning and ledger updates remain uncommitted; predecessor history preserved.

2026-10-27T01:47:19Z — v3/profile_public_details Step 2 handoff: Step 1 Option A explicitly approved. Requirements and checkpoint define collapsed key display/copy, identity-scoped authored threads/posts, visibility/count agreement, bounded history/recovery and shared-view compatibility. Whole-cycle 0.50 reaffirmed, same v1/A/original baseline/R1/P2 and exposed single Codex rater; exact frozen hashes verified. Shared guidance separately committed at user request in d28ea9165; profile plans remain uncommitted. No implementation, deployment, measured labor or accepted-count increment; zenmemes.com acceptance pending and distinct from local verification. Await Approved Step 2.

2026-10-27T01:55:37Z — v3/profile_public_details Step 3 handoff: Step 2 explicitly approved. Plan and checkpoint defines five stages for eligibility/counts and startup rebuild, key disclosure/copy, bounded identity history, host/static parity and acceptance. Whole-cycle projection 0.60 revises earlier 0.50 for newly explicit query-schema/startup and dual-pagination verification obligations; v1/A outcome, original baseline/R1/P2 and single exposed Codex rater retained, exact hashes verified. First S1–S5 stage-work estimates 0.18/0.12/0.22/0.14/0.16 are non-additive. No application work, measured labor or accepted outcome; plans uncommitted, zenmemes.com acceptance pending. Await Approved Step 3.

2026-10-27 UTC — v3/profile_public_details Step 4 local closeout: entry, stages and outcome. Same v1/A/original baseline/R1/P2, exact frozen hashes verified, single exposed Codex rater. Original projected 0.60 retained; separate retrospective cycle scope 0.60. Original S1–S5 0.18/0.12/0.22/0.14/0.16 retained; retrospective stage-work 0.18/0.12/0.22/0.10/0.16. Five stages deliver collapsed copyable key, identity-scoped histories/counts, bounded independent pagination and serving/recovery compatibility. Focused PHP 42/42 plus messaging 5/5; actual HTTP Chromium JavaScript on/off, 13 themes at phone/desktop widths, copy/navigation recovery, startup schema-30 rebuild and final CLI rebuild passed. Zero dependency delta; schema 31 query contract, no new tables/canonical changes. No measured labor or independent child outcome. Deployment/zenmemes.com replay, physical devices, full suite, merge/push and maintainer comfortable-fit acceptance pending; accepted count unchanged. Planning 81e1d51b7 and five stage commits on feat/profile-public-details; prior snapshots preserved.

Cycle v3/import_archive_hardening

2026-10-27 — standing P2 enrollment; scope v1 / R1; baseline 00c84badd8832ed9e81fa0980c670283ae9fa318. Canonical intake and Step 1 handoff: intake at 00:12:50Z 0.90, handoff 0.90 reaffirmed for shared admission limits plus bounded parsing, dependency propagation, GPG execution and normal CLI/recovery verification. Extended estimates enabled; alternative whole-cycle A/B/C estimates 0.90 / 0.40 / 0.80, not additive. Codex single exposed rater after the prior adversarial source review/reproductions and reference exposure; exact frozen R1 hashes verified, no pristine pre-review score invented. Related predecessor v3/import_record_failure_isolation retains its own repair and incomplete broader scope; this is a distinct follow-up, deduplicated across worktrees. No implementation, measured labor, independent rating or accepted-count increment. Await Approved Step 1; assessment/debug/ledger updates uncommitted.

2026-10-27 — v3/import_archive_hardening Step 2 handoff: Step 1 Option A explicitly approved. Requirements/checkpoint defines shared direct/indirect admission, filename policy, bounded text/dependency processing, invocation/GPG budgets, WSL CLI outcomes, truthful partial reports and interrupted-write/publication recovery. Whole-cycle 0.90 reaffirmed; same v1 clarified/original baseline/R1/P2, extended mode and single exposed Codex rater. Exact frozen reference hashes reverified; prior snapshots retained. Shared authentication/write compatibility and timeout lifecycle validation are release gates. No implementation, measured labor or accepted-count increment; await Approved Step 2, documentation uncommitted.

2026-10-27 — v3/import_archive_hardening Step 3 handoff: Step 2 approved. Development plan/checkpoint covers eight stages for lifecycle feasibility, bounded text, shared admission, dependency propagation, GPG bounds, invocation deadline, durable recovery and normal WSL acceptance. 1.00 whole-cycle projection, revised from preserved 0.90 intake/Step 1/Step 2 after inspection of blocking children, promotion windows and verifier callers; same v1 clarified/original baseline/R1/P2 and exposed single Codex rater. First stage-work S1–S8/v1: 0.15, 0.15, 0.25, 0.20, 0.25, 0.30, 0.25, 0.20, non-additive; S8 owns shared closeout. Exact frozen hashes verified; extended mode retained. Eight planned/zero completed, no implementation, measured work or accepted-count increment. Await Approved Step 3; planning records uncommitted.

2026-10-27 — v3/import_archive_hardening Step 4 local closeout: summary and evidence. Same scope v1 clarified/original baseline/R1/P2, extended mode and single exposed Codex rater; earlier checkpoints preserved. Original Step 4 projection 1.00 retained; separate retrospective cycle scope 1.05. S1–S8 original estimates retained; stage retrospectives 0.15, 0.10, 0.25, 0.20, 0.25, 0.30, 0.25, 0.25 (non-additive). Eight stages implement bounded reads/parser/dependency work, GPG and invocation supervision, durable recovery and operator documentation. Combined targeted regression 130/130, final additional guard checks 20/20; isolated WSL ZenMemes preview/import/repeat/resume and served HTTP/offline acceptance passed with truthful partial-source reporting. Zero dependency/schema/UI delta. Full suite, deployment, merge, physical-device validation and maintainer comfortable-fit/acceptance pending. No measured labor, independent rating or accepted-count increment; deduplicate worktree copies. Final stage revision recorded in cycle debug handoff.

Cycle v3/qr_theme

2026-10-27 UTC — standing P2 enrollment; canonical Step 1 checkpoint. Scope v1/A, baseline 085c47701f57334164f7fe1c562454443cd65596, R1 exact three hashes verified. Projected total 0.30 for restrained theme coloring, live switching, preserved invitation/copy recovery and cross-theme verification; alternative B/v1 frame-only total 0.15, not additive. Extended estimates and debug enabled. Codex single exposed rater after source and prior acceptance inspection; pristine pre-inspection intake missing, not reconstructed. Related invite QR predecessor retains its outstanding acceptance; no parent replacement or independent child outcome. Await Approved Step 1; documentation uncommitted, no implementation, measured labor or accepted-count increment. Deduplicate by stable cycle ID across worktrees.

2026-10-27 UTC — v3/qr_theme Step 2 handoff: Step 1 Option A explicitly approved. Requirements/checkpoint retain scope v1/A/original baseline/R1/P2 and whole-cycle 0.30 reaffirmed. Contrast eligibility, effective-theme transitions, stale-result protection, copy recovery and separate physical-camera acceptance clarify the same outcome. Exact frozen hashes reverified; debug/extended modes and single exposed Codex rater retained. Earlier Step 1 and missing pristine intake preserved. Await Approved Step 2; no implementation, commits, measured labor or accepted-count increment.

2026-10-27 UTC — v3/qr_theme Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines safe generation, live synchronization and normal-flow acceptance. Whole-cycle 0.30 independently reaffirmed; first S1–S3/v1 stage-work estimates 0.10/0.10/0.10, not additive. Same v1/A/original baseline/R1/P2, enabled debug/extended modes and single exposed Codex rater; exact frozen hashes reverified. LCD variants/deferred CSS clarify verification within approved scope. Earlier scores/missing pristine intake preserved; three planned/zero completed. Await Approved Step 3; planning remains uncommitted, zero dependency changes, no implementation, measured labor or accepted-count increment.

2026-10-27 UTC — v3/qr_theme Step 4 local closeout: entry, stage evidence and release limits. Step 3 explicitly approved; original whole-cycle projection 0.30 retained, separate retrospective scope 0.35. S1–S3 original stage work 0.10/0.10/0.10 preserved; retrospectives 0.10/0.10/0.15, non-additive. Same v1/A/original baseline/R1/P2, enabled extended/debug modes and single exposed Codex rater. Three stages deliver guarded theme colors, live theme/palette/stylesheet/forced-color synchronization and existing copy/failure recovery. 38 actual theme/palette/viewport combinations decode raw and displayed pixels correctly with qualifying contrast/margins/layout; actual Copy/redemption and focused JS/browser/PHP checks pass (PHP 9/9, public and members-only browser flows). Tooling/profile harness corrections are recorded separately. Zero repository dependency/schema delta; planning plus three stage commits on feature/qr-theme. Physical-camera, full-suite, deployment and maintainer comfortable-fit/acceptance remain pending or unverified; no measured labor, independent outcome, split or accepted-count increment. Earlier intake omission and score history retained; deduplicate worktree copies.

Cycle v3/invite_signing_readiness

2026-10-27 UTC — standing P2 enrollment; Step 1 checkpoint. Scope v1/A, baseline 89a9abbe044a39240a30ab7787977ce735050762, R1 exact frozen hashes verified. Projected whole-cycle 0.50 for real reproduction, consistent session/signing identity, normal direct Invite entry and in-place recovery; alternative B/v1 bounded mismatch retry 0.35, not additive. Extended/debug enabled; single exposed Codex rater after source and predecessor-test inspection. Pristine pre-inspection intake missing, not reconstructed. Distinct reliability follow-up to v3/qr_theme; no evidence that coloring caused the reported signature rejection. Await Approved Step 1; no implementation, measured labor, independent outcome or accepted-count increment. Records uncommitted; deduplicate worktrees by stable ID.

2026-10-27 UTC — v3/qr_theme maintainer visual feedback: review and disposition. User reports most themes still look black/white with a conspicuous white border; visual acceptance failed despite prior pixel/layout passes. Original projection 0.30 and retrospective 0.35 retained. Light-on-dark feasibility discussed; it changes the approved polarity requirement and is not authorized by a question alone. Visual follow-up and physical-camera acceptance remain unresolved; no new implementation, score, measured labor or accepted-count increment. Signing reliability is separately enrolled as v3/invite_signing_readiness.

2026-10-27 UTC — v3/invite_signing_readiness Step 2 handoff: Step 1 Option A explicitly approved. Requirements/checkpoint retain whole-cycle 0.50, v1/A/original baseline/R1/P2 and single exposed Codex rater. Direct Invite entry without Account preconditioning, real cryptographic reproduction, identity consistency, bounded known-pre-write recovery, preserved keys/approval/destination and ambiguous-outcome handling clarify the approved outcome. Frozen hashes reverified; extended/debug modes retained. Earlier projections and missing pristine intake preserved. Await Approved Step 2; no implementation, commits, measured labor or accepted-count increment. QR visual follow-up remains separate and pending.

2026-10-27 UTC — v3/invite_signing_readiness Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines four stages: real direct-entry reproduction, issuer reconciliation, identity-bound signing/recovery and normal-flow acceptance. Whole-cycle 0.50 independently reaffirmed; original S1–S4/v1 stage work 0.10/0.15/0.15/0.15, non-additive. Same v1/A/original baseline/R1/P2 and single exposed Codex rater; exact frozen hashes reverified. Diagnosis remains an implementation gate; previous projections and missing pristine intake retained. Four planned/zero completed, no implementation, measured labor or accepted-count increment. Await Approved Step 3; records uncommitted and unrelated QR review edits preserved separately.

2026-10-27 UTC — v3/invite_signing_readiness authorized diagnostic: reproduction evidence demonstrates repeated exact signature rejection followed by Account recovery with unchanged keys in both access modes. Same-page authentication control passes; public mode also reproduces with a correct cached fingerprint and missing Invite authentication helper. Whole-cycle 0.50 and original stage-work values explicitly reaffirmed, same v1/A/original baseline/R1/P2/exposed rater. New evidence resolves the suspected session/key mechanism without establishing how the user's state arose. This was a bounded diagnostic authorization, not Approved Step 3; no product implementation or stage completion, no measured labor or accepted-count increment. Evidence and planning remain uncommitted.

2026-10-27 UTC — v3/invite_signing_readiness Step 4 local closeout: entry, stages and release limits. Step 3 approved; same v1/A/original baseline/R1/P2 and single exposed Codex rater. Original cycle projection 0.50 retained; separate retrospective cycle scope 0.60. Original S1–S4 stage work 0.10/0.15/0.15/0.15 preserved; retrospectives 0.10/0.15/0.20/0.15, non-additive. Four stages reproduce and fix session/signing-key disagreement, await authentication, bind the signing key and safely inspect uncertain outcomes without reissuance. Real public/members-only direct-entry, identity-race, negative-signature, lost-response, permission, restore/retry, recipient and revocation cases pass; 160 rendered states and 112 focused PHP checks plus Node/browser suites pass. Frozen hashes reverified; zero dependency/schema delta, no measured labor or accepted-count increment. Planning plus four stage commits on feature/invite-signing-readiness; user-device/production/full-suite and maintainer comfortable-fit acceptance pending or unverified. QR appearance remains separate and unresolved; preserve original scores and deduplicate worktrees.

Cycle v3/text_backup_start_latency

Status: Step 1 proposed; standing P2 enrollment; distinct follow-up to v3/archive_export_contention, same ID across worktrees. Scope: v1/A / R1 / P2; baseline c349d7fe12cfb651cd4002fc51ac299d5907dd58; measure and streamline validated content-backup download preparation, including normal-route retry, verification and ledger upkeep. Canonical checkpoints: Intake and Step 1, 2026-10-26T17:49:57Z; intake and handoff 0.65; extended estimates enabled, A 0.65 / B 0.95 / C 0.90, alternative complete cycles. Rater: Codex single exposed rater after source and predecessor-plan inspection; all three frozen host-local R1 hashes verified. Pristine pre-inspection intake missing; no reconstructed earlier score, measured labor or independent rating. Outcome: Await Approved Step 1; production 5–7-second delay is user-reported, not independently timed. No implementation, deployment, commit or accepted-count increment. Predecessor outcome and pending host acceptance preserved.

Cycle v3/high_traffic_toggle

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/high_traffic_toggleLocally complete; maintainer acceptance pendingv3 / R1 / P20.20Intake and Step 1; Step 2; Step 3; Step 4 entry and closeoutFollow-up UI cleanup of high_traffic_mode; acceptance pending

2026-10-27T02:06:46Z: standing P2 enrollment, baseline 6e32cd093e76da88820388159de08c95e7bd9a0d. Intake 0.25 before toggle-source inspection; Step 1 handoff 0.20 for recommended Option A (switch row under Feature Flags heading). Extended options A 0.20, B 0.35, C 0.50, not additive. Claude Code single exposed rater, exact R1 hashes verified. No implementation, measurement or accepted outcome; planning remains uncommitted.

2026-10-27 UTC: user chose Option C; scope v2 is a dedicated Tools › High traffic page with launcher/subnav entries and theme icons. 0.50 projected total, adopting C/v1 unchanged; earlier 0.25 intake and 0.20 Step 1 retained. Same baseline/R1/P2/rater; no implementation or approval.

2026-10-27 UTC: Step 1 Option C approved. Step 2 handoff 0.50 reaffirmed, scope v2 unchanged; capability-filtered tools registry and browser-test move fit the estimate. Same baseline/R1/P2/rater; no implementation or accepted outcome.

2026-10-27 UTC: user returned to Step 1 and chose Option A; scope v3 (switch row under Feature Flags heading). 0.20 projected total, adopting A/v1 unchanged; v2 Option C 0.50 snapshots and Step 2 draft retained as superseded history. Same baseline/R1/P2/rater; no implementation or accepted outcome.

2026-10-27 UTC: Step 1 Option A re-approved. Step 2 rewritten for scope v3; 0.20 reaffirmed. Superseded v2 Step 2 draft (Option C dedicated Tools page, capability-filtered nav, 0.50) not retained as a file. Same baseline/R1/P2/rater; no implementation or accepted outcome.

2026-10-27 UTC: Step 2 approved. Step 3 handoff 0.20 reaffirmed, scope v3; stage-work originals S1 0.10, S2 0.07 (not summed). Same baseline/R1/P2/rater; no implementation or accepted outcome.

2026-10-27 UTC: Step 3 approved; Step 4 entry 0.20 reaffirmed. Closeout: two stages delivered on feat/high-traffic-toggle (planning 8742dc96, Stage 1 072ad8a2, Stage 2 closeout commit). Stage retrospectives S1 0.10, S2 0.06; cycle retrospective scope assessment 0.20, not measured effort. Two pre-existing LocalAppSmoke failures reproduced at baseline. Maintainer comfortable-fit judgment and acceptance pending; no accepted-count increment.

Cycle v3/site_operations_page

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/site_operations_pageLocally complete; maintainer acceptance pendingv1 / R1 / P20.40Intake and Step 2; Step 3; Step 4 and closeoutFollow-up to v3/high_traffic_toggle; acceptance pending

2026-10-27 UTC: standing P2 enrollment, start c462cc92 on feat/high-traffic-toggle. Intake and Step 2 handoff 0.40 for a Tools › Operations page holding high-traffic mode, nav icons and read-only view; Step 1 skipped. Prior exposure to predecessor's Option C (0.50) disclosed. Claude Code single exposed rater, R1 hashes verified earlier today. No implementation or accepted outcome; planning uncommitted.

2026-10-27 UTC: Step 2 approved. Step 3 handoff 0.40 reaffirmed; stage-work S1 0.18, S2 0.07, S3 0.05 (not summed). Same start/R1/P2/rater; no implementation.

2026-10-27 UTC: Step 3 approved; Step 4 entry 0.40 reaffirmed on new branch feat/operations-page. Closeout: three stages (planning aab96984, S1 d160c1ab, S2 b364f71f, S3 closeout commit). Stage retrospectives S1 0.16, S2 0.07, S3 0.03; cycle retrospective scope assessment 0.30, not measured effort. Maintainer judgment and acceptance pending; no accepted-count increment.

Cycle v3/ui_shell_navigation

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_shell_navigationStep 4 complete; maintainer judgment pendingv1 / R1 / P20.90 intake; 0.85 Step 1 (Option B); 0.85 Step 2; 0.90 Step 3Step 1 assessment · Step 2 · Step 3No parent; first cycle of the UI redesign checklist

2026-10-27T03:37:00Z intake, standing enrollment P2, scope v1/R1, baseline 83fba59802ce6f4ba022b1c429b534dda216edd2 (branch ui-redesign-mockups). Scope v1: cycle 1 of the UI redesign checklist, the app shell and navigation on every page (top bar with three destinations, New post and account menu; rare destinations and theme choice moved into the account menu; phone tab bar; theme hooks; icon-theme mapping; all registered themes checked). 0.90 intake projected total, recorded before implementation inspection. Exact R1 hashes verified. Claude single exposed rater: the rater authored the round 1 mockups, plan and checklist in earlier sessions (which named the affected templates) but had not inspected the shell implementation in this cycle. Extended estimates enabled (new-cycle default). No implementation, measured effort or accepted outcome; ledger update uncommitted under planning rules.

2026-10-27 Step 1 handoff: assessment and snapshots. Options A 1.20 (split discussion), B 0.85 recommended (new shell as a ZenMemes navigation presentation-slot choice), C 0.55. Scope v1/R1/P2/baseline unchanged; the drop from 0.90 is new understanding after inspecting the shell, nav items, presentation slots and theme selectors, not a scope change. Claude single exposed rater. No implementation, measured effort or accepted outcome; planning and ledger uncommitted.

2026-10-27T04:18:58Z Step 2 handoff: Step 1 Option B explicitly approved. Feature description/checkpoint defines the ZenMemes-only shell, unchanged reachability for every viewer state with and without JavaScript, unchanged headers on other sites, preserved navigation scripts, and the 13-theme-plus-Auto and icon-theme checks. Scope v1/R1/P2/baseline unchanged; 0.85 total reaffirmed, Claude single exposed rater. No implementation, measured effort or accepted outcome; awaiting Approved Step 2, records uncommitted.

2026-10-27T04:23:38Z Step 3 handoff: Step 2 explicitly approved. Development plan/checkpoint defines eight stages: slot and item placement, shell markup and account menu, desktop styles with early theme skeleton, phone tab bar, navigation scripts, permitted themes, icon themes, acceptance/closeout (including the baked-artifact rebuild). One nav element is placed by CSS for desktop and phone, so the traced single-nav.nav and unique unread-status assumptions hold. 0.90 projected total, up from 0.85 on new understanding (browser tests to update, baked-artifact rebuild), not scope change. Stage work estimates 0.15/0.12/0.10/0.20/0.15/0.15/0.08/0.10, not summed. Scope v1/R1/P2/baseline unchanged; Claude single exposed rater. No implementation, measured effort or accepted outcome; awaiting Approved Step 3, records uncommitted.

2026-10-27 Step 4 entry and closeout: Step 3 approved; Step 4 summary, branch feat/ui-shell-navigation, planning 062c19f4b. 0.90 reaffirmed at entry, no in-cycle revision; separate 0.95 retrospective scope assessment; Claude single exposed rater. Eight planned stages complete (stage work original/retrospective 0.15/0.12, 0.12/0.12, 0.10/0.10, 0.20/0.15, 0.15/0.20, 0.15/0.12, 0.08/0.06, 0.10/0.15; not summed). Scope v1/R1/P2/baseline unchanged. Other-site headers byte-identical, guest JS on/off phone/desktop matrix and 15 navigation browser tests pass; full suite partial (712 run, 711 passed, the 1 failure caused by a concurrent docs edit), not a full-suite claim. Pull-only deploy request recorded as separate follow-up work; merging current main pending. Zero dependency delta; no measured labor or accepted-count increment; maintainer fit pending.

Cycle v3/tui_operator_workspace

Status: Step 1 proposed; standing P2 enrollment; distinct follow-up to delivered terminal UI/private-config editor; deduplicate worktree copies by this ID. Scope: v1/A / R1 / P2; baseline 6e1b92798364dc84e30a411777d915b9d9d45f2a; existing-whiptail status/action navigation, current-value LLM editing and streaming read-only diagnostics, including recovery, verification and documentation. Canonical checkpoints: Intake and Step 1 handoff, 2026-10-27T04:57:58Z; exposed intake 0.75, handoff 0.75 reaffirmed. Extended estimates enabled; alternative whole-cycle A/B/C 0.75/1.30/1.10, not additive; B/C require split discussion. Rater: Codex single exposed rater after source and prior-plan inspection; all three frozen R1 source hashes verified. Pristine pre-inspection intake missing, not reconstructed; no measured labor or independent rating. Outcome: Await Approved Step 1; no implementation, dependency addition, commit, upload or accepted-count change. Maintainer acceptance pending; documentation uncommitted.

2026-10-27T05:10:33Z — v3/tui_operator_workspace Step 2 handoff: Step 1 Option A explicitly approved. Requirements/checkpoint define status-first navigation, searchable existing read-only diagnostics, streaming/interruption/return, current-value LLM editing, real redacted diffs and terminal/configuration recovery. Whole-cycle 0.75 reaffirmed; same v1/A/original baseline/R1/P2, extended mode and single exposed Codex rater; all three frozen reference hashes reverified. Prior scores preserved. Await Approved Step 2; documents uncommitted, no application work, dependency delta, measured labor, independent outcome or accepted-count increment.

2026-10-27T16:51:19Z — v3/tui_operator_workspace Step 3 handoff: Step 2 explicitly approved. Development plan/checkpoint defines six stages for streaming/recovery, bounded home status, searchable navigation, current-value editing, conflict-aware review/save and WSL terminal acceptance. Whole-cycle 0.75 reaffirmed; first S1–S6 stage-work 0.18/0.12/0.10/0.15/0.18/0.14, non-additive. Same v1/A clarified/original baseline/R1/P2, extended mode and single exposed Codex rater; all frozen hashes verified, prior checkpoints preserved. Six planned/zero implemented; zero dependency delta. Await Approved Step 3; documents uncommitted, no measured labor, independent outcome or accepted-count increment. Actual remote SSH evidence remains pending.

2026-10-27 UTC — v3/tui_operator_workspace Step 4 local closeout: entry, resize discovery, stages and limits. Same v1/A/original baseline/R1/P2, extended mode and single exposed Codex rater; frozen hashes verified. Original entry projection 0.75 retained; prospective resize-discovery revision 0.85; separate retrospective whole-cycle scope 0.85. S1–S6 originals 0.18/0.12/0.10/0.15/0.18/0.14; S6 prospective revision 0.20; retrospectives 0.18/0.12/0.10/0.15/0.18/0.22, non-additive. Six stages deliver shared health/search navigation, streaming diagnostics/recovery, current-value editing, conflict-aware atomic saves and actual WSL keyboard acceptance. Focused PHP 37/37 and five Python suites passed, including real whiptail live resize and long review; zero dependency/schema delta. Actual remote SSH, physical devices, full suite, deployment/merge and maintainer comfortable-fit/acceptance remain pending. No measured labor, independent outcome or accepted-count increment; deduplicate worktree copies. Plans and stage artifacts on feat/tui-operator-workspace; prior checkpoints retained.

Cycle v3/ui_tab_bar_scroll_away

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_tab_bar_scroll_awayStep 4 complete; iPhone check and merge pendingv1 / R1 / P20.45 intake; 0.45 Step 1 (Option A); 0.45 Step 2; 0.45 Step 3; 0.45 Step 4 entry; 0.40 retrospectiveStep 1 · Step 2 · Step 3 · Step 4Follow-up to v3/ui_shell_navigation (tab bar on main); related to v3/ui_thread_reply_dock

2026-10-27T23:06:56Z intake and Step 1 handoff, standing enrollment P2, baseline main 7ef735dd2. Scope v1: the ZenMemes phone tab bar hides on scroll down and returns on scroll up, at page ends or on focus; dependents follow its height. 0.45 intake, recorded before code inspection for this cycle; Claude single exposed rater (built the bar in cycle 1). Options A 0.45 (recommended), B 0.30, C 0.55; not summed. Extended estimates enabled. No implementation, measured effort or accepted outcome; records uncommitted.

2026-10-27 Step 2 handoff: Step 1 Option A explicitly approved. Feature description/checkpoint: hide on scroll down, return on scroll up/page ends/focus, stay while the account menu is open, dependents follow the visible height, reduced motion and no-JavaScript fallbacks, desktop and other sites unchanged. 0.45 reaffirmed; scope v1/R1/P2 unchanged; Claude single exposed rater. Approved Step 2 received 2026-10-28.

2026-10-28 Step 3 handoff: development plan/checkpoint in three stages (scroll script and hidden state 0.22; dependents follow the visible bar 0.10; themes, acceptance and closeout 0.13). 0.45 reaffirmed; scope v1/R1/P2 unchanged; Claude single exposed rater. No implementation; awaiting Approved Step 3, records uncommitted.

2026-10-28 Step 4 entry and closeout: Step 3 explicitly approved; Step 4 summary, branch feat/ui-tab-bar-scroll-away from 7ef735dd2, planning 5357102ec. 0.45 reaffirmed at entry, no in-cycle revision; separate 0.40 retrospective scope assessment; Claude single exposed rater. Three stages complete (stage work original/retrospective 0.22/0.20, 0.10/0.08, 0.13/0.12; not summed). Scope v1/R1/P2 unchanged; one deviation (dependents move instantly rather than sliding). Full suite once: 1595 run, 1589 passed; five failures also fail on main, the sixth (a gpg signing step) passed on rerun. 13 themes plus Auto checked shown and hidden at 390px. Real-iPhone check, deployment, merge and maintainer fit pending. Zero dependency delta; no measured labor or accepted-count increment.

Cycle v3/ui_account_states

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_account_statesStep 4 complete; review and merge pendingv1 / R1 / P20.70 intake; 0.95 Step 2; 0.95 Step 3; 0.95 Step 4 entry; 1.00 retrospectiveStep 2 · Step 3 · CloseoutNo parent; cycle 4 of the UI redesign checklist

2026-10-28T16:23:12Z intake, standing enrollment P2, baseline main cba7d54f9, Step 1 skipped. 0.70 intake from the checklist item before code inspection; Claude single exposed rater (authored the mockup and checklist). Extended estimates enabled.

2026-10-28 Step 2 handoff: user chose all sites, one cycle and name-first set-up. Feature description/checkpoint: three first-paint states, dated backup status, everyday rows with prompt-free rename, backup sheet with one Download, remove confirmation with Back up first, Advanced, inline errors; all four sites. 0.95 revised (all-site checks, prompt-free rename, sheet/dialog and first-paint work exceeded the checklist reading). Revised the same day before approval: the user pointed out that v3 keys are disposable and users are names aggregated across approved keys; the page is reframed around the name and this browser's key (save-a-copy prompt only for approved keys, Remove this key, /user/<name> link, join hint). 0.95 reaffirmed. No implementation; awaiting Approved Step 2, records uncommitted.

2026-10-28 Step 3 handoff: Step 2 explicitly approved. Development plan/checkpoint in five stages: three states on first paint 0.25; naming without prompts and /api/get_username 0.20; save a copy and use a key from another device 0.20; remove this key 0.08; sites, themes, copy and closeout 0.17 (not summed). 0.95 reaffirmed; scope v1/R1/P2 unchanged; Claude single exposed rater. No implementation; awaiting Approved Step 3, records uncommitted.

2026-10-28 Step 4 entry and closeout: Step 3 explicitly approved; Step 4 summary, branch feat/ui-account-states from cba7d54f9, planning f7ba168da. 0.95 reaffirmed at entry, no in-cycle revision; separate 1.00 retrospective scope assessment; Claude single exposed rater. Five stages complete (stage work original/retrospective 0.25/0.25, 0.20/0.22, 0.20/0.26, 0.08/0.08, 0.17/0.20; not summed). Scope v1/R1/P2 unchanged; corrective work inside scope: in-place sign-in on the account page (sign-in reload race), theme fixes. Full suite once: 1607 run, 1601 passed; three fail on main, two wording fixes rerun, one gpg flake passed on rerun. 59 site/theme combinations checked. User follow-ups recorded (sign-in reload elsewhere, Starfield robustness). Real-phone check, merge, deployment and maintainer fit pending. Zero dependency delta; no measured labor or accepted-count increment.

Cycle v3/ui_first_post_identity

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_first_post_identityStep 4 complete (technical); maintainer fit pendingv1.2 (G1) / R1 / P20.75 intake; 0.80 Step 1 (Option A); 0.85 Step 1 rev. 1 (Option D); 0.80 Step 1 rev. 2 (G1); 0.85 Step 2; 0.85 Step 3; 0.85 Step 4 entry (reaffirmed); 0.90 retrospective scope assessmentStep 1 · Step 2 · Step 3 · Step 4No parent; cycle 5 of the UI redesign checklist

2026-10-28T18:13:41Z intake, standing enrollment P2, baseline main 74d044c1f. Scope v1: checklist cycle 5, a first post with no browser dialogs and no long wait after Post (inline name, key prepared ahead, visible creation state with recovery). 0.75 intake before code inspection; Claude single exposed rater (authored the checklist and mockup, built cycle 4's naming). Exact R1 hashes verified. Extended estimates enabled.

2026-10-28 Step 1 handoff: options A 0.80 (recommended: unpublished key prepared on composer focus, published at Post), B 0.85 (publish on writing intent), C 1.20 (register with the first post; split discussion); not summed. 0.80 for A is new understanding (three composers and shared prompt callers), not a scope change. No implementation, measured effort or accepted outcome; records uncommitted.

2026-10-28 Step 1 revision 1: the user pointed out that votes use the same key, so it must be published right away. A and B superseded (C kept). New options D 0.85 (recommended: publish at once, keep unused keys, hide them from the pending list), E 1.10 (D plus timed cleanup; history purge not yet built), F 1.25 (key known to the server, committed on first use); not summed. 0.85: a user correction to the scope (v1.1), not an independent outcome. No implementation; records uncommitted.

2026-10-28 Step 1 revision 2: the user flagged the write lock, ruling out per-visitor publishing. D/E/F superseded. Option G (register the key with its first post, reply, Like or rename) 1.05, split into G1 0.80 (this cycle: local key, no background publishing of unused keys, no dialogs, first action registers then acts) and G2 0.55 (proposed follow-up: server accepts the key with the first action; would get its own cycle ID). 0.80 for G1 is a scope change (v1.2), not new understanding. Not summed; no implementation; records uncommitted.

2026-10-28 G2 note: the user chose one request for a first vote (browser builds and signs the bootstrap record; server checks it). G1 0.80 reaffirmed; proposed follow-up G2 0.60 (from 0.55). No implementation; records uncommitted.

2026-10-28 Step 2 handoff: Step 1 explicitly approved (G1; G2 a follow-up). Feature description/checkpoint: no dialogs on any site, local key until the first post, reply, Like or rename, no background publishing, composer name row, first action registers then acts, inline recovery. 0.85 (from 0.80) is new understanding (account page handling of unregistered keys, publish setting removal, Outbox, members-only sign-in). No implementation; awaiting Approved Step 2, records uncommitted.

2026-10-28 Step 3 handoff: Step 2 explicitly approved with both defaults (name row on every site; publish setting removed). Development plan/checkpoint in eight stages: local keys and no dialogs 0.15; one registered check 0.15; composer name row 0.15; change name from composer 0.12; creation state and recovery 0.12; other signed paths and members-only 0.10; sites, themes, docs 0.10; acceptance 0.06 (not summed). 0.85 reaffirmed; Claude single exposed rater. No implementation; awaiting Approved Step 3, records uncommitted.

2026-10-28 Step 4 entry and closeout: Step 3 explicitly approved; Step 4 summary, branch feat/ui-first-post-identity from 74d044c1f, planning 33a76fb31. 0.85 reaffirmed at entry, with no in-cycle revision. A separate 0.90 retrospective scope assessment reflects work found in-scope during implementation: the public-site sign-in path that also registered readers, Outbox signed reactions, and the Forte toolbar's first paint. Claude single exposed rater. All eight stages are complete. Stage work original/retrospective: 0.15/0.17, 0.15/0.14, 0.15/0.15, 0.12/0.14, 0.12/0.12, 0.10/0.08, 0.10/0.11, 0.06/0.06 (not summed). Scope v1.2 (G1) / R1 / P2 unchanged; there were no new requests, and corrective work stayed in scope. Full suite run once: 1616 run, 1613 passed; the three failures predate the branch. 59 site/theme combinations were checked. The phone-sized replay on a ZenMemes-sized copy passed: no requests while reading, one registration, and post to thread page in 0.1–0.8 s locally. Still pending: the real-iPhone check, merge, deployment and maintainer fit. G2 remains a proposed follow-up with its own cycle ID. Zero dependency delta; no measured labor; no increment to the accepted count.

2026-10-28 after closeout: three user-reported corrective fixes inside scope (a332f69f5, bef7f07da, e08e5c737); the user then closed the cycle. Handoffs recorded in the backlog (unexpected page reload; Outbox and identity). No new projection; the 0.90 retrospective assessment is unchanged. The real-iPhone check and maintainer fit are pending.

Cycle v3/unified_removal_format

2026-10-29T00:03:48Z — standing P2 enrollment; canonical intake and Step 1 handoff. Scope v1/A, baseline b8afb7711cdf6816da943755268de848b6f33781, R1 exact three hashes verified. Codex single exposed rater after checklist and receipt/consumer inspection; intake 0.75, handoff 0.75 reaffirmed. Extended estimates enabled; complete-cycle alternatives A 0.75 / B 0.45, not additive. Prior conversational F02 0.45 screening remains conversion-only; A adds shared retraction acceptance format/consumers while retaining existing text receipts and exact signatures. F02 JSON compatibility excluded by maintainer decision. Related completed v3/retraction_text_format remains separate. No implementation, measured effort, acceptance or accepted-count increment. Await Approved Step 1; planning/debug/ledger changes uncommitted.

2026-10-29T00:13:16Z — v3/unified_removal_format Step 2 handoff: Step 1 Option A explicitly approved. Requirements and checkpoint define one future receipt contract with distinct signed/local authority and delete/resolve effects, existing-text compatibility, no F02 JSON migration, same-post evidence preservation and normal source/rebuild/import/recovery acceptance. Scope v1/A clarified, original baseline/R1/P2 and exposed single Codex rater retained; all three frozen hashes reverified. Whole-cycle 0.75 reaffirmed. No implementation, measurement, accepted outcome or dependency delta; await Approved Step 2.

2026-10-29 UTC — v3/unified_removal_format Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines seven stages for shared receipt validation/interpretation, CLI and signed transactions, source/import/export, maintenance and normal-flow acceptance. Total 0.85 revises preserved 0.75 on newly inspected same-ID array precedence and pending-journal recovery, not new scope. S1–S7/v1 stage-work estimates 0.15/0.20/0.20/0.15/0.15/0.10/0.20, non-additive; S7 owns shared acceptance/closeout. Same v1/A/original baseline/R1/P2; exact hashes reverified; single exposed Codex rater. Existing readable retractions preserved, F02 JSON unsupported. No implementation, measured labor, dependency delta or accepted outcome; await Approved Step 3, documents uncommitted.

2026-10-29 UTC — v3/unified_removal_format scope v2/A revision: maintainer explicitly abandons previous F01 text receipts as well as F02 JSON because no existing data needs saving. Canonical revised Step 3 checkpoint: whole-cycle 0.70 supersedes preserved v1 0.75 intake/Steps 1–2 and 0.85 Step 3. Remove old-reader/migration/coexistence/replay and old-state recovery work; retain all new-format authority, evidence, transitions and recovery. S1–S7/v2 stage-work 0.10/0.15/0.15/0.10/0.15/0.10/0.15, originals retained in plan; non-additive. Same original baseline/R1/P2, exact hashes reverified, single exposed Codex rater. Explicit instruction authorizes narrowing previously approved requirements, not implementation. Await Approved Step 3; no runtime changes, data deletion, measurements or accepted-count increment.

2026-10-29 UTC — v3/unified_removal_format Step 4 local closeout: entry, stages and evidence. Step 3 explicitly approved; scope v2/A/original baseline/R1/P2, single exposed Codex rater retained. Entry whole-cycle 0.70 reaffirmed; separate retrospective scope assessment 0.75. Original S1–S7/v2 0.10/0.15/0.15/0.10/0.15/0.10/0.15 retained; retrospectives 0.10/0.15/0.15/0.10/0.15/0.10/0.20, non-additive. Seven stages deliver one future receipt codec/interpretation, distinct local/signed authority, preserved new signed bytes and label bindings, text operator receipts, source/import/export and operation-aware cleanup. No previous-format migration/readers. Focused regressions 122/122; final API/CLI flows 21/21 after operator rejected-commit retry correction; actual browser four scenarios/13 themes at phone/desktop, menu keyboard/Escape/touch and raw receipt inspection pass. Zero dependency/schema delta. Full suite, deployment, physical devices, merge/push and maintainer comfortable-fit/acceptance pending; no measured labor or accepted-count increment. Planning and stage commits recorded in summary; F02 closed locally.

Cycle v3/background_sign_in

Status: Step 1 proposed; standing enrollment P2 Canonical checkpoint: Step 1 handoff, 2026-10-28T23:39:23Z Scope: v1 / Option A; baseline 49a9024412c7e7f6d9230fb7ed1e7b72acf4627e; R1 / P2 Projected total: 0.35; alternative B 0.55, not additive Exposure: Codex single exposed rater; source inspection preceded rating; pristine intake missing, not reconstructed. All three frozen R1 hashes verified. Extended estimates enabled. Relationship: Distinct follow-up to v3/ui_first_post_identity and Account's in-place sign-in; same stable ID across worktrees. Authorization: Background direction selected; Step 1 requested, awaiting Approved Step 1. No implementation, measured labor, acceptance or accepted-count increment. Planning records uncommitted.

2026-10-28T23:41:05Z Step 2 handoff: Approved Step 1 received; canonical feature description/checkpoint. Whole-cycle 0.35 reaffirmed, scope v1/Option A/original baseline/R1/P2 unchanged; Codex single exposed rater, inherited frozen-reference verification and additional shared-caller inventory. Public background restoration preserves document/interaction, usable sessions and explicit recovery; protected navigation retains its intent. Pristine intake remains missing. Await Approved Step 2; no implementation, commits, measured effort or accepted-count increment.

2026-10-28T23:52:47Z Step 3 handoff: Approved Step 2 received; canonical development plan/checkpoint. Whole-cycle 0.35 reaffirmed; four stage-work originals 0.12/0.10/0.10/0.08, not summed. Scope v1/Option A/original baseline/R1/P2 unchanged; Codex single exposed rater, inherited frozen-reference verification, shared-caller and test inspection. Pristine intake remains missing. Stage 4 owns shared acceptance; protected navigation and concurrent-call semantics precede browser acceptance. Await Approved Step 3; no implementation, commits, measured effort or accepted-count increment.

2026-10-29 Step 4 local closeout: Approved Step 3 received; canonical implementation/closeout. Entry projection 0.35 reaffirmed, no prospective revision; separate retrospective scope 0.45. Same v3/background_sign_in, scope v1/Option A/original baseline/R1/P2/single exposed Codex rater. Planning a9372972, S1 bb4355e2, S2 121796eb, S3 71df7611; final stage contains closeout. Four/four stages complete; stage original/retrospective 0.12/0.12, 0.10/0.12, 0.10/0.12, 0.08/0.15, non-additive. Public sign-in preserves document/interaction/session; Account testing-only reload and queued-key drift corrected in scope. Focused PHP 21/21; combined smoke 174/175 with one archive test failure reproduced on baseline. Browser flows and Chromium 13 explicit ZenMemes themes plus Firefox/WebKit passed, with documented fixture corrections and limits. Zero dependencies; no measured labor, independent rating, merge/push/deployment or accepted-count increment. Physical devices, branded site-specific themes, full suite and maintainer fit remain unchecked/pending; pristine intake remains missing.

v3/fastmod_virtual_tags — Step 1 estimate

Status: Locally complete; maintainer acceptance pending; distinct simplification follow-up to E07/root meta tagging and its shared flag. Scope: v1/A / R1 / P2; baseline 60518d9e7ce80b34c93587d73a04d999b3b462b8. Projected total: 0.70 at Step 3/4; original Step 1/2 0.60 and alternative B 0.90 preserved, non-additive complete-cycle estimates. Canonical checkpoint: Step 1 assessment, 2026-10-29T02:16:33Z. Rater: Codex single exposed rater; all three frozen R1 hashes verified; pristine intake missing after source inspection, not reconstructed. Extended estimates/debug enabled. Acceptance: No implementation, measurement, approval or accepted outcome; same stable ID across worktrees. Planning and ledger updates uncommitted.

2026-10-29T18:35:07Z — v3/fastmod_virtual_tags Step 2 handoff: Step 1 Option A approved; feature description/checkpoint reaffirms whole-cycle 0.60, v1/A/original baseline/R1/P2. Shared mapping layer, dynamic root labels, ordinary refresh and read-only legacy exclusions define the proposed outcome. Future mappings/editor remain out of scope. Three frozen hashes reverified; single exposed Codex rater, extended/debug modes retained, missing pristine intake preserved. Await Approved Step 2; no implementation, measurement or accepted outcome.

2026-10-29T18:44:39Z — v3/fastmod_virtual_tags Step 3 handoff: Step 2 approved. Plan/checkpoint revises whole-cycle 0.60 to 0.70 for newly traced static-release, high-traffic and docs integration, unchanged v1/A/original baseline/R1/P2. Original S1–S8 stage work 0.12/0.15/0.08/0.12/0.08/0.08/0.08/0.12, non-additive; eight planned, zero completed. Frozen hashes verified, single exposed Codex rater, missing pristine intake and earlier projections preserved. Await Approved Step 3; no implementation, tests, measured labor or accepted outcome.

2026-10-29 UTC — v3/fastmod_virtual_tags Step 4 entry and local closeout: canonical implementation checkpoints. Approved Step 3; entry projection 0.70 reaffirmed after planning commit 3300df0a; eight stages completed. Separate retrospective cycle scope 0.70, original stage estimates preserved; S8 retrospective 0.15 for fixture corrections/acceptance, other stage retrospectives unchanged. Same v1/A/original baseline/R1/P2 and single exposed Codex rater; no reconstructed intake or measured labor. Dynamic score-derived mapping, read-only legacy exclusions, ordinary snapshot refresh and retired CLI guidance verified locally. Focused PHP 54/54, subsequent derived/flag additions and real browser passed; 29/29 cache/docs and 8/8 offline stage checks passed. Broader smoke 156/157 with sole failure reproduced on c5783108; full suite/deployment/live-model validation not claimed. Maintainer judgment/acceptance pending, no accepted-count increment; same ID across worktrees.

Cycle v3/approval_acceptance_text

2026-10-29 UTC — standing P2 enrollment; canonical Step 1 checkpoint. Scope v1/A; baseline d26a90f9b9bfa8eb67e72804a7c24707947ab7c0; R1 exact three hashes verified; extended estimates enabled. Codex single exposed rater after audit, source and test inspection. Pristine intake missing, not reconstructed. Whole-cycle projection 0.65, alternative B 0.45, not additive. F03 is distinct from completed F01/F02 cycles; no parent split or replacement. Preserve existing approval evidence by default; fresh-only alternative requires its own disposability decision. Await Approved Step 1; no implementation, measured effort, accepted outcome or accepted-count increment. Planning/debug/ledger remain uncommitted.

2026-10-29 UTC — v3/approval_acceptance_text Step 1 revision 1: removable legacy support, scope v2/A. User requested an easy later removal path: isolate decoding, add a readable readiness check and removal procedure, verify current text behavior without the reader, preserve historical digest validation separately. Whole-cycle 0.70 revises preserved v1 0.65 for added scope; B remains 0.45, not additive. Same baseline/R1/P2 and exposed single Codex rater; hashes reverified; pristine intake still missing. Actual retirement and old-backup policy remain later decisions. Await Approved Step 1; no implementation, measured effort or accepted-count increment.

2026-10-29 UTC — v3/approval_acceptance_text Step 2 handoff: revised Option A explicitly approved. Requirements/checkpoint cover readable new receipts, validated conversion/retry, legacy restore, independent signed-digest verification and a bounded reader-retirement path with archive uncertainty. Scope v2/A/original baseline/R1/P2 unchanged; whole-cycle 0.70 reaffirmed, earlier 0.65 retained. Codex single exposed rater; hashes reverified; source-link/API/shared-template inspection added. Pristine intake missing; no implementation, measurement or accepted-count increment. Await Approved Step 2; planning uncommitted.

2026-10-29 UTC — v3/approval_acceptance_text Step 3 handoff: Step 2 explicitly approved. Development plan/checkpoint defines six stages covering readable/digest contract, new writes/resolution, archive/replay, operator conversion/recovery, removable legacy support and acceptance. Whole-cycle 0.75 revises preserved 0.70 for new understanding of path-based retry and archive identity handling; scope v2/A/original baseline/R1/P2 unchanged. S1–S6/v1 stage-work originals 0.15/0.15/0.10/0.20/0.10/0.15, non-additive; S6 owns shared acceptance. Exact R1 hashes reverified; single exposed Codex rater, pristine intake missing. No implementation, measurement, dependency delta or accepted outcome; await Approved Step 3, planning uncommitted.

2026-10-29 UTC — v3/approval_acceptance_text Step 4 local closeout: canonical summary. Approved Step 3; planning aa9a7f7b and six stage commits. Scope v2/A/original baseline/R1/P2/single exposed Codex rater retained. Entry 0.75 reaffirmed, separate retrospective scope 0.80. Stage original/retrospective 0.15/0.15, 0.15/0.15, 0.10/0.10, 0.20/0.20, 0.10/0.10, 0.15/0.20, non-additive. New text receipts, preserved signed evidence, legacy conversion/retry/restore and bounded reader removal readiness complete locally. Focused PHP 59/59 plus edge regression 1/1; actual signed browser flow across 13 supported themes/two widths, standalone Forte histories and public/private invitation browser flows pass. Earlier stale browser cancellation expectation and fixture corrections disclosed in summary. Zero dependency/schema delta. No full suite, physical devices, deployment, production conversion, reader removal, merge/push or measured labor. Pristine intake missing; maintainer fit/acceptance pending; no accepted-count increment.

Cycle v3/railspike_feature_gating

Status: Step 1 proposed; standing P2 enrollment; deduplicate worktrees by this stable ID. Scope: v1/A / R1 / P2; baseline cdb7a4e75a8b0e9065140656ec79dba5cf12e229; feature flag and active-work polling for browser Railspike development, including disabled execution, retained records, recovery and rendered verification. Related Activity workflow cleanup remains a separate outcome; private-message synchronization excluded. Canonical checkpoints: Intake and Step 1, 2026-10-29 UTC; exposed intake 0.60 and handoff 0.60 reaffirmed; extended alternatives A 0.60 / B 0.45, complete cycles, not additive. Rater: Codex single exposed rater after source inspection in the preceding conversation; all three frozen host-local R1 hashes verified. Pristine pre-inspection intake unavailable, not reconstructed; no measured labor or independent rating. Outcome: Await Approved Step 1; proposed default-disabled rollout not yet approved. No implementation, commit, deployment, dependency change or accepted-count increment; maintainer acceptance pending. Planning and ledger remain uncommitted.

2026-10-29T18:14:46Z — v3/railspike_feature_gating Step 1 revision: user accepts polling only with a Railspike thread open. Revised assessment scopes v2/A to visible eligible thread context, independent of queued/running state, with the same flag and recovery contract. Revised projected total 0.50; v1 intake/handoff 0.60 preserved; B 0.45 unchanged. Same baseline/R1/P2, extended mode and single exposed Codex rater; prior hash verification carried forward. Direction refinement is not Approved Step 1; no implementation, measurement or accepted-count change.

2026-10-29T18:36:23Z — v3/railspike_feature_gating Step 2 handoff: Step 1 v2/A explicitly approved, including default-off flag. Feature description/checkpoint defines visible eligible-thread polling independent of workflow state, disabled API/worker behavior, finish-existing/pause-new execution, retained records/drafts, stale-page stop and reload recovery. Whole-cycle 0.50 reaffirmed; same v2/A/original baseline/R1/P2 and single exposed Codex rater; verified reference state carried forward. Production acceptance requires authorized deployment and actual production evidence; local checks cannot substitute. Await Approved Step 2; no implementation, measured labor or accepted-count change; documents uncommitted.

2026-10-29T18:59:40Z — v3/railspike_feature_gating Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines five stages: flag/API, worker suspension, eligible-page/first-paint gating, polling/drafts, acceptance. Cycle projection 0.60 revises 0.50 for newly examined reconciliation/static/draft obligations, not changed scope; preserve all earlier scores. Original stage work S1–S5 0.12/0.14/0.15/0.14/0.12, non-additive. Same v2/A/baseline/R1/P2 and single exposed Codex rater; prior reference verification carried forward. Production replay remains separately authorized and pending. Await Approved Step 3; five planned, none implemented; no measured labor or accepted-count increment; records uncommitted.

2026-10-29 UTC — v3/railspike_feature_gating Step 4 local closeout: entry, stages and limits. Step 3 explicitly approved; entry 0.60 reaffirmed, separate retrospective cycle scope 0.65. Same v2/A/original baseline/R1/P2 and single exposed Codex rater. Original S1–S5 0.12/0.14/0.15/0.14/0.12 preserved; retrospective work 0.12/0.14/0.15/0.18/0.18, non-additive. Planning ef47c56ae, four staged commits then acceptance/closeout on feat/railspike-feature-gating. Five stages deliver default-off flag, disabled API/worker suspension, visible eligible-thread polling and retained drafts. Focused PHP batches 77/77, 6/6, final flag/cache 4/4 and API 3/3 (overlapping); signed browser/recovery/network checks and 13-theme phone/desktop matrix pass; shared backup toggle regression covers 240 states. Normal-toggle readiness and storage-failure draft corrections remain within approved scope. Zero dependency/schema delta, no measured labor or accepted-count increment. Full suite, physical devices, deployment, production replay and maintainer comfortable-fit/acceptance unverified or pending. Deduplicate worktree copies; original checkpoints retained.

Cycle v3/viewer_nav_prepaint

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/viewer_nav_prepaintLocally complete; maintainer acceptance pendingv3 / R1 / P20.50Intake and Step 2Related to high_traffic_mode and nav_links_load_stability; acceptance pending

2026-10-27 UTC: standing P2 enrollment, start 2bfab452. Intake and Step 2 handoff 0.45 for pre-paint Messages/Invite menu consistency across shared and live pages; Step 1 skipped (user chose the approach). Prior inspection disclosed. Claude Code single exposed rater. No implementation or accepted outcome; planning uncommitted.

2026-10-27 UTC: Step 2 revised to scope v2 (client-only decision, uniform server HTML, in-place updates on real status change; CONTRIBUTING/AGENTS guidance then done directly outside the cycle). 0.40 projected total, revised from 0.45 for scope change. Same start/R1/P2/rater; no implementation.

2026-10-27 UTC: viewer_nav_prepaint Step 2 v2 approved. Step 3 checkpoint reaffirms 0.40 whole-cycle projection; four stage-work originals S1–S4/v1 0.10 / 0.12 / 0.08 / 0.10, not additive. Same baseline 2bfab452/R1/P2; Codex single exposed rater after inherited Claude estimates and source inspection, exact frozen hashes verified. Four planned/zero completed stages; prior scores retained, no implementation, measured labor or accepted-count increment. Await Approved Step 3; planning and ledger uncommitted.

2026-10-29T18:37:06Z: plans rebased on main c5783108 after the app shell, background sign-in and Users redesign merged. Step 2 v3 revision and Step 3 revision checkpoint: scope v3, start c5783108, 0.50 projected total (0.45 without the optional Waiting-tab stage), revised from 0.40 mostly for new understanding (two shell render sites, conditional messaging scripts, tab-bar hiding). Stage-work S1–S5/v2 0.08 / 0.15 / 0.12 / 0.05 / 0.10, not additive; v1 originals retained. R1 hashes verified; Claude Code single exposed rater. No implementation or accepted outcome; await Approved Step 2 (v3) and Step 3; planning uncommitted.

2026-10-29 UTC: user chose Waiting-tab option A (count in shared HTML; exposure/staleness follow-ups in todo.txt). 0.50 reaffirmed; same v3/start/R1/P2/rater. Scope choice only; Step 2 v3 approval still pending.

2026-10-29 UTC: Step 2 v3 and Step 3 approved; Step 4 entry 0.50 reaffirmed on feat/viewer-nav-prepaint (planning c8beee50). Same v3/start c5783108/R1/P2/rater. Stage 1 complete; retrospective stage work 0.08 (original 0.10 v1, 0.08 v2). No accepted-count increment.

2026-10-29 UTC: Stage 2 complete; retrospective stage work 0.15 (original 0.12 v1, 0.15 v2). Cycle 0.50 unchanged; no accepted-count increment.

2026-10-29 UTC: Stage 3 complete; retrospective stage work 0.14 (original 0.08 v1, 0.12 v2; history-sync viewer binding was extra discovery). Cycle 0.50 unchanged; no accepted-count increment.

2026-10-29 UTC: Stage 4 complete; retrospective stage work 0.05 (original 0.05 v2). Cycle 0.50 unchanged; no accepted-count increment.

2026-10-29 UTC: Stage 5 and closeout: five of five stages on feat/viewer-nav-prepaint (planning c8beee50, S1 d50d10ac, S2 32fce977, S3 d9a0b0a1, S4 e6185887, S5 closeout commit). Stage retrospectives S1–S5 0.08 / 0.15 / 0.14 / 0.05 / 0.13, not summed. Entry projection 0.50 retained; cycle retrospective scope assessment 0.55, not measured effort. Same v3/start c5783108/R1/P2; Claude Code single exposed rater. Full PHP suite 1626/1630 (three long-standing, one fixed after the user narrowed the static-release guard); browser matrices pass. Maintainer judgment and acceptance pending; no accepted-count increment.

v3/fastmod_score_transfer — Step 1 estimate

Status: Proposed, estimate only; separate follow-up to v3/fastmod_virtual_tags, not an accepted outcome. Scope: v1/A / R1 / P2; baseline 53f0c89260c08e3fdf1d5535380d84d7cec92768. Projected total: 0.70 integrated score supplement; alternative manual transfer B 0.40, non-additive complete-cycle estimates. Canonical checkpoint: Step 1, 2026-10-29T19:42:20Z. Rater: Codex single exposed rater; all frozen R1 hashes verified, extended/debug enabled, pristine intake missing after source inspection. No earlier score reconstructed, implementation, measured labor or accepted outcome. Same ID across worktrees; records uncommitted.

2026-10-29 UTC — v3/fastmod_score_transfer Step 2 handoff: Step 1 Option A approved. Requirements/checkpoint reaffirms 0.70, same v1/A/original baseline/R1/P2, source export and destination import opt-ins, score-only allowlist and destination-wins recovery. Authorized main merge f6f295f9 incorporates origin/main 9005e876 and Railspike v0.5.0-beta.1; concepts touched documented prospectively, missing inventory entries proposed only. Exact R1 hashes verified, single exposed Codex rater, pristine intake still missing. Await Approved Step 2; no implementation, measured labor or accepted outcome.

2026-10-29 UTC — v3/fastmod_score_transfer scope v2/A: user requests automatic score inclusion without parameters. Revised Step 3 reaffirms 0.75; earlier 0.70 and original stage estimates retained, non-additive. Same baseline/R1/P2 and single exposed rater; inherited reference verification. No implementation, measured labor, dependencies or acceptance; await Approved Step 3.

2026-10-29 UTC — v3/fastmod_score_transfer Step 4 local closeout: implementation/checkpoints. User approved Step 3 after requesting automatic inclusion without controls. Entry projection 0.75 reaffirmed; separate retrospective cycle scope 0.75. Same v2/A/original baseline/R1/P2 and single exposed Codex rater; no reconstructed intake or measured labor. Eight stages complete, original stage estimates retained; S7 retrospective 0.15, others unchanged, non-additive. Combined regressions 77/77; real HTTP export → CLI preview/import/repeat → live/Forte/text/offline/static tags passes, Chromium 390/1280 widths and JS on/off, zero provider calls. Recovery before/after score merge and during offline publication passes without original source; local conflicts/suppressions, timestamps and malformed input handling verified. Zero dependency/schema delta. Full suite, production migration/deployment, exhaustive themes/browsers, physical devices and maintainer acceptance pending; no accepted-count increment. Planning/stage commits retained; no merge/push.

Cycle v3/ui_messages

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_messagesStep 4 complete (technical); maintainer fit pendingv1.1 (split) / R1 / P21.10 intake; 0.85 Step 2; 0.85 Step 3; 0.85 Step 4 entry (reaffirmed); 0.95 retrospective scope assessmentStep 2 · Step 3 · Step 4No parent; cycle 8 of the UI redesign checklist

2026-10-29T18:46Z intake, standing enrollment P2, baseline main b3a5b1621, Step 1 skipped. Scope v1: the whole checklist item (list, conversation, two panes, member picker, send states, not-a-member page, hooks). 1.10 intake before code inspection; Claude single exposed rater (authored the mockups and checklist). Over 1.0, so a split discussion. Exact R1 hashes verified. Extended estimates enabled.

2026-10-29 Step 2 handoff: feature description/checkpoint proposes scope v1.1: this cycle keeps the list, conversation, per-item failure recovery, send states on the bubble and the not-a-member page, single-pane; proposed follow-up v3/ui_messages_panes (about 0.55; own ID) takes two panes, the member picker and scroll loading. Excluded: avatars, read receipts ("Seen" for the sender), Outbox queueing, legacy mailbox page. 0.85 is a scope change (split) plus new understanding (bubbles, day separators, grouped failures and send-attempt recovery already exist). Not summed. No implementation; awaiting Approved Step 2, records uncommitted.

2026-10-29 Step 3 handoff: Step 2 approved ("Approvee Step 2", read as Approved Step 2) with the split. Development plan/checkpoint in six stages: send states on the bubble 0.18; conversation reads like a chat 0.15; unreadable messages and recovery 0.12; list rows 0.15; not-an-approved-member page 0.15; sites, themes and closeout 0.12 (not summed). 0.85 reaffirmed; scope v1.1/R1/P2 unchanged; Claude single exposed rater. No implementation; awaiting Approved Step 3, records uncommitted.

2026-10-29 Step 4 entry and closeout: Step 3 explicitly approved; Step 4 summary, branch feat/ui-messages from b3a5b1621, planning b129c36fa. 0.85 reaffirmed at entry, no in-cycle revision; separate 0.95 retrospective scope assessment (test-harness repairs needed to verify, sign-in result mapping, three theme-matrix fixes; new understanding, no scope change). Claude single exposed rater. Six of six stages; stage work original/retrospective 0.18/0.22, 0.15/0.15, 0.12/0.12, 0.15/0.13, 0.15/0.17, 0.12/0.15 (not summed). Full suite once: 1627 run, 1623 passed; three failures predate the cycle, one Git acceptance test failed during a concurrent scratch-worktree removal and passed alone. Four sites in every permitted theme at two widths checked. Real phones, members-only beyond the guest redirect, merge, deployment and maintainer fit pending. Proposed follow-up v3/ui_messages_panes keeps its own ID. Zero dependency delta; no measured labour or accepted-count increment.

Cycle v3/agent_response_text

2026-10-29 UTC — standing P2 enrollment, intake before this cycle's detailed source inspection. Baseline 9005e87611b82e2304c0be52505d994674dc4efa; scope v1: F05 named agent-response headers for future posts, preserved historical signed replies and response/version relationships, ordinary generation/expansion/rebuild/offline verification. R1 exact three hashes reverified; Codex single exposed rater (audit and prior F03 cycle/reference scores visible). Whole-cycle intake 0.65; extended estimates enabled. Distinct audit follow-up, not a split or replacement of F03. Step 1 assessment and checklist update authorized; implementation unapproved. No measurement or accepted outcome; canonical intake and handoff.

2026-10-29 UTC — v3/agent_response_text Step 1 handoff: assessment/checkpoint. Scope v1/A/original baseline/R1/P2; whole-cycle 0.65 reaffirmed after source inspection. Alternative B 0.45, not additive. New headers with isolated legacy decoding preserve old signed posts, source/version relationships, mixed-format expansions and machine read-model/offline JSON. Removal of legacy reading requires a later retained-record/archive decision, not an F03-style in-place conversion. Intake remains prospective to this cycle's detailed inspection with prior audit/F03 exposure disclosed; single Codex rater. Checklist reviewed at 4 complete/12 open and F03 merged/pushed. Await Approved Step 1; no implementation, measured labor or accepted-count increment; planning uncommitted.

2026-10-29 UTC — v3/agent_response_text Step 1 revision 1: legacy retirement design, scope v2/A. User requested eventual removal be designed in; compatibility remains supported now. Add explicit read-only readiness/dependency inspection, bounded adapter-removal guidance and new-format acceptance with adapter unavailable. Whole-cycle 0.70 revises preserved intake/v1 handoff 0.65 for added scope; B remains 0.45, non-additive. Same baseline/R1/P2 and single exposed Codex rater; frozen hashes reverified. No historical signed-post rewrite or actual retirement authorized. Await Approved Step 1; no implementation, measurement or accepted-count increment.

2026-10-29 UTC — v3/agent_response_text Step 2 handoff: revised Option A explicitly approved. Requirements/checkpoint cover named headers, preserved old signed records, mixed-generation expansions, isolated legacy decoding, read-only operator readiness and new-format acceptance without the adapter. Whole-cycle 0.70 reaffirmed; scope v2/A/original baseline/R1/P2, single exposed Codex rater retained. R1 hashes reverified; command/shared UI/API inspection added. Original 0.65 intake/v1 handoff preserved. Await Approved Step 2; no implementation, measurement, dependency delta or accepted-count increment; planning uncommitted.

2026-10-29 UTC — v3/agent_response_text Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint defines five stages: compatible metadata, signed publication, transfer/offline integration, retirement inspection/proof and acceptance. Whole-cycle 0.70 reaffirmed; S1–S5/v1 original stage work 0.15/0.15/0.12/0.15/0.15, non-additive; S5 owns shared acceptance. Scope v2/A/original baseline/R1/P2 and single exposed Codex rater retained; hashes reverified, prior 0.65 intake/v1 preserved. Added parser/test inspection confirms duplicate handling and the need for actual publication acceptance beyond intercepted browser fixtures. Await Approved Step 3; no implementation, measurement, dependency delta or accepted-count increment; planning uncommitted.

2026-10-29 UTC — v3/agent_response_text Step 4 local closeout: canonical summary. Approved Step 3; planning 36abf44c, five implementation stages. Scope v2/A/original baseline/R1/P2/single exposed Codex rater retained. Entry 0.70 reaffirmed, no in-cycle revision; separate retrospective whole-cycle scope 0.75 reflects transfer-matrix/removal-proof verification. S1–S5 original/retrospective 0.15/0.15, 0.15/0.15, 0.12/0.15, 0.15/0.15, 0.15/0.15, non-additive. Original 0.65 intake/v1 preserved; frozen hashes reverified. Focused PHP 90/90 and final scanner 4/4 (overlap), browser thread/post/source/offline at phone/desktop widths pass. New named signed headers, unchanged historical signed bytes, mixed-format transfer and isolated decoder/readiness complete locally. Zero dependency/schema delta; no full suite, live provider, physical device, deployment, production conversion, reader removal or merge/push. Measured labor unknown; maintainer fit/acceptance pending; no accepted-count increment.

Cycle v3/unified_reaction_records

Status: Step 4 locally complete; maintainer acceptance pending; separate follow-up to v3/signed_thread_label_records. Scope: v1 / Option A; baseline 60d17174ceef711479a0cd3b20ad56d885a0f012; R1 / P2. Canonical checkpoint: Step 1 assessment, 2026-10-30T01:32:39Z. Intake 0.90 (before source inspection); Step 1 projection 0.75; alternatives B 1.10 / C 0.40, complete-cycle, not additive. Rater: Claude (claude-opus-5-5), single exposed rater; all three frozen R1 hashes verified. Extended estimates and debug enabled. No implementation, measured labor or accepted outcome. Records uncommitted.

2026-10-30T01:58:00Z Step 2 handoff: Approved Step 1 (Option A) received; feature description/checkpoint. Whole-cycle 0.75 reaffirmed; same v1/A/baseline/R1/P2, single exposed rater. All producers (including hashtag and offline replay) write one scoped format; legacy forms read as stored; no migration. Await Approved Step 2.

2026-10-30 UTC Step 3 handoff: Approved Step 2 received; plan/checkpoint. Whole-cycle 0.75 reaffirmed; five stage-work originals S1–S5/v1 0.15/0.15/0.15/0.20/0.10, not additive. Same v1/A/baseline/R1/P2, single exposed rater. Legacy signed client layout stays accepted. Await Approved Step 3.

2026-10-30 UTC Step 4 entry and local closeout: Approved Step 3 received; implementation/closeout. Entry 0.75 reaffirmed; separate retrospective cycle scope 0.75. Planning 59c663e4, S1 f50534bb, S2 0012ca21, S3 1c67b412, S4 2eed99b8, S5 closeout commit; 5/5 stages. Stage original/retrospective 0.15/0.12, 0.15/0.15, 0.15/0.15, 0.20/0.15, 0.10/0.12, non-additive. ER1 (isolate legacy support for later removal) handled in scope after the user chose "isolate only for now". Full suite 1657/1661 (3 baseline + 1 intermittent). Maintainer judgment pending; no accepted-count increment.

Cycle v3/private_message_sync_idle

Status: Step 1 proposed; standing P2 enrollment; same stable ID across worktrees. Scope: v1/A / R1 / P2; baseline 02dafa857152adab9e8eab488c947b6c34f988e4; history eligibility through unread status, one combined idle synchronization check, necessary-work continuation and recovery/privacy preservation. Distinct follow-up to private-message history/sender synchronization; separate from merged Railspike gating. Canonical checkpoints: Intake and Step 1, 2026-10-29 UTC. Exposed intake 0.75 and handoff 0.75 reaffirmed; extended complete-cycle alternatives A 0.75 / B 0.95, not additive. Rater: Codex single exposed rater after prior conversational/source inspection; all three frozen host-local R1 hashes verified. Pristine pre-inspection intake unavailable, not reconstructed; no measured labor or independent rating. Outcome: Await Approved Step 1; no application changes, commits, dependencies, deployment or accepted-count increment. Production parity and maintainer acceptance unverified/pending; documents remain uncommitted. Concept additions are proposed for implementation, not created during planning.

2026-10-29T20:17:46Z — v3/private_message_sync_idle Step 2 handoff: user approved Step 1 Option A. Feature description/checkpoint defines account history eligibility, one combined idle check, bounded necessary continuation, donor privacy and first-message/new-device recovery. Whole-cycle 0.75 reaffirmed; same v1/A/original baseline/R1/P2, extended mode enabled and single exposed Codex rater; three frozen source hashes reverified. Local verification and separately authorized production replay remain distinct. Await Approved Step 2; no implementation, measured labor or accepted-count increment; planning remains uncommitted.

2026-10-29 UTC — v3/private_message_sync_idle Step 3 handoff: Step 2 approved; requested origin/main update completed at e614fbd9b, preserving original baseline and both ledger append histories. Plan/checkpoint reaffirms cycle 0.75, same v1/A/R1/P2 and exposed single Codex rater. Six stages cover eligibility, sender evidence, combined discovery, client processing, acceptance and documentation; original stage-work estimates 0.12/0.14/0.16/0.16/0.16/0.06, non-additive. Prior exact R1 verification retained. Await Approved Step 3; no application changes, measurement, production acceptance or accepted-count increment.

2026-10-29 UTC — v3/private_message_sync_idle local closeout: summary and evidence. Step 3 approved; entry projection 0.75 reaffirmed and separate retrospective cycle scope 0.80, same v1/A/original baseline/R1/P2 and exposed single Codex rater. Updated implementation base e614fbd9b. Six stages complete; originals 0.12/0.14/0.16/0.16/0.16/0.06 preserved, retrospectives 0.12/0.14/0.16/0.16/0.20/0.06 non-additive. Account gate, combined idle check, necessary continuation and donor/privacy recovery locally verified: focused 41/41 and final query checks 14/14, same-account/sender/direct real-browser flows, network counts, signed toggles across themes and storage/outage recovery pass. Broader list suite bob-link timeout reproduced on untouched main; later unread UI checks remain unverified. Zero dependency/schema delta; no full suite, production replay/deployment, measured labor, merge/push or accepted-count increment. Maintainer fit/acceptance pending; deduplicate worktree copies.

Cycle v3/qdb_memory_audit

Status: Step 4 documentation complete; Steps 1–3 approved for Option A; runtime remediation unapproved; standing P2 enrollment. Scope: v2/A source inventory, preserving v1/B synthetic evidence; baseline cfb8364f6db03cc09e27cd26afb93c109c723a08; R1/P2. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC. Projection: 0.40 total reaffirmed at handoff; alternatives A 0.20 / C 0.90, non-additive whole-audit estimates. Pristine pre-inspection intake missing; prior incident work and source screening disclosed. Rater: Codex, single exposed rater; all three frozen R1 hashes verified. Debug and extended estimates enabled. No measured labor, independent rating, runtime implementation approval or accepted-outcome increment. Relationship: Follow-up to direct fixes 074deea6 and cfb8364f, which remain outside Railspike enrollment. Audit documentation committed; historical executable remains outside this cycle; no application changes or deployment.

2026-10-30 UTC, v3/qdb_memory_audit budget discussion: User questioned the 128 MiB target. Assessment revision proposes 32 MiB ordinary request and 64 MiB maintenance ceilings, with usual 16/48 MiB peaks, pending approval and large-corpus/max-record evidence. Tiny QDB static fixture peaks at 6 MiB under 64M. Audit v1/B scope, original baseline and 0.40 projection reaffirmed; historical 128 MiB evidence preserved. No production setting changes or accepted-outcome increment.

2026-10-30 UTC, v3/qdb_memory_audit task clarification: Assessment and findings now distinguish diagnostic completion from outstanding remediation/capacity acceptance. Lower 32/64 MiB ceilings remain proposed, with 16/48 MiB ordinary peaks, fixed-size 1000/10000/40000-record scaling checks, maximum-record/large-thread/large-commit and recovery coverage, and shared ownership for M02/M04/M09 with v3/load_before_selection_audit. Original 128 MiB evidence retained. Scope v1/B, baseline/R1/P2 and audit-only total 0.40 reaffirmed; implementation is not included in that score or authorized. No new runtime verification or accepted-outcome increment.

2026-10-30 UTC, v3/qdb_memory_audit selection: User chose Option A and requested a separate Option C expansion plan. Current assessment is v2/A; already-performed B probes remain evidence. Preserve original A 0.20 and v1/B 0.40 estimates. Current total 0.40 reflects work already performed; it is not a new source-only estimate or remediation budget. Broader future measurement moves to proposed v3/application_capacity_study; load-before-selection audit choice unchanged. No advancement approval or accepted-outcome increment.

2026-10-30 UTC, v3/qdb_memory_audit Step 2 handoff: User clarified that Approved Step 1 applies to QDB memory audit Option A, not the capacity expansion. Feature description/checkpoint defines documentation-only inventory completion, source/caller validation, evidence labels and linked follow-ups. v2/A, original baseline/R1/P2, debug/extended mode and exposed rater unchanged; total 0.40 reaffirmed including prior probes. No new campaign, application change, accepted outcome or Step 3 approval. Other assessments remain at Step 1. Await Approved Step 2.

2026-10-30 UTC, v3/qdb_memory_audit Step 3 handoff: Step 2 approved. Plan/checkpoint retains v2/A documentation-only scope: validate ten findings/evidence, operator recovery and ownership guidance, then document integrity/closeout. Three planned stages, none executed. Original baseline/R1/P2 and single exposed rater unchanged; frozen hashes reverified; whole-cycle 0.40 reaffirmed. Original stage work S1 0.15 / S2 0.10 / S3 0.08, non-additive, includes checks/corrections; Stage 3 owns shared integrity checks. No runtime changes, new benchmark campaign, branch/commit, measured labor or accepted outcome. Other plans remain unapproved. Await Approved Step 3.

2026-10-30 UTC, v3/qdb_memory_audit Step 4 entry and closeout: Step 3 explicitly approved. Summary/outcome records planning 6a824006, S1 4000874a, S2 7ac4ee39 and the Stage 3 summary-bearing closeout commit. Three stages complete; documentation-only checks passed, runtime/host checks inapplicable or unverified as stated. Same v2/A/original baseline/R1/P2 and single exposed rater; entry projection 0.40 reaffirmed, separate retrospective scope 0.40. S1/S2/S3 original and retrospective stage work 0.15/0.10/0.08, non-additive, no revisions. Maintainer fit/acceptance pending; no measured labor, production recovery claim, merged/pushed release or accepted-count increment. Separate capacity and selection plans remain unapproved and uncommitted.

Cycle v3/agent_posting

Status: Step 1 proposed; standing enrollment P2 Canonical checkpoint: Step 1 handoff, 2026-10-29T19:23:19Z Scope: v1/A; baseline b3a5b1621e9df25bac6e023c26aca66537852dfe; R1/P2 Projected total: 0.85; alternative B 1.30, not additive Exposure: Codex single exposed rater; source inspection preceded rating, pristine intake missing and not reconstructed; all three frozen R1 hashes verified. Extended estimates enabled. Relationship: Full Claude request retained as parent outcome; recommended posting slice first, approval UI deferred to a linked future cycle. No independent child outcome counting by default. Authorization: Review and assessment only; awaiting Approved Step 1. No implementation, dependency additions, measured labor, acceptance or accepted-count increment; planning records uncommitted.

2026-10-29T19:33:45Z Step 2 handoff: Step 1 Option A explicitly approved. Canonical requirements/checkpoint: scope v1.1/A names the portable client v3_client.py per user instruction; first-use signed posting, precise validation, busy JSON, compatible legacy errors, rule discovery and recovery. Whole-cycle 0.85 reaffirmed; original baseline/R1/P2/single exposed Codex rater and missing pristine intake retained. Existing publisher reuse identified; zero dependencies. Request 4 remains follow-up. Await Approved Step 2; no implementation, commits, measured labor or acceptance.

2026-10-29T19:39:27Z v3/agent_posting naming revision: user selected frm.py and /frm.py; Step 2 scope v1.2/A, naming only. Whole-cycle 0.85 reaffirmed; prior snapshots, baseline/R1/P2 and single exposed rater retained. Await Approved Step 2; no implementation or accepted outcome.

2026-10-29T19:51:48Z Step 3 handoff: Step 2 explicitly approved; canonical plan/checkpoint. Scope v1.2/A unchanged; whole-cycle 0.95 revises preserved 0.85 on original-coordinate normalization and uncertain-write recovery inspection. S1–S7/v1 stage work 0.18/0.18/0.12/0.20/0.18/0.08/0.15, not additive. Same baseline/R1/P2, exact hashes reverified, Codex single exposed rater, missing pristine intake retained. Zero dependencies; no implementation, measured labor or accepted outcome. Await Approved Step 3; planning records uncommitted.

2026-10-29T19:57:39Z v3/agent_posting paused explicitly by user before Step 3 approval or implementation. Projection 0.95 retained; pause record. Related new protocol planning is v3/single_request_posting; original requests remain incomplete, not an accepted outcome.

2026-10-30T11:33:22Z v3/agent_posting resumed by user; revised Step 3, protocol integration v1.3/A on prerequisite head 28665bdcd, original baseline retained. Whole-cycle 0.95 reaffirmed, R1/P2 and single exposed Codex rater; three frozen hashes verified. S1–S7 estimates unchanged, with original scopes/history retained and current v2 annotations. Preferred signed bundle plus conservative older-instance fallback, seven stages, zero dependencies. Await agent_posting Approved Step 3; no runtime implementation/tests, measured labor or accepted outcome. Pristine intake remains missing. Predecessor work is separately recorded, not counted again.

2026-10-30 UTC v3/agent_posting Step 4 closeout: entry/stages/outcome, user approved Step 3 v1.3/A. Branch feature/agent-posting, planning 17395d9bb and seven stage commits; original baseline/R1/P2/single exposed Codex rater retained. Entry/projected 0.95 reaffirmed, earlier 0.85 preserved, separate retrospective whole-cycle 1.00. Stage originals 0.18/0.18/0.12/0.20/0.18/0.08/0.15, retrospectives 0.18/0.18/0.12/0.20/0.20/0.08/0.18, non-additive. Portable downloaded frm.py, signed/prepared paths, exact recovery, text diagnostics/discovery and API error consistency delivered locally. Focused PHP 66/66 plus host/schema 3/3; Python failure tests 6/6 and existing publisher tests 7/7 pass. Full suite, deployed/live/other-platform acceptance and large-instance performance unverified. Zero dependency/schema delta; no merge/push/deploy. Grouped approval/session labels remain deferred. Missing pristine intake, unknown measured labor and pending maintainer fit/acceptance retained; no accepted-count increment. Protocol prerequisite work is separately recorded, not counted again.

Cycle v3/single_request_posting

Status: Step 1 proposed; standing P2 enrollment Canonical checkpoint: Step 1, 2026-10-29T19:57:39Z Scope: v1/A; baseline b3a5b1621e9df25bac6e023c26aca66537852dfe; R1/P2 Projected total: 0.85; alternative B 1.05, not additive Exposure: Codex single exposed rater, current API/G2 inspection preceded rating; pristine intake missing, not reconstructed. Frozen R1 verification inherited from this session; extended estimates enabled. Relationship: Related protocol slice while v3/agent_posting is paused; stronger posting scope than the unimplemented G2 two-request proposal, without absorbing G2 votes/browser work. No duplicate outcome accounting. Authorization: Plan only; await Approved Step 1. No implementation, tests, commits, measured labor, dependencies or accepted-count increment.

2026-10-29T20:11:53Z v3/single_request_posting Step 2 handoff: Step 1 Option A approved; canonical requirements/checkpoint. Whole-cycle 0.85 reaffirmed; v1/A clarified, original baseline/R1/P2/single exposed Codex rater and missing intake retained. Requirements cover one-request signed first thread/reply, fingerprint reuse, exact-byte validation, atomic commit, duplicate-safe retry, old-flow compatibility and explicit documentation inventory. frm.py remains paused; no implementation, measured labor, dependencies or accepted outcome. Await Approved Step 2.

2026-10-29T22:37:54Z v3/single_request_posting scope revision: user approved Step 2 v1/A, then during Step 3 investigation rejected ordinary-post bootstrap anchors and requested Option B. Revised Step 2 checkpoint: v2/B uses separately signed dedicated bootstrap and actual post in one HTTP request/commit; known keys/anchors are reused. Whole-cycle 1.05 replaces preserved 0.85 due to scope change, original B 1.05 reaffirmed; above-reference split tradeoff recorded. Same baseline/R1/P2/exposed single rater/missing intake. No Step 3 artifact, implementation, measurements or accepted outcome. Await revised Approved Step 2; frm.py remains paused.

2026-10-29T22:59:48Z v3/single_request_posting Step 3 handoff: revised Step 2 v2/B approved. Canonical plan/checkpoint pins bundled endpoint, dedicated bootstrap, existing-key reuse, atomic recovery, committed-record replay and documentation owners. Whole-cycle 1.05 reaffirmed; eight stages with S1–S8/v1 originals 0.16/0.12/0.20/0.18/0.10/0.10/0.08/0.15, not additive. Above-reference split tradeoff retained; broader transaction/schema work triggers rescope. Same baseline/R1/P2/single exposed rater, exact hashes reverified, missing intake preserved. Await Approved Step 3; no implementation, tests, measured labor, dependency delta or accepted outcome; frm.py remains paused.

2026-10-30 UTC — v3/single_request_posting Step 4 local closeout: entry/stages/limits, revised Step 3 v2/B approved. Original baseline/R1/P2/single exposed Codex rater retained; entry projection 1.05 reaffirmed, separate retrospective 1.10. Eight stages complete locally, stage originals 0.16/0.12/0.20/0.18/0.10/0.10/0.08/0.15; retrospectives unchanged except S8 0.22, non-additive. New API preserves dedicated bootstrap, exact signed bytes, key reuse and atomic replay/recovery. Focused PHP 51/51, subsequent final targeted checks and browser evidence in summary; actual rebuild and byte-preserving repacked snapshot import pass. Direct export/import layout mismatch remains an existing limitation; full rebuild latency is unbenchmarked at production scale. Zero dependencies/schema delta, no measured labor, merge/push/deployment or accepted-count increment. Full suite/live release/physical devices/maintainer fit pending; frm.py remains paused; pristine intake missing.

Cycle v3/load_before_selection_audit

Status: Four documentation audit stages complete; fixes and host validation unimplemented; maintainer acceptance pending. Scope: v1/B codebase-wide audit of loading whole collections before selection; baseline cfb8364f6db03cc09e27cd26afb93c109c723a08; R1/P2. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC; 0.55 total reaffirmed. Alternatives A 0.20 / C 0.90, non-additive whole-audit projections. Rater: Codex, single exposed rater; prior memory-audit exposure explicit; all three frozen hashes verified. Debug and extended estimates enabled. No measured labor, independent rating or accepted outcome. Relationship: Related to v3/qdb_memory_audit, broadening from memory to unnecessary work before selection. Seed findings overlap and must not be counted as independent discoveries. No application changes, dependency additions, commits or deployment.

2026-10-31 UTC, v3/load_before_selection_audit Step 2 handoff: Requirements/checkpoint. v1/B/original baseline/R1/P2 retained; source context ade35a65 includes delivered fixes, without resetting history. Whole-cycle 0.55 reaffirmed; single exposed Codex rater, all frozen hashes reverified, debug/extended enabled. Documentation-only audit with disposable local probes and explicit family coverage; no fixes, automated detection or production capacity claim. No measured labor, independent rating or accepted outcome. Await Approved Step 2.

2026-10-31 UTC, v3/load_before_selection_audit Step 3 handoff: Step 2 approved. Plan/checkpoint retains v1/B/original baseline/R1/P2 and single exposed Codex rater; frozen hashes verified. Whole-cycle 0.55 independently reaffirmed; original stage work S1 0.08 / S2 0.18 / S3 0.18 / S4 0.11, non-additive, not hours. S1 owns baseline/conventions; S2/S3 own family probes; S4 owns consolidation. Documentation-only scope, explicit local/host evidence limits; no audit execution, runtime fixes, measured labor or accepted outcome. Await Approved Step 3; new planning artifacts remain uncommitted.

2026-10-31 UTC, v3/load_before_selection_audit Step 4 closeout: Step 3 explicitly approved. Entry/stages/outcome. Same v1/B/original baseline/R1/P2; frozen hashes verified; single exposed Codex rater. Entry total 0.55 reaffirmed, separate retrospective scope 0.55; stage originals/retrospectives S1 0.08 / S2 0.18 / S3 0.18 / S4 0.11, no revisions, non-additive. Four stages complete: ranked tracked causes, coverage/exceptions, concept and operator handoff. All 24 local selection samples passed IDs/count checks at 128 MiB; QDB reader 8/60 MiB, offline selection 4/24 MiB for 1000/10000 candidates. Direct-method synthetic evidence only; SQL scans/full UI/build/production recovery unverified. Documentation-only changes, zero dependencies/runtime/schema delta; no merge/push/deployment, measured labor or accepted-count increment. Maintainer fit/acceptance pending.

Cycle v3/application_capacity_study

Status: Seven documentation investigation stages complete locally; measured failures/deferred coverage retained; real host and study acceptance pending. Scope: v1/B workload-family capacity study; baseline cfb8364f6db03cc09e27cd26afb93c109c723a08; R1/P2. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC. Projection: Parent Option C 0.90 retained as inherited. Current whole-cycle 0.90 reaffirmed; alternative A 0.75, non-additive. Includes local harness, fixtures, per-family/concurrent measurements, recovery checks and reporting, not remediation or guaranteed host access. Rater: Codex, single exposed rater; prior audit/probe exposure and verified R1 carried forward. Debug/extended estimates enabled; no pristine independent discovery claim, measured labor or accepted outcome. Relationship: Separate expansion of v3/qdb_memory_audit. Reuse earlier findings without counting them twice; coordinate with v3/load_before_selection_audit. No application changes, dependencies, measurement campaign, commits or deployment.

2026-10-31 UTC, v3/application_capacity_study Step 2 handoff: Step 1 Option B approved. Requirements/checkpoint retain v1/B/original baseline/R1/P2; whole-cycle 0.90 reaffirmed, all three frozen hashes verified, Codex single exposed rater. Documentation-only investigation with disposable local harnesses, normal-entry family coverage, isolated/overlap measurements, semantic parity and interruption recovery; host evidence explicitly separate. Current inspection 3dc2c3fe includes later QDB fixes without resetting original history. Zero dependencies/runtime changes; no campaign, measured labor or accepted outcome. Await Approved Step 2; planning remains uncommitted.

2026-10-31 UTC, v3/application_capacity_study Step 3 handoff: Step 2 v1/B approved unchanged. Plan/checkpoint retains original baseline/R1/P2 and single exposed Codex rater; all frozen hashes reverified. Whole-cycle 0.90 independently reaffirmed; stage-work originals S1–S7 0.12/0.16/0.18/0.14/0.10/0.14/0.10, non-additive. Seven bounded stages cover isolated fixtures, normal-entry families, interruption/retry, overlap and qualified report. S1 owns shared setup, S7 consolidation. No runtime/test/config changes, new dependencies, measurements, measured labor or accepted outcome. Await Approved Step 3; plans remain uncommitted.

2026-11-01 UTC, v3/application_capacity_study Step 4 closeout: User approved Step 3 v1/B unchanged. Canonical summary/checkpoint and capacity report. Original baseline/R1/P2 and single exposed Codex rater retained; frozen hashes verified. Whole-cycle entry 0.90 reaffirmed; separate retrospective 1.00. Seven stages complete under explicit family/dimension dispositions; stage originals retained and retrospectives non-additive. Normal HTTP/CLI measures 72 MiB public pages at 10000 records and repeated 128 MiB rebuild failure at 40000; recovery retains prior model and smaller reset publishes. Eighteen 30-second parallel/overlap windows, 4627 requests, zero errors; latency criteria passed locally. Signed/image/archive parity and offline import resume verified; direct import-repository layout failure retained. Earlier instrumentation failures and omitted shapes/roles documented. Documentation-only changes, zero dependencies/runtime/schema delta; actual PHP 8.3/FastCGI host, full suite, long soak and maintainer fit/acceptance unverified/pending. No measured labor, independent rating, merge/push/deployment or accepted-count increment.

Cycle v3/qdb_rebuild_scope

Status: Six stages locally complete; early integration pushed at user request; production and maintainer acceptance pending. Scope: v1/B catalog plus proposed bounded tag browsing as the first rebuild-cost fix; baseline 0392dd59c0646bebc37042455ecaccf825b13889; R1/P2 standing enrollment. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC. Total 0.85 reaffirmed; alternatives A 0.30/C 1.15, non-additive. C requires split discussion. Rater: Codex single exposed rater after prior audits/fix and initial source inspection; pristine prospective intake missing. Three frozen R1 hashes verified. Debug/extended enabled; no measured labor, independent rating or accepted outcome. Relationship: Reuses QDB audit M02/M04, follows direct tags-index fix 16465fed, and leaves capacity/load-before-selection audits separate. New tag-page production incident is recorded in the catalog. No duplicate discovery/outcome, runtime changes, dependency additions, commit or deployment. Optional prebuilding and selective derivation remain separately scoped follow-ups.

2026-10-30 UTC, v3/qdb_rebuild_scope Step 2 handoff: Step 1 Option B approved. Requirements/checkpoint defines 25-item tag pages, complete native traversal, first-page publication, frontend/offline position recovery, source-backed catalog and explicit PHP 8.3 host acceptance. v1/B/original baseline/R1/P2 and single exposed rater unchanged; three frozen hashes reverified; whole-cycle 0.85 reaffirmed. Fixed-result 1000/10000/40000-record checks proposed at 32 MiB public/64 MiB tag generation, max 4 MiB growth, with maximum-valid-record testing separately at 128 MiB. No runtime work, measured labor, accepted outcome or Step 3 approval. Await Approved Step 2; planning remains uncommitted.

2026-10-30 UTC, v3/qdb_rebuild_scope Step 3 handoff: Step 2 approved; all-site tag behavior explicitly confirmed in scope. Development plan/checkpoint has six stages through bounded live selection, traversal/recovery, static serving, offline saved paging, incident/scaling checks and UI/catalog/operator handoff. Same v1/B/baseline/R1/P2/exposed rater; frozen hashes reverified; whole-cycle 0.85 reaffirmed. Original stage-work estimates 0.20/0.12/0.12/0.18/0.15/0.14 are non-additive, not measured work. No implementation or host recovery; await Approved Step 3. Uncommitted plans and cycle-scoped closeout bookkeeping preserve unrelated drafts.

2026-10-30 UTC, v3/qdb_rebuild_scope Step 4 closeout: Entry, stages and outcome. Step 3 approved; entry 0.85 reaffirmed, separate retrospective cycle 0.85. Same v1/B/baseline/R1/P2 and single exposed rater. Six stages complete, originals 0.20/0.12/0.12/0.18/0.15/0.14 retained; retrospectives 0.20/0.12/0.12/0.18/0.15/0.16, non-additive. Final focused 63/63 plus online/offline real-browser acceptance and 16 theme styles at phone/desktop; fixed-result scaling 6 MiB through 40000 threads, one exact-limit record 38 MiB. Early merge/push c4933cc5 explicitly requested before final tests. No dependencies, full-suite/physical-device/live-host claim, measured work or accepted outcome; maintainer fit/acceptance pending. Optional prebuilding and other memory findings remain separate.

Cycle v3/history_purge

Status: Step 4 complete locally (seven stages committed); maintainer acceptance and merge pending; standing enrollment P2 Canonical checkpoints: Step 1 handoff, 2026-10-30T20:30:04Z; Step 2; Step 3; Step 4 entry and Stage 1; Stage 2; Stage 3; Stage 4; Stage 5; Stage 6; Stage 7 and closeout Scope: v1 / Option A; baseline 2e17c971308a710a540c905e738048c4f51e53ca; R1 / P2 Projected total: 0.80; alternatives B 0.60 and C 0.35, not additive Exposure: Claude single exposed rater; handoff, receipt spec, exporter, import, source-route and read-model history consumers inspected before rating while writing the Nostr comparison; pristine intake missing, not reconstructed. All three frozen R1 hashes verified. Extended estimates and debug enabled. Relationship: Release 2 of the retraction simplification direction; follows v3/unified_removal_format (receipt format) and v3/retraction_effects; same stable ID across worktrees. Authorization: Step 1 requested by the user; awaiting Approved Step 1. No implementation, history rewrite, measured labor, acceptance or accepted-count increment. Planning, debug log and this ledger entry uncommitted.

2026-10-30 UTC Step 2 handoff: Approved Step 1 received for Option A; canonical feature description/checkpoint. Whole-cycle 0.80 reaffirmed; scope v1/A, baseline 2e17c971, R1/P2 and single exposed Claude rater unchanged. Requirements: receipt-driven worklist, built-in Git under the existing lock with preview/run, committed Key: value commit map resolving old source links, verified removal before success, honest limits. Sizing gate on a QDB-derived copy at Stage 1 decides between filter-branch and horizon squash behind the same contract. Pristine intake remains missing. Await Approved Step 2; no implementation, measured effort or accepted-count increment. Planning uncommitted since the Step 1 commit.

2026-10-30 UTC Step 3 handoff: Approved Step 2 received; canonical development plan/checkpoint. Whole-cycle 0.80 reaffirmed; stage-work originals S1–S7/v1 0.15/0.10/0.20/0.10/0.10/0.10/0.15, not summed; Stage 7 owns shared acceptance. Stages: sizing gate and planner, commit map record, rewrite engine with restore and verification, map commit and rebuild, source-route resolution, CLI/runbook/concepts, QDB-copy acceptance and closeout. Scope v1/A, baseline 2e17c971, R1/P2 and single exposed Claude rater unchanged; pristine intake remains missing. Await Approved Step 3; no implementation, measured effort or accepted-count increment.

2026-10-30 UTC Step 4 entry: Approved Step 3 received; branch feat/history-purge, planning commit 7dfc7118. Whole-cycle 0.80 reaffirmed; stage originals unchanged. Environment limit: no QDB-derived copy locally; the sizing gate runs on a synthetic QDB-shaped repository and is recorded as synthetic.

2026-10-31 UTC Stage 1 checkpoint: sizing gate and planner complete, Stage 1 record. Engine decision: fast-export stream rewrite (user-confirmed), replacing both engines the plan named within the unchanged Option A contract. Stage 1 retrospective 0.20 against original 0.15 (rewrite primitive and map capture pulled forward). Stage 3 material revision 0.20 to 0.15, new understanding not changed scope. Whole-cycle 0.80 reaffirmed independently. Synthetic measurements only; no measured labor, no accepted outcome, Stage 7 acceptance still owed.

2026-11-01 UTC Stage 2 checkpoint: commit map record contract complete, Stage 2 record. Spec history_rewrite_record_v1, CommitMap codec/resolver with 100,000-block parts under the 16 MiB record limit, validator and activity label updates; 4/4 focused plus 21 neighbouring tests pass. Stage 2 retrospective 0.10 against original 0.10. Whole-cycle 0.80 reaffirmed. No measured labor, no accepted outcome; Stages 3-7 pending.

2026-11-01 UTC Stage 3 checkpoint: rewrite engine with restore and verification complete, Stage 3 record. HistoryPurge under the shared write lock: journal, rewrite, ref verification with restore on failure, prune, object-id verification; interrupted runs restored automatically before prune and reported by the planner after. 13/13 focused tests; synthetic 100,010-commit purge verified in 35 s. Stage 3 retrospective 0.15 against revised original 0.15. Whole-cycle 0.80 reaffirmed. No measured labor, no accepted outcome; Stages 4-7 pending.

2026-11-01 UTC Stage 4 checkpoint: map commit and rebuild complete, Stage 4 record. HistoryPurge::run commits the history rewrite record with a fixed subject, rebuilds the read model, truncates the commit-manifest cache, clears or marks the stale marker, regenerates static artifacts when a root is given. 14/14 focused tests including a real rebuild before and after. Stage 4 retrospective 0.10 against original 0.10. Whole-cycle 0.80 reaffirmed. No measured labor, no accepted outcome; Stages 5-7 pending.

2026-11-01 UTC Stage 5 checkpoint: source routes resolve old identities, Stage 5 record. Blob and commit routes consult the map after Git misses, name the resolved identity, and keep the deletion notice for purged paths; every Step 2 consumer classified as resolved, rebuilt, refused or documented. 39/39 focused and neighbouring tests. Stage 5 retrospective 0.08 against original 0.10. Whole-cycle 0.80 reaffirmed. No measured labor, no accepted outcome; Stages 6-7 pending.

2026-11-01 UTC Stage 6 checkpoint: CLI, runbook and concept entries complete, Stage 6 record. ./v3 purge-history preview|run --confirm=<root> under the CLI contract, runbook with backup, pause, verification, mirrors and recovery, three concept entries, references linked. 17/17 focused tests including a full purge through the dispatcher with static build; docs links resolve; one long-standing docs static failure inherited. Stage 6 retrospective 0.10 against original 0.10. Whole-cycle 0.80 reaffirmed. No measured labor, no accepted outcome; Stage 7 pending.

2026-11-01 UTC Step 4 local closeout: Stage 7 evidence and closeout. Planning 7dfc7118, stages ca583ae9 a7e72b65 42339396 ecf9c1e3 9b2d8280 db58dfda plus the Stage 7 commit; seven of seven complete locally. Scope v1/A, baseline 2e17c971, R1/P2, single exposed Claude rater. 0.80 original projection; 0.80 retrospective scope assessment, independently judged. Stage retrospectives 0.20/0.10/0.15/0.10/0.08/0.10/0.15 against originals 0.15/0.10/0.20(0.15)/0.10/0.10/0.10/0.15, non-additive. Engine deviation (fast-export stream, user-confirmed) within the unchanged contract. Acceptance on a real-receipt clone (57 of 87 commits rewritten, receipts byte-identical, read model identical except commit identities) and a QDB-derived clone (14,887 quotes, delete-record receipt, verified in 10.5 s); HTTP old-link resolution, interrupted-run restore and image-backup refusal replayed. Full suite 1730/1737 with five inherited failures and two load-sensitive tests passing in isolation; not an unqualified pass. Entry note corrected: QDB-derived copies did exist in sibling checkouts. Zero dependency delta. Maintainer comfortable-fit judgment, acceptance, merge and any production run pending; no measured labor, independent rating or accepted-count increment.

2026-11-01 UTC correction after closeout: user asked run to confirm interactively instead of requiring --confirm=<root>; follow-up record. Prompt on the terminal, --yes to skip, refusal without a terminal; dispatcher tests 2/2 and a pseudo-terminal check. Correction to Stage 6, not a new request; scores unchanged, acceptance still pending.

2026-11-01 UTC correction after closeout: user asked for progress reporting during run; follow-up record. Phase and commit-count progress on stderr through a closure in the engine, rebuild and static builders; one redundant read-model rebuild removed. 17/17 focused tests and two watched synthetic runs. Correction, not new scope; scores unchanged, acceptance still pending.

2026-11-01 UTC correction after closeout: preview now lists accepted delete receipts whose post has no file left in history; follow-up record. 10/10 focused tests. Scores unchanged, acceptance still pending.

2026-11-01 UTC merge onto main (7272877f): no conflicts in code; scripts/purge_history.php now resolves its path defaults through DeploymentSettings to satisfy the deployment-settings rule that landed after the baseline; follow-up record. 17/17 focused tests. Scores unchanged, acceptance still pending.

2026-10-30 UTC, v3/qdb_rebuild_scope host update: User reports successful production build and activation of release-20261030201011-af62aa46 in 314.961 seconds; 5253 HTML files/53 assets. Operator evidence closes the previously unverified build outcome as user-reported, not agent-observed. Published pagination checks and study comfortable-fit judgment not separately supplied. Timing reduction moves to distinct v3/qdb_build_time; original scope/estimates preserved.

Cycle v3/qdb_build_time

Current status: Eight stages locally implemented and verified; production replay and maintainer fit/acceptance pending. Initial Step 1 status: Awaiting review; implementation then unapproved. Scope: v1/A optional profile prebuilding with preserved runtime/static-only delivery and before/after measurement; baseline 4abda3dbd144370a3353781b29e8690e46d47d88; R1/P2 standing enrollment. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC; 0.50 total reaffirmed. Alternatives B 0.90/C 1.25, non-additive; C requires split. Rater: Codex single exposed rater; prior audit/fix and initial source exposure before checkpoint, pristine intake missing; all three frozen R1 hashes verified. Debug/extended enabled; no measured labor or accepted outcome. Relationship: Follows v3/qdb_rebuild_scope successful host activation and reuses QDB audit M03; no duplicate discovery/outcome. Separate capacity/load-before-selection plans remain pending. No application/config changes, dependencies, measurement campaign, commits or deployment in this handoff.

2026-10-30 UTC, v3/qdb_build_time selection revision: User chose Option C, combining optional profile prebuilding, commit indexing and activity evidence optimization. Selection/checkpoint records v2/C total 1.25 reaffirmed from the existing alternative; original v1/A 0.50 retained. Same baseline/R1/P2/single exposed rater. Prior split recommendation discussed; user selects combined scope, subject to normal stage/day sizing before implementation. No Step 1 approval, runtime work or accepted outcome; await Approved Step 1.

2026-10-30 UTC, v3/qdb_build_time Step 2 handoff: Step 1 Option C explicitly approved. Requirements/checkpoint defines independent profile-prebuild control with preserved defaults/runtime/static-only recovery, equivalent commit counts/history, bounded evidence reuse, and separate repeated before/after measurements plus combined full-build acceptance. v2/C/baseline/R1/P2/exposed rater unchanged; frozen hashes reverified; total 1.25 reaffirmed, original v1/A 0.50 retained. No implementation, measured work, production timing improvement or accepted outcome. Await Approved Step 2; combined stage/day feasibility remains a planning gate.

2026-10-30 UTC, v3/qdb_build_time Step 3 handoff: Step 2 C approved. Development plan/checkpoint covers eight stages: baselines, profile control, transitions, streamed commit indexing, operation-local disk-backed evidence reuse, maintenance/recovery parity, separate/combined measurements, and operator closeout. v2/C/baseline/R1/P2/exposed rater unchanged; total 1.25 reaffirmed; original stage work 0.15/0.16/0.15/0.20/0.23/0.16/0.15/0.10 non-additive. Frozen hashes verified. Timing/noise, memory and runtime-profile gates fixed before coding; stage/day ceiling and failure gates retained. No implementation, benchmarks or accepted outcome; await Approved Step 3.

2026-10-30 UTC, v3/qdb_build_time Step 4 local closeout: Entry/stages/outcome. Approved Step 3, v2/C, original baseline/R1/P2/single exposed rater retained. Entry 1.25 reaffirmed; prospective whole-cycle revision 1.35 at S7 after scratch overhead discovery; separate retrospective 1.40. Stage originals 0.15/0.16/0.15/0.20/0.23/0.16/0.15/0.10 retained; S7 revised 0.22; retrospectives 0.18/0.13/0.15/0.18/0.22/0.14/0.27/0.12, non-additive. All three fixed workload timing gates, exact data parity, memory/runtime budgets and normal CLI activation pass; supplemental small-commit evidence costs 0.0407s (8.7%) more and is disclosed. Full production replay, full-suite result, maintainer comfortable-fit judgment and acceptance remain pending. One unchanged baseline timing-progress test failure is recorded; no dependency/schema delta, measured labor, independent rating, merge/push/deployment or accepted-count increment. Preserve v1/A 0.50, failed/noisy samples and deduplicate worktree copies.

Cycle v3/multi_redemption_invites

Date: 2026-10-30 UTC Status: Step 1 planning handoff; awaiting approval; no multi-redemption implementation Scope: v1; baseline 2e17c971308a710a540c905e738048c4f51e53ca plus uncommitted invite-copy cleanup; capped shared invites with compatible replay, atomic capacity and retry recovery. Separately authorized 30-day browser default excluded from cycle. Reference: R1 / P2; exact three frozen source hashes verified; standing enrollment; extended estimates enabled Projection: Intake 0.85 and Step 1 0.85 reaffirmed; Codex single exposed rater; prior invitation inspection disclosed Canonical checkpoints: Step 1 snapshots Alternatives: A/v1 0.85; B/v1 0.70; independent alternative whole-cycle projections, not additive Relationship: New cycle; related invitation-entry and approval-acceptance work, no split outcome Outcome: Planning only; no measured effort, independent rating, implementation approval or accepted outcome. Records uncommitted; deduplicate worktree copies by stable cycle ID.

2026-10-31 UTC, v3/multi_redemption_invites Step 2 handoff: Step 1 approved; recommended Option A selected. Requirements and checkpoint retain scope v1/original baseline/R1/P2, 0.85 projected total reaffirmed. Default-one finite capacity, 30-day browser expiry without selector, atomic distinct-key acceptance, duplicate recovery, partial-use revocation, legacy preservation and rebuild/import parity. R1 exact hashes reverified; Codex single exposed rater, debug/extended enabled. No application work, tests, measured effort or accepted outcome. Await Approved Step 2; new planning/ledger changes uncommitted.

2026-10-31 UTC, v3/multi_redemption_invites Step 3 handoff: Step 2 approved. Plan/checkpoint defines six bounded stages for signed limits, accepted-recipient replay, atomic APIs/recovery, normal UI, restore/exclusion parity and release verification. Same scope v1/original baseline/R1/P2; 0.85 whole-cycle projection reaffirmed. Stage-work originals S1–S6 0.12/0.18/0.20/0.16/0.12/0.12, non-additive; frozen hashes verified, Codex single exposed rater. Content import retains invitation-authority exclusion; trusted restore retains counts. No runtime change/tests, measurement or acceptance; await Approved Step 3, new planning records uncommitted.

2026-10-31 UTC, v3/multi_redemption_invites scope revision: user explicitly excludes all UI changes. Step 2 v2 and Step 3 v2 now specify backend-only issuance/redemption/revocation with unchanged browser compatibility. Whole-cycle v2 0.70, earlier v1 0.85 retained in history. S4/v2 0.08 and S6/v2 0.08; S1/S2/S3/S5 unchanged 0.12/0.18/0.20/0.12. Same baseline/R1/P2, frozen hashes verified, Codex single exposed rater, debug/extended enabled. Scope change removes UI/visual work, not authority/replay safeguards. No implementation, measured work or accepted outcome; await revised Step 3 approval.

2026-10-31 UTC, v3/multi_redemption_invites: user explicitly reapproved Steps 1 and 2 for backend-only scope v2. Step 3 handoff reaffirmed at 0.70 whole-cycle effort, unchanged stage estimates and original baseline/R1/P2; frozen hashes reverified. Codex single exposed rater; no new scope, runtime work, measured effort or accepted outcome. Await Approved Step 3; planning remains uncommitted.

2026-10-31 UTC, v3/multi_redemption_invites Step 4 local closeout: canonical entry/stages/outcome. User approved Step 3 for backend-only v2; six stages implemented on feat/multi-redemption-invites, planning 465d3b38. Original baseline/R1/P2/single exposed Codex rater retained; frozen hashes verified. Entry projection 0.70 reaffirmed, separate retrospective cycle 0.80; stage originals 0.12/0.18/0.20/0.08/0.12/0.08, retrospectives 0.12/0.18/0.20/0.10/0.12/0.10, non-additive. Signed bounded APIs, distinct-key atomic capacity, same-key recovery, prospective revocation and replay/restore delivered without frontend changes. Final focused PHP 77/77, client 92/92 and export/import 26/26 pass (overlapping); real Chrome capped and legacy public/members-only suites pass. Initial manual browser acceptance-time failure did not recur; cause unresolved. Existing archive wrapper mismatch requires repacking; full suite/live deployment/full-history restore/old-reader rollback not verified. Zero dependencies/schema delta, no measured labor, independent rating, merge/push/deployment or accepted-count increment. Maintainer comfortable-fit/acceptance pending; preserve v1 history and deduplicate worktrees.

Restore invitation prompt

Cycle: v3/restore_invitation_prompt Status: Step 1 proposed; standing P2 enrollment; implementation unapproved Checkpoint: Step 1, 2026-11-01 UTC Scope: v1/A; baseline 767a8a2ba8270e29269fd9d2f6d2e707bff8ffa4; R1/P2 Projection: First recorded Step 1 total 0.55; alternatives B 0.25 / C 0.65, non-additive Evidence: Three frozen R1 hashes verified; Codex single exposed rater; prior source diagnosis disclosed, pristine intake missing. Debug and extended estimates enabled. Relationship: Separate invitation-naming follow-up to v3/multi_redemption_invites; no inherited implementation approval or branch reuse authorization. Outcome: Planning only; no measured labor, independent rating, accepted outcome or count increment. Planning and ledger changes remain uncommitted; await Approved Step 1.

2026-11-01 UTC, v3/restore_invitation_prompt selection revision: User selected inline Username entry with Redeem invitation. Revised Step 1 records v2/C, whole-cycle 0.65 reaffirmed from the original C alternative; v1/A 0.55 retained. Same baseline/R1/P2/single exposed rater; hashes reverified. Same-key initial naming, Account recovery, field preservation on failure and targeted-entry compatibility remain proposed. Revised Step 1 approval pending; no Step 2, implementation, measured effort or accepted outcome.

2026-11-01 UTC, v3/restore_invitation_prompt Step 2 handoff: Step 1 Option C explicitly approved. Requirements/checkpoint define inline untargeted naming, same-key initial guest naming despite disabled later renaming, Account recovery, authoritative one-time eligibility and partial-success retry. Scope v2/C, original baseline/R1/P2 and single exposed rater retained; 0.65 whole-cycle projection reaffirmed, earlier A 0.55 preserved. Frozen hashes verified; pristine intake remains missing. No runtime work, measured effort or accepted outcome; await Approved Step 2.

2026-11-01 UTC, v3/restore_invitation_prompt Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint retains v2/C; whole-cycle 0.75 revises 0.65 for durable committed-name retry and cross-tab recovery within approved requirements. Original A 0.55/C 0.65 preserved. Five stages, original stage work S1 0.12 / S2 0.15 / S3 0.12 / S4 0.15 / S5 0.14, non-additive; S5 owns shared checks. Same baseline/R1/P2 and single exposed rater; frozen hashes verified. No implementation, measured labor or accepted outcome; await Approved Step 3.

2026-11-01 UTC, v3/restore_invitation_prompt Step 4 local closeout: User approved Step 3; entry/stages/outcome. New branch feat/invitation-username, planning 4cb17b77 and five sequential stage commits. Same v2/C/original baseline/R1/P2/single exposed rater; entry 0.75, revised whole-cycle 0.85 for first-paint and transaction recovery corrections, separate retrospective 0.85. S1–S5 originals 0.12/0.15/0.12/0.15/0.14 retained; S5 revised 0.22; retrospectives 0.12/0.15/0.12/0.16/0.24. Non-additive judgments, no measured labor. Final focused 177/177 and Chrome naming/Account/legacy/capped suites passed; all 16 permitted themes at phone/desktop checked. Zero dependencies/schema changes. Full suite, physical devices, production scale and actual user deployment unverified; no merge/push/deploy or accepted-count increment. Maintainer acceptance pending; missing pristine intake retained.

<a id="cycle-v3recent_activity"></a>

v3/recent_activity — Reader-facing recent conversation

Status: Step 1 proposed; standing P2 enrollment; no implementation authorization. Canonical checkpoints: Step 1 intake and handoff, 2026-10-30T20:30:16Z. Scope: v1/A; baseline 3a21fab67708c07ef77712790218e12a92c61bcd; R1/P2; dedicated public thread/reply feed with ordinary navigation, exact-post links, bounded native pagination and recovery. Projection: exposed intake 0.75; Step 1 handoff 0.75 reaffirmed. Pristine pre-inspection intake unavailable; prior catalog/source/status exposure disclosed. Inherited feedback-only 0.5 preserved separately. Option totals A 0.75 / B 0.95 / C 0.35 are alternatives, not additive. Rater: Codex, single exposed rater; frozen R1 hashes verified; debug and extended estimates enabled. Relationship: PF-20261021-F04; distinct from completed local Activity performance work. No second observation for worktree copies. Outcome: Await Approved Step 1; no measured labor, runtime acceptance, implementation, commits or accepted-outcome increment. Maintainer comfortable-fit judgment pending. This ledger bookkeeping is within the cycle's planning documentation boundary.

2026-10-30T20:37:32Z — v3/recent_activity Step 2 handoff: user approved Step 1 Option A. Feature description/checkpoint defines ordinary Recent navigation, individual public contributions, compact previews/exact-post links, bounded native pagination, visibility, static/live serving and recovery. Scope v1/A, original baseline/R1/P2, single exposed Codex rater and missing pristine intake retained; whole-cycle 0.75 reaffirmed, frozen hashes reverified. Debug/extended mode enabled. No implementation, runtime acceptance, measured labor or accepted-count increment; planning remains uncommitted. Await Approved Step 2.

2026-10-30T20:44:52Z — v3/recent_activity Step 3 handoff: Step 2 approved. Development plan/checkpoint retains v1/A and original baseline/R1/P2; whole-cycle 0.85 revises preserved 0.75 for inspected attribution, index/startup and static-invalidation obligations, not changed outcome. Seven stage-work originals S1–S7: 0.10/0.18/0.15/0.10/0.15/0.15/0.05, non-additive; S6 owns shared acceptance. Single exposed Codex rater, hashes verified, missing pristine intake/inherited 0.5 retained. Await Approved Step 3; no implementation, runtime acceptance, measured labor, commits or accepted-count increment.

2026-10-30 UTC — v3/recent_activity Step 4 local closeout: user approved Step 3 and requested deletion of mockups (deleted, never committed). Canonical entry/stages/release/closeout; v1/A, original baseline/R1/P2, single exposed Codex rater retained. Entry projection 0.85 reaffirmed; separate retrospective whole-cycle scope assessment 0.85. Seven stages complete locally; original and retrospective stage work 0.10/0.18/0.15/0.10/0.15/0.15/0.05, non-additive. 213 affected checks: 208 initial passes, two progress assertions corrected and rerun successfully, three remaining failures reproduced at original baseline; additional high-traffic fallback passes. Browser 13 themes at two widths, no-JavaScript exact-post/paging/Back/reload/reconnect pass; 1k/10k/40k bounded-query evidence recorded. Schema 39 needs rebuild/republish. Zero dependencies; no measured labor, merge/push/deployment or accepted-count increment. Maintainer fit, physical-device and production acceptance pending; original 0.75, inherited 0.5 and missing pristine intake preserved. No separate worktree outcome.

Cycle v3/ui_tools_launcher

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/ui_tools_launcherStep 4 complete; merged; maintainer fit pendingv1 / R1 / P20.40 intake; 0.40 Step 1 (Option A); 0.45 Step 2; 0.45 Step 3; 0.45 Step 4 entry (reaffirmed); 0.45 retrospective scope assessmentStep 1 and snapshots · Step 2 · Step 3 · Step 4No parent; cycle 9 of the UI redesign checklist

2026-10-31T00:34:06Z intake, standing enrollment P2, baseline main 41a6dbe9c, R1 hashes verified. Scope v1: checklist Cycle 9 (grouped Tools launcher, each tool once, data-tone/data-shape hooks, icon themes). 0.40 recorded before source inspection; exposure: checklist item, mockup notes from earlier sessions, AGENTS.md icon rule. Claude (claude-opus-5-5) single exposed rater.

2026-10-31 Step 1 handoff: assessment recommends Option A (one grouped launcher, same tools for everyone); 0.40 reaffirmed. Extended options A 0.40, B 0.75 (hide by access before paint), C 0.45 (back link instead of subnavigation), not additive. No implementation, measurement or accepted outcome; planning and ledger uncommitted.

2026-10-31 Step 2 handoff: Step 1 Option A approved ("approved step 1"). Feature description/checkpoint: 15 tools once in four groups, Account removed, Tools bar in the same order on every tool page, data-tone/data-shape hooks, every site and permitted theme. 0.45 (new understanding: Tools bar on 15 pages and launcher styles shared with Bookmarklets); 0.40 Step 1 retained. Same rater/R1/P2/baseline. No implementation; awaiting Approved Step 2.

2026-10-31 Step 3 handoff: Step 2 approved ("approved step 2"). Four-stage plan/checkpoint: registry and bar, grouped launcher, site/theme matrix, records. 0.45 reaffirmed; stage work S1 0.10, S2 0.15, S3 0.15, S4 0.05, not additive. Same rater/R1/P2/baseline. No implementation; awaiting Approved Step 3.

2026-11-01 Step 4 closeout: Step 3 approved 2026-10-31 ("approved step 3"); Step 4 summary, branch feat/ui-tools-launcher from 41a6dbe9c, planning 58f8906cc, stages 162623aa2, 8804bffb7, 429f66ea3, merged to main 32918c910 on 2026-10-31; Stage 4 (records) on chore/ui-tools-launcher-stage4. 0.45 reaffirmed at entry, no in-cycle revision; separate 0.45 retrospective scope assessment (work matched the plan; the post-Stage 2 review changes and closeout matrix fit the rating). Rater change disclosed: Steps 1–3 and Stages 1–2 rated by claude-opus-5-5; the review pass, Stage 3 and closeout by claude-fable-5-1; original ratings untouched. Four of four stages; stage work original/retrospective 0.10/0.10, 0.15/0.15, 0.15/0.15, 0.05/0.05 (not summed). Browser matrix on four sites, every permitted theme, two widths passed; full suite once 1740 run, 1734 passed, six failures predate the cycle or reproduce without its code. Zero dependency delta; no measured labour; maintainer fit pending; no accepted-count increment.

Cycle v3/message_sync_activity

Status: Eight stages locally complete; maintainer acceptance and deployment pending; standing P2 enrollment; deduplicate worktrees. Scope: v2/A; baseline 4b14e622f3cca6cb8f041145fd1df954bacc74e4; R1/P2; extended estimates enabled. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC; exposed intake 0.85, handoff 0.85 reaffirmed. Codex single exposed rater; frozen source hashes verified. Earlier implementation/diagnostic/discussion exposure disclosed; no pristine intake reconstruction. Relationship: One of three separately requested follow-ups (message_sync_activity, key_retirement, active_key_limit); preserves the merged private_message_sync_idle cycle and its incomplete production outcome. Dependency links and distinct scopes in assessment; estimates are not additive. Outcome: Local implementation complete; see closeout below. Original estimates and incomplete compatibility checkpoint retained; no measured labor or accepted-count increment; maintainer judgment pending.

Cycle v3/key_retirement

Status: Eight stages locally complete; maintainer acceptance and deployment pending; standing P2 enrollment; separate stable ID, deduplicate worktrees. Scope: v3/A; baseline 4b14e622f3cca6cb8f041145fd1df954bacc74e4; R1/P2; extended estimates enabled. Canonical checkpoints: Intake and Step 1, 2026-10-30 UTC; exposed intake 0.95, handoff 0.95 reaffirmed. Codex single exposed rater; frozen source hashes verified. Earlier implementation/diagnostic/discussion exposure disclosed; no pristine intake reconstruction. Relationship: One of three separately requested follow-ups (message_sync_activity, key_retirement, active_key_limit); preserves the merged private_message_sync_idle cycle and its incomplete production outcome. Dependency links and distinct scopes in assessment; estimates are not additive. Outcome: Local implementation complete; see closeout below. Original projections and gate history retained; no measured labor or accepted-count increment; maintainer acceptance pending.

2026-10-30T11:47:06Z — v3/message_sync_activity Step 2 handoff: user selected sync first and authorized advancing Step 1 Option A. Description/checkpoint specifies private recent-activity priority with fairness, settled quietness, bounded automatic continuation and numeric request/response/admission limits. Whole-cycle 0.95 revises preserved 0.85 for clearer bounded key retrieval, server admission and invalidation obligations, same v1/A/original baseline/R1/P2 and exposed single Codex rater. Prior exact reference verification retained. Retirement/cap remain queued Step 1 proposals, not approved by this direction. No implementation, measured labor, runtime acceptance or accepted-count increment; await Approved Step 2.

2026-10-30 UTC — v3/message_sync_activity Step 3 handoff: Step 2 explicitly approved. Plan/checkpoint reaffirms whole-cycle 0.95, same v1/A/original baseline/R1/P2 and single exposed Codex rater; prior R1 hash verification retained. Eight original stage-work estimates 0.12/0.10/0.15/0.17/0.13/0.13/0.15/0.06, non-additive: admission/baseline, activity, bounded key/payload retrieval, priority/progress, deduplication, continuation, scale acceptance and closeout. Explicit compatibility/budget gates precede dependent browser work. Other two cycles remain queued Step 1 proposals; no implementation, runtime acceptance, measured labor or accepted-count increment. Await Approved Step 3; planning uncommitted.

2026-10-30 UTC — v3/message_sync_activity implementation compatibility checkpoint: Step 3 approved; planning b58d281c7, Stage 1 68167edd2 and Stage 2 f2c3a8a98 committed. Whole-cycle entry 0.95 reaffirmed; completed stage retrospectives 0.12/0.10, originals retained, not additive. Stage 3 incomplete: submitting identity is not proof of encrypted signer; experimental narrowing failed the new regression and was withdrawn. Proposed compatibility revision requires renewed Step 2/3 approval; no new-scope implementation. Current history tests 20/20 and existing real-key crypto check pass; no full-suite, deployment or final recovery/traffic acceptance. Stages 4–8 not started, no cycle retrospective or accepted-count increment; maintainer judgment pending. Same R1/P2 and single exposed Codex rater.

2026-10-30 UTC — v3/message_sync_activity revised Step 2 handoff: recovery without send restrictions, scope v2/A, same original baseline/R1/P2 and single exposed Codex rater. Whole-cycle 0.95 reaffirmed; original projections and stage estimates retained. User selected recorded-key-first recovery with bounded approved-key fallback and explicitly rejected blocking sends. Prior upgrade-required legacy proposal withdrawn from current recommendation, never approved; old-client compatibility remains a feasibility gate. Stages 1–2 remain committed, Stage 3 incomplete, later stages not started. Documentation-only revision; no new runtime tests, implementation, dependency, measured labor or accepted outcome. Await renewed Approved Step 2, then revised Step 3 approval.

2026-10-30 UTC — v3/message_sync_activity revised Step 3 handoff: plan/checkpoint. Revised Step 2 approved; whole-cycle 0.95 and original stage estimates reaffirmed, v2/A, same baseline/R1/P2 and exposed single Codex rater; all three frozen hashes reverified. Stage 3 now specifies first-key hint, bounded fallback and old-client checkpoint/timeout gate, with shared verification continuation in Stages 5–6 and signed mismatch/no-send-rejection acceptance in Stage 7. Stages 1–2 retained; no resumed implementation, runtime acceptance, measured work or accepted-count increment. Await Approved Step 3; revised planning remains uncommitted.

2026-10-31 UTC — v3/message_sync_activity local closeout: summary/checkpoint, acceptance. Eight stages locally complete; final application 733b180b0, documentation closeout in this commit. Whole-cycle projection 0.95 retained; separate retrospective scope 1.00, v2/A, original baseline/R1/P2, single exposed Codex rater; all frozen hashes reverified. Stage original/retrospective pairs 0.12/0.12, 0.10/0.10, 0.15/0.20, 0.17/0.20, 0.13/0.13, 0.13/0.16, 0.15/0.30 (revision 0.25 retained), 0.06/0.06 are non-additive. Natural recovery, bounded compatibility and idle traffic locally verified; 57 focused checks, four browser journey modes and seven store lifecycle checks pass. Earlier failures/withdrawn scope preserved. Full-suite, production replay and full previous-release rollback rehearsal not claimed. Zero dependencies; no merge/push/deployment or measured labor. Maintainer fit/acceptance pending; no accepted-count increment. Sibling retirement/cap proposals remain separate and unapproved.

Cycle v3/deployment_config

Status: Six stages locally implemented and verified; QDB host acceptance and maintainer fit/acceptance pending; standing enrollment P2. Scope: v1 / Option A (+ status reporting from C); baseline 4abda3dbd144370a3353781b29e8690e46d47d88; R1 / P2. Canonical checkpoint: Step 1 assessment, 2026-10-30T20:47:01Z. Intake 0.80 (before code inspection); Step 1 projection 0.80; alternatives B 0.95 / C 0.35, complete-cycle, not additive. Rater: Claude (claude-opus-5-5), single exposed rater; all three frozen R1 hashes verified. Extended estimates and debug enabled. No implementation, measured labor or accepted outcome. Records uncommitted.

2026-10-30 UTC Step 1 revision 1: user added per-checkout private file lookup to Option A; revision. Scope v1.1; projection 0.85 supersedes 0.80 (scope change). Same baseline/R1/P2/rater. Await Approved Step 1.

2026-10-30 UTC Step 2 handoff: Approved Step 1 (revised A) received; feature description/checkpoint. Whole-cycle 0.85 reaffirmed; scope v1.1, same baseline/R1/P2/rater. QDB host acceptance defined as an operator-run step, pending until run. Await Approved Step 2.

2026-10-30 UTC Step 3 handoff: Approved Step 2 received; plan/checkpoint. Whole-cycle 0.85 reaffirmed; six stage-work originals S1–S6/v1 0.10/0.15/0.15/0.15/0.10/0.10, not additive. Same v1.1/baseline/R1/P2/rater. Await Approved Step 3.

2026-10-30 UTC Step 4 entry: Approved Step 3 received; planning commit e51751cf on feat/deployment-config; entry checkpoint. Whole-cycle 0.85 reaffirmed; stage originals S1–S6 0.10/0.15/0.15/0.15/0.10/0.10 copied, not additive. Implementation from origin/main 2ee0d198; planning baseline unchanged. Same v1.1/R1/P2/rater (claude-opus-5-5). Baseline full suite 1732 run, 6 pre-existing failures recorded. No measured labor or accepted outcome.

2026-10-31 UTC Step 4 closeout: Stage 6 and closeout. Six of six stages complete; commits planning e51751cf, S1–S5 06f903e7/5536338c/6a464910/40fd290f/53b3f5a2, S6 38c99d35. Prospective 0.80 and 0.85 retained; separate retrospective cycle 0.85 by Claude (claude-fable-5-1), a different model from the prospective rater. Stage retrospectives 0.08/0.12/0.15/0.15/0.10/0.10, non-additive. Full suite 1743 run / 1734 passed / 9 failed: six identical baseline failures plus three load-induced timing failures that pass 24/24 rerun alone; no attributable regression. Pre-existing baseline failures unchanged. QDB host acceptance pending (operator checklist in runbook). One Stage 2 plan deviation with the same outcome, two Stage 6 documentation corrections; no new requests, splits or follow-up cycles. Maintainer comfortable-fit/acceptance pending; no accepted-outcome increment; no merge, push, upload or measured labor.

Cycle v3/compose_keyboard_fit

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/compose_keyboard_fitThree stages locally complete; iPhone SE acceptance, merge and maintainer fit pendingv1.1 / R1 / P20.20 intake; 0.20 Step 1 (Option A); 0.20 Step 2; 0.20 Step 3; 0.20 Step 4 entry; 0.20 retrospective; alternatives B 0.40 / C 0.50, not additiveIntake and Step 1 · Step 2 · Step 3 · Step 4Replaces forum-only v3/mobile_compose_keyboard (2026-10-31, no repository artifacts); maintainer fit/acceptance pending

2026-11-02T01:15Z standing P2 enrollment: /compose/thread on a phone keeps the body and Post visible with the keyboard open and moves tags below Post (forum thread thread-20261031051903-0e8e7df4). Baseline main 2a7d356f84dc5b613b46ea08e75be86f5ec42ca8. Intake recorded after source and forum inspection, including exposure to the forum's 0.40 projection for a heavier scope; no pristine intake. Claude (claude-fable-5-1) single exposed rater; all three frozen R1 hashes verified. Extended estimates and debug enabled. Theme overflow requests recorded as separate work. No implementation, measured labor or accepted outcome; records uncommitted.

2026-11-02T01:20Z Step 2 handoff: Approved Step 1 (Option A) received; feature description/checkpoint. Whole-cycle 0.20 reaffirmed; scope v1, same baseline/R1/P2, Claude (claude-fable-5-1) single exposed rater. Requirements: tools after Post in the full composer, compact body height and no reserved picker footprint on phones, first paint final, compact and reply composers unchanged; paned New Thread dialog receives the new order. Theme overflow and keyboard docking remain separate. No implementation, measured labor or accepted outcome; records uncommitted.

2026-11-02T01:25Z Step 2 revision 1: maintainer asked for the Title below the Post row; revision. Scope v1.1; 0.20 reaffirmed (same partial and styles, one more field reordered). Same baseline/R1/P2/rater. Not approval of Step 2; records uncommitted.

2026-11-02T01:30Z Step 3 handoff: Approved Step 2 received at scope v1.1; plan/checkpoint. Whole-cycle 0.20 reaffirmed; stage-work originals S1–S3/v1.1 0.07/0.08/0.05, not additive. Same baseline/R1/P2/rater. Three stages: full composer order, phone body height and footprint, device replay and closeout. No implementation, measured labor or accepted outcome; awaiting Approved Step 3, records uncommitted.

2026-11-02 UTC Step 4 entry and closeout: Approved Step 3 received; branch feat/compose-keyboard-fit from 2a7d356f8, planning 6e043cb6e, stages 439000c06 / e27587b9f / final stage commit with this ledger. Closeout. 0.20 reaffirmed at entry; 0.20 retrospective scope assessment; stage originals 0.07/0.08/0.05, retrospectives 0.07/0.10/0.05, not summed. Three of three stages complete: full composer order, phone body height without reserved footprint, records. Full suite 1768 run, 1760 passed; all eight failures reproduce on main. Browser checks Chromium only, 13 themes at 375 by 667 and 375 by 300. Real iPhone SE check, merge, deployment and maintainer fit pending; zero dependency delta; no measured labor or accepted-count increment.

2026-11-02 UTC merge acceptance for v3/compose_keyboard_fit: maintainer said "great job, please merge and push"; record. Current main integrated without conflicts; combined-tree smoke 159/162 (three long-standing), composers and 39-case phone fit pass in Chromium. Merged and pushed. Study comfortable-fit judgment, iPhone SE device check and production acceptance remain pending; scores and accepted-count unchanged.

Cycle v3/qdb_page_selection

Date: 2026-11-01 UTC; standing P2 enrollment; reference R1; scope v1/A; baseline 75b5e30eb40b16f6297f69d83214b4e4926499b2. Status: Locally complete; maintainer acceptance pending. Earlier checkpoints retained below. Canonical checkpoint: QDB bounded page selection. Projection: First recorded intake after exposure 0.80; Step 1 handoff 0.80 reaffirmed. All option estimates retained in the artifact, non-additive. Relationship: Separate follow-up to v3/application_capacity_study; no predecessor scope reset or duplicate accepted outcome. Host cycle reuses earlier shared-host delivery work rather than replacing it. Exposure: Codex single exposed rater; prior capacity campaign and current source inspection disclosed; pristine pre-inspection intake unavailable. Exact frozen hashes verified; debug/extended estimates enabled. Outcome: Await Approved Step 1 for this cycle. No implementation, host execution, commits, dependencies, measured labor, independent rating or accepted-count increment. Maintainer fit/acceptance pending.

2026-11-02T01:21:17Z: QDB Step 1 Option A approved explicitly; Step 2 requirements/checkpoint drafted. Scope v1/A, original baseline, R1/P2 and exposed rater retained; Step 2 projected total 0.80 reaffirmed, frozen hashes verified. Await Approved Step 2; uncommitted planning only, no implementation or accepted outcome. Sibling cycles remain Step 1.

2026-11-02T02:20:28Z: QDB Step 2 approved unchanged. Step 3 plan/checkpoint covers five stages through normal HTTP, upgrade recovery, capacity replay and shared-consumer verification. Scope v1/A, original baseline and R1/P2 retained; total 0.80 reaffirmed independently of stage-work estimates. Frozen hashes verified; single exposed rater. Await Approved Step 3; planning remains uncommitted, no implementation or accepted outcome.

2026-11-02 UTC: Step 3 approved and implementation completed on feature/qdb-page-selection. Step 4 closeout: entry projection 0.80 reaffirmed, retrospective cycle scope 0.80; S1–S5 original/retrospective stage values retained separately. R1/P2, scope v1/A, baseline and exposed-rater history unchanged. Ordinary HTTP capacity, schema recovery, shared consumers and rendered themes verified locally; four smoke failures reproduced on baseline, PHP 8.3/FastCGI not claimed. No measured labor, independent rating or accepted-count increment; maintainer acceptance pending. Sibling cycles remain Step 1.

2026-11-02 UTC: User authorized QDB merge/push. Integration with main 99522a99 advances the combined schema identity to 43, preserving message/Recent indexes; 70 focused tests and normal CLI/HTTP upgrade recovery passed. Original cycle snapshots and acceptance-count boundary remain unchanged; see the Step 4 merge-verification entry.

2026-11-01 UTC — v3/key_retirement Step 1 current-code review: canonical revision checkpoint. Reviewed main f82bdc3e9; Option A remains relevant. Scope v1/A clarified, original baseline/R1/P2 and exposed single Codex rater retained; exact frozen hashes reverified. Whole-cycle 0.95 and Option B 0.65 reaffirmed. Merged bounded recovery, session forwarding, signed-post entry and historical approval replay are explicit integration constraints. No implementation, runtime acceptance, measured labor or accepted-count increment; await Approved Step 1. Committed and pushed before approval at the session stop hook's request; no approval implied.

2026-11-01 UTC — v3/key_retirement Step 1 operator expansion: canonical v2/A checkpoint. User requested expansion to active root-approved operators; same-account path retained, ordinary member cross-account retirement excluded regardless of approval flag. Last-active-key protection applies to both paths, with replacement approval before retiring a lost final key. Whole-cycle projection 1.00 revises retained v1/A 0.95; Option B remains 0.65. Original baseline/R1/P2 and exposed single Codex rater retained. No implementation, runtime acceptance, measured labor or accepted-count increment; await Approved Step 1. Committed and pushed before approval at the session stop hook's request; no approval implied.

2026-11-01 UTC — v3/key_retirement Step 2 handoff: Step 1 v2/A explicitly approved. Description/checkpoint defines same-account/operator retirement, independent approval-flag permissions, last-active-key protection, replacement-first recovery and preserved historical signatures/grants/message transfers. Proposed policy excludes fingerprint reactivation in this slice. Whole-cycle 1.00 reaffirmed; same v2/A, original baseline/R1/P2 and exposed single Codex rater; frozen references verified this session. No implementation, runtime acceptance, measured labor or accepted-count increment. Await Approved Step 2; planning uncommitted.

2026-11-01 UTC — v3/key_retirement Step 3 handoff: Step 2 v2/A explicitly approved. Plan/checkpoint retains whole-cycle 1.00, original baseline/R1/P2 and exposed single Codex rater; three frozen R1 hashes reverified. Original S1–S8 stage-work estimates 0.15/0.16/0.17/0.20/0.15/0.16/0.15/0.12 are non-additive. Authority/historical-transfer feasibility precedes record/replay, active authorization, history recovery, signed API, shared UI, restore and closeout; failure returns to Step 2 before dependent implementation. No runtime acceptance, implementation, measured labor or accepted-count increment. Await Approved Step 3; planning uncommitted.

2026-11-01 UTC — v3/key_retirement Step 4 entry and Stage 1 gate: Step 3 explicitly approved; planning commit 15373adbb on feature/key-retirement precedes the summary. Entry projection 1.00 reaffirmed for approved v2/A; original baseline/R1/P2 and exposed single Codex rater retained. Real signed approval/rename/rebuild fixture confirms current same-name approved keys do not prove same-account authority; legacy acceptance context can be absent. Proposed Step 2 clarification requires evidence-backed membership or operator assistance; proposed v3/A projection pending scope decision. Baseline 33/33 and gate/history checks 2/2 passed. Stage 1 incomplete pending decision; S2–S8 not started; no retirement runtime implementation, stage retrospective, measured labor or accepted-count increment. Prior estimates retained.

2026-11-01 UTC — v3/key_retirement revised Steps 2–3: user selected rename-disabled public instances and explicitly approved Step 2. Step 2 v3/A supersedes the unselected broad association-evidence proposal; revised plan uses effective rename flag off plus unchanged bootstrap names and verified rename-history exclusions for member authority, preserving operator assistance and last-key protection. Whole-cycle 1.00 reaffirmed; original S1 0.15 retained, revised S1 whole-stage 0.20; S2–S8 unchanged. Same original baseline/R1/P2/exposed single rater; exact hashes verified. Step 3 reapproval pending; no retirement runtime implementation, new runtime acceptance, measured labor or accepted-count increment.

2026-11-02 UTC — v3/key_retirement local closeout: summary/checkpoint, acceptance. User approved revised Step 3 v3/A; eight stages locally complete. Original 0.95 and approved 1.00 projections retained; Stage 7 revised projection 1.05 and separate retrospective scope 1.05. Original baseline/R1/P2, exposed single Codex rater, exact frozen hashes verified. Original/retrospective S1–S8: 0.15/0.20, 0.16/0.16, 0.17/0.17, 0.20/0.20, 0.15/0.15, 0.16/0.16, 0.15/0.20, 0.12/0.12; S1/S7 revisions retained, scores non-additive. Real member/operator browser journeys, retired private history, canonical/private restore and concurrent acceptance passed. Full suite 1754/1763 before corrected approval-label regression; eight remaining failing tests reproduced on unchanged main. Over-1.00 fit discussion applies to future cycle sizing; required recovery was not dropped. Zero dependencies; no production, merge, measured labor or accepted-count increment. Maintainer comfortable-fit/acceptance pending; sibling drafts remain separate.

Cycle v3/app_sessions

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/app_sessionsSeven stages locally complete; iPhone check, merge and maintainer fit pendingv1 / R1 / P20.90 intake; 0.90 Step 1 (Option A); 0.90 Step 2; 0.95 Step 3; 0.95 Step 4 entry; 0.95 retrospective; alternatives B 0.80 / C 0.45, not additiveIntake and Step 1 · Step 2 · Step 3 · Step 4New cycle; follows the deferred alternative in session_reauthentication_reference; acceptance pending

2026-11-03T01:28:51Z standing P2 enrollment: replace PHP's built-in session management (todo.txt entry, 2026-11-02 failures). Baseline main e6493e2ff4869f8bf98e5f43b3f6388814742c26. Intake 0.90 recorded after reading the todo outline and request, before source inspection. Step 1 handoff 0.90 for Option A (app-owned SQLite sessions), reaffirmed after inspection. Claude (claude-opus-5-5) single exposed rater; all three frozen R1 hashes verified. Extended estimates and debug enabled. No implementation, measured labor or accepted outcome; records uncommitted.

2026-11-03 UTC Step 1 revision 1: user asked for an inventory of existing PHP-session workarounds; inventory. Server-side workarounds fold into Option A; client simplifications deferred. 0.90 reaffirmed, scope v1 (new understanding), same baseline/R1/P2/rater. Await Approved Step 1; records uncommitted.

2026-11-03T02:08:04Z Step 2 handoff: Approved Step 1 (Option A) received; feature description/checkpoint. Whole-cycle 0.90 reaffirmed, scope v1, same baseline/R1/P2/rater; R1 hashes re-verified. Real iPhone Safari check is an acceptance item. Await Approved Step 2; records uncommitted.

2026-11-03 UTC Step 3 handoff: Approved Step 2 received unchanged; plan/checkpoint. Whole-cycle 0.95, revised from 0.90 (new understanding, same scope v1: behavior-neutral test pre-pass and TLS replay harness). Stage-work originals S1–S7 0.15/0.10/0.10/0.25/0.07/0.15/0.08, not additive. Same baseline/R1/P2/rater. Await Approved Step 3; records uncommitted.

2026-11-03 UTC Step 4 entry and closeout: Approved Step 3 received; branch feat/app-sessions from e6493e2f, planning eafa09b5, stages 435d1a61 / 414a2bd6 / 8959db42 / 9c1b9ad0 / 78ed137d / eebd9fd3 / final stage commit with this ledger. Closeout. 0.95 reaffirmed at entry; 0.95 retrospective scope assessment; stage originals 0.15/0.10/0.10/0.25/0.07/0.15/0.08, retrospectives 0.12/0.10/0.10/0.25/0.05/0.15/0.08, not summed. Seven of seven stages complete. Final full suite 1839 run, 1824 passed; all 15 failures reproduce on main. http/https Chrome replay 7/7 (6/7 fail on main with the reported errors). One plan deviation (Stage 4 not split), no new requests or splits. Real iPhone Safari check, merge, deployment and maintainer fit pending; zero dependency delta; R1 hashes re-verified; no measured labor or accepted-count increment.

2026-11-03 UTC merge for review of v3/app_sessions: user authorized push and pull request; main fd4d0e02 (incl. key retirement) merged into feat/app-sessions without rebasing; record. Sign-in keeps the retired-key check; two retirement tests adapted to app-owned sessions. Focused suites and browser checks pass; full suite pending at push. Scores and accepted-count unchanged.

Cycle v3/rebuild_memory_bound

Date: 2026-11-01 UTC; standing P2 enrollment; reference R1; scope v1/A; baseline 75b5e30eb40b16f6297f69d83214b4e4926499b2. Status: Step 1 drafted for review; planning only, uncommitted. Canonical checkpoint: Bounded post-heavy rebuild. Projection: First recorded intake after exposure 1.00; Step 1 handoff 1.00 reaffirmed. All option estimates retained in the artifact, non-additive. Relationship: Separate follow-up to v3/application_capacity_study; no predecessor scope reset or duplicate accepted outcome. Host cycle reuses earlier shared-host delivery work rather than replacing it. Exposure: Codex single exposed rater; prior capacity campaign and current source inspection disclosed; pristine pre-inspection intake unavailable. Exact frozen hashes verified; debug/extended estimates enabled. Outcome: Await Approved Step 1 for this cycle. No implementation, host execution, commits, dependencies, measured labor, independent rating or accepted-count increment. Maintainer fit/acceptance pending.

Cycle v3/repository_import_compatibility

Date: 2026-11-01 UTC; standing P2 enrollment; reference R1; scope v1/A; baseline 75b5e30eb40b16f6297f69d83214b4e4926499b2. Status: Step 1 drafted for review; planning only, uncommitted. Canonical checkpoint: Repository archive import compatibility. Projection: First recorded intake after exposure 0.45; Step 1 handoff 0.45 reaffirmed. All option estimates retained in the artifact, non-additive. Relationship: Separate follow-up to v3/application_capacity_study; no predecessor scope reset or duplicate accepted outcome. Host cycle reuses earlier shared-host delivery work rather than replacing it. Exposure: Codex single exposed rater; prior capacity campaign and current source inspection disclosed; pristine pre-inspection intake unavailable. Exact frozen hashes verified; debug/extended estimates enabled. Outcome: Await Approved Step 1 for this cycle. No implementation, host execution, commits, dependencies, measured labor, independent rating or accepted-count increment. Maintainer fit/acceptance pending.

Cycle v3/php83_host_verification

Date: 2026-11-01 UTC; standing P2 enrollment; reference R1; scope v1/B; baseline 75b5e30eb40b16f6297f69d83214b4e4926499b2. Status: Step 1 drafted for review; planning only, uncommitted. Canonical checkpoint: PHP 8.3 and FastCGI host verification. Projection: First recorded intake after exposure 0.65; Step 1 handoff 0.65 reaffirmed. All option estimates retained in the artifact, non-additive. Relationship: Separate follow-up to v3/application_capacity_study; no predecessor scope reset or duplicate accepted outcome. Host cycle reuses earlier shared-host delivery work rather than replacing it. Exposure: Codex single exposed rater; prior capacity campaign and current source inspection disclosed; pristine pre-inspection intake unavailable. Exact frozen hashes verified; debug/extended estimates enabled. Outcome: Await Approved Step 1 for this cycle. No implementation, host execution, commits, dependencies, measured labor, independent rating or accepted-count increment. Maintainer fit/acceptance pending.

Cycle v3/reply_title_directive

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/reply_title_directiveLocally complete; deployment and maintainer acceptance pendingv2 / R1 / P20.85 (retrospective 0.85)Step 1; Step 2; Step 3; Step 4 closeoutNew cycle from PF-20261103-F01; acceptance pending

2026-11-03T05:19:48Z: standing P2 enrollment for retitling a thread through a title: reply line with authority, plus a visible on-thread signals layer for likes, flags and title changes. Baseline e6493e2ff4869f8bf98e5f43b3f6388814742c26; Claude Code single exposed rater (model claude-fable-5-1); all three R1 hashes verified; extended estimates enabled. No pristine intake: source inspection of the existing thread-subject record family, hashtag labels and reaction templates preceded rating. Step 1 handoff projection 0.80 for recommended Option B; alternatives A 0.45, B 0.80, C 1.10, non-additive. No implementation, measured effort, approval or accepted outcome; planning and this ledger entry remain uncommitted.

2026-11-03T05:29:44Z: Step 1 revision. User chose Option B with two feature flags (FORUM_TITLE_DIRECTIVE_ENABLED default on; FORUM_TITLE_DIRECTIVE_APPROVED_MEMBERS default off, selecting author/operator versus any approved member), unauthorized directives out of scope with a recorded follow-up, immediate retitles and the proposed signals copy. Revised direction. Scope v2 projected 0.85, scope change not new understanding; v1 0.80 and option alternatives retained. Same baseline/R1/P2/exposed rater. No approval yet; nothing committed.

2026-11-03T05:34:01Z: Step 2 handoff. Step 1 explicitly approved ("reading: confirmed. approved step 1"). Feature description/checkpoint defines authorized title: replies, latest-authored-wins precedence with reply provenance and withdrawal, a server-rendered signals line on all card variants, two feature flags and the missing record spec. Scope v2 0.85 reaffirmed; same baseline/R1/P2/exposed rater. No implementation, measured effort or accepted outcome; await Approved Step 2; records uncommitted.

2026-11-03T08:53:36Z: Step 3 handoff. Step 2 explicitly approved. Eight-stage plan/checkpoint: record provenance and spec, two flags, directive write with authority, read-model precedence with schema 43→44, signal eligibility and actor query, signals UI, withdrawal/deletion/shared consumers, known-user replay and closeout. Scope v2 0.85 reaffirmed; stage-work originals 0.08/0.08/0.15/0.15/0.12/0.20/0.12/0.12, non-additive. Pre-plan check: one local thread-subject record, system-authored. Same baseline/R1/P2/exposed rater. No implementation or accepted outcome; await Approved Step 3; records uncommitted.

2026-11-03T18:34:36Z: Step 4 closeout. Step 3 explicitly approved ("approved step 3"); branch feat/reply-title-directive, planning commit 671715b1, eight stage commits. Entry, stages and closeout. Entry projection 0.85 reaffirmed; retrospective scope assessment 0.85; stage-work originals 0.08/0.08/0.15/0.15/0.12/0.20/0.12/0.12 and retrospectives 0.06/0.08/0.18/0.15/0.12/0.22/0.08/0.15, non-additive. Delivered: authored title directive with authority and two flags, schema 44 precedence and eligibility, signals line on all card variants, withdrawal on retraction/deletion, consumer coverage, known-user replay in Chromium. Full suite 1846 run with five reproduced baseline failures; two cycle findings fixed and re-verified. Production acceptance, Firefox/WebKit, physical phone and maintainer fit/acceptance pending; no measured effort, independent rating or accepted-count increment. Same stable cycle across checkouts.

2026-11-03T19:37:24Z: v3/reply_title_directive merge verification. User authorized merge and push; merged origin/main (schema integration to 46) as 699ebd26, fast-forwarded and pushed main. Merged-tree checks: full suite 1892 run, five known baseline failures; four concurrency artifacts pass alone. Scope, estimates and pending maintainer acceptance unchanged; no accepted-count increment.

Cycle v3/reply_title_live_update

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/reply_title_live_updateOne-shot implemented locally; merge and maintainer acceptance pendingv1 / R1 / P20.15 (retrospective 0.10)One-shot recordFollow-up to v3/reply_title_directive; acceptance pending

2026-11-03T19:07:37Z: standing P2 enrollment, one-shot mode, user authorization "go ahead please" after an estimate of about 0.15. Intake 0.15 (exposure: predecessor code read before rating, disclosed), execution entry 0.15 reaffirmed, retrospective 0.10 after the client-only simplification (root card synced from the already-fetched render document; no server or PHP change). Browser verification in Chromium; Forte pane out of path. Baseline main after the predecessor merge; branch feat/reply-title-live-update. No measured effort, independent rating or accepted-count increment; maintainer fit pending.

Stable cycle IDStatusScope / reference / protocolProjected totalCanonical checkpointsParent / acceptance
v3/board_thread_searchOne-shot technically complete; maintainer acceptance pendingv1 / R1 / P20.30 (intake 0.25; retrospective 0.30)One-shot recordItem 1 of the board search checklist; acceptance pending

2026-11-03: standing P2 enrollment of a one-shot cycle for zenmemes thread-only search. Baseline 446aa34c7fcc4d8691e9dcc0af9c8b71a4b98175. Claude (claude-opus-5-5) is the single exposed rater, and R1 hashes were verified. The intake of 0.25 followed source inspection, so no pristine intake exists. Execution entry revised it to 0.30 from new understanding: the read-model version contract and the canonical keyset pagination. Closeout reaffirmed 0.30, with a retrospective of 0.30. No measured labor, independent rating or accepted-count increment.